16 Sept 2026drilling result▲ GoodMajor
Foroko, 3km from the Kobada plant, returns very high grades, including 28m at 8.86g/t gold with 3m at 61.2g/t. The results feed the resource update, now targeted for early October, which could add ounces and an alternative oxide feed source.
Final northern infill results from Kobada include 44m at 3.12g/t and 17m at 3.95g/t gold. These were the assays held up at the Bamako lab, so the resource update has now started, targeted for end Q3 2026. Ore reserve and mine plan update follows in Q4.
Kobada construction is reported on schedule: process plant works have started, the water dam is done and the airstrip and camp are nearing completion. First gold is still targeted for Q3 2027. The first gold stream drawdown is expected by end-August, and the MRE update is due by end of Q3.
Infill RC drilling in the northern part of the Kobada resource returns high-grade intercepts, including 72m at 2.27g/t gold and 53m at 3.67g/t. Assay delays at the Bamako laboratory leave many results pending. The resource update is now scheduled to start in Q3 2026, later than the earlier 1H 2026 plan.
RC drilling at Kobada South defines oxide mineralisation over 1.6km of strike within 1km of the planned plant site, including 19m at 1.02g/t and 1m at 39.7g/t. Zone was mostly Inferred; results are expected to feed the resource update.
Toubani launches up to 100,000m of drilling in 2026, its largest yet, and reports new high-grade results outside the 2.2Moz resource, including 1m at 116g/t gold and 7m at 9.43g/t. A resource update is planned for first half 2026.
First 2025 drill results at Kobada show mineralisation outside the 2.2Moz resource, including 50.8m at 0.97g/t gold between 120m and 250m depth, plus RC oxide intercepts such as 1m at 21.7g/t. Supports resource growth; more results due in coming weeks.
A 5,000m diamond drilling program starts at Kobada, testing mineralisation below the 2.2Moz resource, where drilling averages only 110m depth. It also gathers geotechnical data, with RC drilling planned later. Delivers the long-pending deep drilling; FID targeted by end of 2025.
The long-awaited DFS shows a post-tax NPV8% of US$635m, 58% IRR, US$216m upfront capital and AISC of US$1,004/oz at US$2,200/oz gold. Maiden Ore Reserve is 1.56Moz, giving 162koz a year over 9 years, up from 100koz in 2021. Cash is A$10.5m.
2024 resource rises to 2.2Moz (78Mt at 0.88g/t). Indicated ounces up 30% to 2.0Moz, oxide Indicated up 44% to 1.4Moz, and over 80% of targeted oxide Inferred converted. It delivers the resource update; the DFS update is due in September.
Final assays from the 2024 program, including 1m at 100g/t and 13m at 6.23g/t. Entech has started updating the August 2023 resource, aiming to convert Inferred to Indicated. DFS delivery is still due later in 2024.
Further results from 24 holes, including 57m at 2.48g/t and 24m at 5.75g/t. Drilling is complete at 120 holes (11,785m). Final assays are awaited, then the resource update planned for 2Q 2024.
More infill results from 11 holes, led by 19m at 20.6g/t from 105m including 2m at 178g/t, and 48m at 2.84g/t. 114 holes (10,947m) are drilled; drilling ends in days, with the resource update still planned for 2Q 2024.
Further infill results from 13 more holes, including 27m at 1.23g/t and 21m at 2.97g/t, and 41m at 1.45g/t. 91 holes (9,309m) are complete; drilling ends mid April, with a resource update still planned for 2Q 2024.
First results from the 2024 infill program: 71m at 1.86g/t from 79m, including 15m at 4.04g/t, plus 7m at 7.67g/t, from 30 holes. Results feed a resource update planned for 2Q 2024. This is the first return on the drilling funded by the 2023 placement.
Target Drilling engaged for an up to 10,000m RC infill program at Kobada, starting early February and finishing by end Q1 2024. It aims to convert near-surface Inferred oxide to Indicated and feed a 2024 resource update, following the DFS Update work.
Independent review by Entech lowers the Kobada resource to 2.4Moz (87Mt at 0.86g/t) from 3.1Moz in the 2021 estimate, with 1.5Moz shallow oxide and 1.53Moz Indicated. Kobada West and Gosso are not included. Drilling to start this quarter.
Phase 1 2023 drilling complete: 105 holes, 14,122m, extending drill-defined mineralisation from 5km to 11km, with all targets hit (incl. Kobada West and Kobada East). About 40km of 50km+ shear zones remain untested. Further drilling planned for second half 2023.
Kobada West discovery: first-ever drilling found shallow oxide gold over 600m of strike, less than 1km from the Kobada Main deposit (best 9m at 1.72g/t, 1m at 11.3g/t). All five 2023 targets hit; drilled strike extent rises from 5km to 11km. Resolves the pending Kobada West results.
Maiden RC drilling confirms the Kobada East discovery, first found by auger sampling in 2022: shallow oxide mineralisation over 400m of strike (best 6m at 0.85g/t). Four of five planned targets have now hit new mineralisation; Kobada West results are expected shortly.
Drilling shows mineralisation now over 2km north of previous drilling at Kobada North, and extends Gosso strike from 1,600m to 2,100m (best 1m at 5.78g/t). Kobada North 2 gave only thin results (1m at 8.51g/t). Program raised by 3,000m to 13,750m.
First results from the 10,750m program extend Kobada mineralisation by almost 1km north and south of the main deposit (3.1Moz resource). Best north result is 9m at 1.32g/t and 14m at 1.02g/t. Mineralisation remains open; Kobada North 2 results are pending and the rig is now drilling Gosso.
A 10,750 metre drill program has started at Kobada, targeting strike extensions beyond the existing 3.1 million ounce resource, of which 1.7 million ounces is Measured and Indicated. Lead manager Canaccord was paid A$360,000 (6%) and holds 2,972,383 options.