The story so far
The events that changed the company's story, in plain English, each written against everything known about the company at the time. The dot shows whether it was good, bad or neutral for shareholders.
2026
- 16 Sept
Foroko, 3km from the Kobada plant, returns very high grades, including 28m at 8.86g/t gold with 3m at 61.2g/t. The results feed the resource update, now targeted for early October, which could add ounces and an alternative oxide feed source.
drilling result
- 24 Aug
The first US$25m under the US$160m Eagle Eye gold stream is received after remaining conditions were met. This delivers the planned Q3 drawdown, with regular drawdowns to follow through construction.
debt financing
- 12 Aug
Mark Somlyay is appointed CFO, replacing Robert Ierace. Kerry Griffin becomes Operations Director and Riaan Lombard General Manager of Kobada. This builds out the operating team as the project moves from construction toward production.
director officer appointment
- 5 Aug
The retail offer closes, completing the A$70m entitlement offer at A$0.30. About 60.96M retail shares were not taken up and were placed under the shortfall policy, including to underwriter Canaccord. New shares are due to be allotted 10 August and trade 11 August.
capital raising announcement
- 15 July
The institutional part of the entitlement offer raises about A$52m at A$0.30 a share, issuing about 172M shares at a 14.3% discount to the last price. A retail offer of up to about A$18m follows, closing 3 August. Eagle Eye (~34.2%) and Helikon (~19.9%) take up their full entitlements.
capital raising announcement
- 13 July
Toubani signs binding documents for a US$160m (A$232m) Eagle Eye gold stream and a fully underwritten A$70m entitlement offer. The Coris senior debt is not proceeding 'at this time'; a term sheet for up to US$40m from an AFG Bank-led syndicate replaces it. Capex is over 60% committed.
debt financing
- 1 July
Corica Mining Services is appointed Kobada mining contractor on an initial five-year term, with long-form documentation still being finalised and equipment orders placed. This resolves the open mining contractor selection. The announcement gives conflicting dates: highlights say mobilisation Q4 2026 and first ore Q2 2027, the body says Q4 2027 and Q1 2027.
contract award
- 29 June
Toubani agrees to acquire 19.9% of CSE-listed Avanti Gold by issuing 72.9M Toubani shares and 36.45M options at A$0.60 for 44.5M Avanti shares. Avanti owns 73.5% of the Misisi project in the DRC, with a foreign-standard 3.1Moz inferred estimate. Closing is due by 20 July 2026.
asset acquisition disposition
- 23 June
Infill RC drilling in the northern part of the Kobada resource returns high-grade intercepts, including 72m at 2.27g/t gold and 53m at 3.67g/t. Assay delays at the Bamako laboratory leave many results pending. The resource update is now scheduled to start in Q3 2026, later than the earlier 1H 2026 plan.
drilling result
- 15 May
Toubani signs a binding commitment letter with a Coris-led lender group for the US$73.3m senior facility, subject to conditions including Malian Government approvals. This firms up the January non-binding term sheet; the mezzanine and EEA gold stream documentation are still being finalised.
debt financing
- 9 Mar
Board approves a positive final investment decision for Kobada and construction has formally started. Over 36% of project capital cost is committed, and first gold is targeted for Q3 2027. This meets the FID goal; funding documentation is nearing completion, not finished.
other
- 23 Feb
Toubani receives the Kobada environmental permit, approving the ESIA and resettlement plan, and says it now holds all key construction permits. Resettlement has started. This resolves the open environmental permit thread.
regulatory community update
- 30 Jan
Toubani signs a binding agreement with Mali, with the State's interest capped at 35% under the 2023 Mining Code. The mining licence transfer to Mines de Kobada SA was approved on 28 January. This resolves the pending Mali implementation and licence-transfer thread.
material agreement
- 29 Jan
Toubani launches up to 100,000m of drilling in 2026, its largest yet, and reports new high-grade results outside the 2.2Moz resource, including 1m at 116g/t gold and 7m at 9.43g/t. A resource update is planned for first half 2026.
drilling result
- 28 Jan
Toubani receives a credit-approved, non-binding term sheet from Coris Bank for a US$73.3m senior facility at 10% and a US$10.2m mezzanine facility. They would replace 50% of the EEA gold stream, leaving US$80m for a 5.55% stream. Documentation is still to be finalised.
debt financing
2025
- 30 Oct
Ausenco is appointed EPCM engineer for the Kobada processing plant, covering detailed engineering, procurement, construction management and commissioning. This resolves the EPCM tender and moves the project towards a final investment decision. No contract value is given.
contract award
- 16 Oct
Mali approves the Kobada ESIA, with minor modification requests; an updated environmental permit is due shortly. This meets the September-quarter ESIA expectation and clears a key permitting step ahead of on-site works later this year.
regulatory community update
- 10 Oct
Toubani announces an A$395m funding package for Kobada: A$242m (US$160m) 11.1% gold stream with EEA, A$26m from EEA option exercise, and A$125m placement at A$0.40. EEA would hold about 35%. Targets FID in 2025 and first production by Q3 2027.
capital raising announcement
- 30 Sept
First 2025 drill results at Kobada show mineralisation outside the 2.2Moz resource, including 50.8m at 0.97g/t gold between 120m and 250m depth, plus RC oxide intercepts such as 1m at 21.7g/t. Supports resource growth; more results due in coming weeks.
drilling result
- 16 June
A 5,000m diamond drilling program starts at Kobada, testing mineralisation below the 2.2Moz resource, where drilling averages only 110m depth. It also gathers geotechnical data, with RC drilling planned later. Delivers the long-pending deep drilling; FID targeted by end of 2025.
drilling spud
- 30 Apr
Toubani raises A$29m at A$0.24 a share (about 120.8M shares, 9.4% discount to last close) in two tranches, with a free option per share at A$0.336. A2MP, backed by Afreximbank, puts in about A$15.2m for 18%, and offers a non-binding minimum US$160m debt facility letter.
capital raising announcement
- 31 Mar
Toubani agrees with Mali to develop Kobada under the 2023 mining code: Toubani 65%, State 35%, with a 2.0% royalty reduction. This resolves the long-open Mali convention thread. Updated DFS NPV8% is US$500m at US$2,200/oz, down from US$635m; FID targeted later this year.
material agreement
2024
- 26 Nov
Toubani appoints Endeavour Financial to advise on project financing for Kobada, after interest from potential lenders post-DFS. ESIA update has started and drilling to begin next month. Talks with Mali continue; the company says it has no tax disputes there.
debt financing
- 31 Oct
The long-awaited DFS shows a post-tax NPV8% of US$635m, 58% IRR, US$216m upfront capital and AISC of US$1,004/oz at US$2,200/oz gold. Maiden Ore Reserve is 1.56Moz, giving 162koz a year over 9 years, up from 100koz in 2021. Cash is A$10.5m.
resource reserve update
- 21 Aug
Raised A$10.0m via a two-tranche placement of about 58.8M shares at A$0.17, a 5.6% discount to last close. Paradice would reach 9.9%. Tranche 2 (A$2.8m, including A$170k from directors) needs approval at an October general meeting. Funds the DFS and resource growth.
capital raising announcement
- 2 July
2024 resource rises to 2.2Moz (78Mt at 0.88g/t). Indicated ounces up 30% to 2.0Moz, oxide Indicated up 44% to 1.4Moz, and over 80% of targeted oxide Inferred converted. It delivers the resource update; the DFS update is due in September.
resource reserve update
- 27 May
Matt Wilcox, former Tietto Minerals CEO, joins as non-executive director. Scott Perry becomes chair, replacing Callow, who stays as a director. Marc Rowley, Dave Clark and Dhanu Anandarasa join the DFS owners team. The board is now five.
director officer appointment
- 26 Apr
Raised A$3.85m via a placement of about 33.5m shares at A$0.115, a 14.8% discount to the last close. Director Kestell adds A$150,000 subject to approval, taking the total to A$4.0m. Funds the drilling, resource update and DFS; cash was about A$1m at 31 March.
capital raising announcement
- 22 Apr
More infill results from 11 holes, led by 19m at 20.6g/t from 105m including 2m at 178g/t, and 48m at 2.84g/t. 114 holes (10,947m) are drilled; drilling ends in days, with the resource update still planned for 2Q 2024.
drilling result
- 25 Mar
First results from the 2024 infill program: 71m at 1.86g/t from 79m, including 15m at 4.04g/t, plus 7m at 7.67g/t, from 30 holes. Results feed a resource update planned for 2Q 2024. This is the first return on the drilling funded by the 2023 placement.
drilling result
- 12 Jan
Toubani was registered as an Australian company from 8 January 2024 and renamed Toubani Resources Limited, as approved at the 1 September 2023 AGM. CDIs are cancelled and replaced by ordinary shares 1:1 held directly. Board says it may cut costs.
other
2023
- 5 Sept
Lycopodium appointed lead engineer for the Kobada DFS Update, which will test higher processing rates than the 2021 plan of 3.0Mtpa, starting with an oxide phase. Completion now targeted 1Q 2024, versus end-2023 previously stated.
contract award
- 30 Aug
Placement of 31,666,667 CDIs at A$0.12 raises A$3.8m, a 14.3% discount to last close. Tranche 1 is A$1.84m; Tranche 2 needs shareholder approval and includes A$350,000 from directors. Funds go to the DFS update and drilling. Follows the cash fall to US$669k at June.
capital raising announcement
- 18 Aug
Independent review by Entech lowers the Kobada resource to 2.4Moz (87Mt at 0.86g/t) from 3.1Moz in the 2021 estimate, with 1.5Moz shallow oxide and 1.53Moz Indicated. Kobada West and Gosso are not included. Drilling to start this quarter.
resource reserve update
- 19 July
Phase 1 2023 drilling complete: 105 holes, 14,122m, extending drill-defined mineralisation from 5km to 11km, with all targets hit (incl. Kobada West and Kobada East). About 40km of 50km+ shear zones remain untested. Further drilling planned for second half 2023.
drilling result
- 11 July
Board approves a Definitive Feasibility Study update on the 3.1Moz Kobada project, assessing higher processing rates (the 2021 DFS assumed 3.0Mtpa) with an oxide-first phase. Starts July 2023, completion targeted by end-2023, plus drilling to upgrade Inferred resources. Shifts strategy toward a larger project.
other
- 17 May
Kobada West discovery: first-ever drilling found shallow oxide gold over 600m of strike, less than 1km from the Kobada Main deposit (best 9m at 1.72g/t, 1m at 11.3g/t). All five 2023 targets hit; drilled strike extent rises from 5km to 11km. Resolves the pending Kobada West results.
drilling result
- 15 May
Former Centerra Gold CEO Scott Perry and ex-Tietto Minerals director Mark Strizek join as non-executive directors; Jan-Erik Back and Doug Jendry retire. Callow becomes non-executive chair on 1 June. Options (A$0.35) for new directors need AGM approval.
director officer appointment
- 26 Apr
Maiden RC drilling confirms the Kobada East discovery, first found by auger sampling in 2022: shallow oxide mineralisation over 400m of strike (best 6m at 0.85g/t). Four of five planned targets have now hit new mineralisation; Kobada West results are expected shortly.
drilling result
- 20 Apr
Toubani has applied to voluntarily delist its common shares from the TSX Venture Exchange, citing better liquidity and lower administrative costs from a single ASX listing. Subject to TSX-V approval; TSX-V holders will need to convert to CDIs to trade on ASX.
listing compliance notice
- 11 Apr
Drilling shows mineralisation now over 2km north of previous drilling at Kobada North, and extends Gosso strike from 1,600m to 2,100m (best 1m at 5.78g/t). Kobada North 2 gave only thin results (1m at 8.51g/t). Program raised by 3,000m to 13,750m.
drilling result
- 8 Mar
First results from the 10,750m program extend Kobada mineralisation by almost 1km north and south of the main deposit (3.1Moz resource). Best north result is 9m at 1.32g/t and 14m at 1.02g/t. Mineralisation remains open; Kobada North 2 results are pending and the rig is now drilling Gosso.
drilling result
2022
- 15 Dec
Phil Russo, formerly of Barrick, Dacian and Perseus, becomes CEO and executive director from 9 January 2023. Danny Callow moves to Executive Chairman until mid-2023, then Non-Executive Chairman; Jan-Erik Back becomes a non-executive director. This is a leadership change after the listing.
director officer appointment
- 12 Dec
A 10,750 metre drill program has started at Kobada, targeting strike extensions beyond the existing 3.1 million ounce resource, of which 1.7 million ounces is Measured and Indicated. Lead manager Canaccord was paid A$360,000 (6%) and holds 2,972,383 options.
drilling spud
- 2 Dec
Etasi & Co Drilling, a Mali-based contractor and successor to AMCO, was awarded the contract for the 2022/23 reverse circulation drilling at Kobada, testing six targets. This puts IPO funds toward growing the 3.1 million ounce resource. Contract value not disclosed.
contract award
- 24 Nov
Toubani Resources was admitted to the ASX on 24 November 2022, with CDI quotation starting 28 November. Its IPO raised $6,000,000 by issuing 30,000,000 shares at $0.20 each. The company is incorporated in Ontario and focused on mineral exploration.
capital raising announcement