30 Apr 2025regulatory community update▲ Good
Pre-construction work has started: the old plant is being decommissioned and final design and engineering packages are complete. Construction tender is done and contract drafting is under way. Execution contracts are forecast for Q2 2025, with bulk earthworks starting upon project approval.
Amended release of the Pensworth option exercise (30m shares at 12c). Only the use of funds changed, now yellow equipment purchase, staff training and site preparation rather than mine design and plant engineering. Amounts are unchanged.
28 Mar 2025capital raising announcement▲ GoodMajor
Pensworth Holdings, a Hong Kong investor, exercised 30 million options at 12c, giving Theta A$3.6m. The funds are for mine design and plant engineering work. A modest cash injection while the main project funding is still outstanding.
Half-year report to 31 December 2024 says the plant footprint and MR83 are fully permitted and final plant design is done, with Theta 'ready to mine post-funding'. An updated feasibility study including surface gold is expected in May. Financial figures are not visible.
Chairman Bill Guy's presentation for the February 2025 Cape Town Indaba conference. The visible text repeats known figures: 6.1Moz resource and the 2022 feasibility study (US$324m NPV, US$77m capital). No new information is visible.
After shareholders approved it on 28 October, Theta issued 46,276,113 shares at 13c plus 23,138,057 options for the US$4m (about A$6.02m) June placement. This completes that raise and resolves the approval thread.
What it means for a shareholder
46.3m new shares at $0.130 to raise about $6.0m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
The US$2m placement completed: 22,475,136 shares at 13c plus 11,237,568 options issued on 2 October, about A$2.93m, using existing placement capacity with no shareholder vote. This completes the extra raise flagged on 16 September.
What it means for a shareholder
22.5m new shares at $0.130 to raise about $2.9m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
2024 annual report restates known milestones: MR83 permits, PowerChina as preferred EPC partner, 174,000oz surface gold and the 2Invest bond redemption. Next year's aim is to finalise funding and start construction. Financial statements are not visible in the text.
Ruihua Tranche 1 (US$6m, about A$8.99m at 13c) has settled, resolving the delay. A further US$2m placement was secured, and the A$6m 2Invest secured bonds were fully redeemed, freeing project security for future financing. Tranche 2 (US$4m) needs shareholder approval.
Lab tests found gold is recoverable from historic rock dumps (about 95% recovery) but only 58.95% from the main tailings dam sample. This resolves the awaited recovery results; 174,000oz of surface gold may support early cashflow, which the company is still only considering.
26 June 2024capital raising announcement▲ GoodMajor
Theta raised a further US$4m (about A$6.02m) at 13c per share, a 10.3% discount to last close, on top of the May US$10m. About 46.3m shares plus attaching options, subject to shareholder approval. Funds are received; Golden Asian Investment Group was lead manager.
What it means for a shareholder
46.3m new shares at about US$0.0864 to raise about US$4.0m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Tranche 1 of the Ruihua placement did not settle on 5 June as planned, awaiting Chinese outbound-investment approval. Completion is now expected by end of June. Ruihua reconfirmed its US$10m commitment. This is a delay to the May raise.
Drilling on the TGME Main tailings dam confirmed expected gold grades: 46 of 80 samples at or above 1g/t, including 8 at 2 to 4.11g/t. Metallurgical recovery results are still awaited. PowerChina is said to be satisfied with the grades, supporting its due diligence.
Theta has firm commitments for up to US$10m (about A$15.2m) from existing 6.49% holder Hong Kong Ruihua, at 13c per share, a 16.1% discount to last close. About 116.9m shares plus one free option per two shares. Tranche 1 (US$6m) depends on Chinese outbound-investment approval.
PowerChina's contractor finished 407m of drilling on TGME tailings dams for metallurgical testing. Tailings hold about 140,000oz gold (141,000oz total JORC). Theta is considering adding tailings recovery to bring forward early cashflow ahead of underground development. This follows the February early-cashflow idea.
Half-year report to 31 December 2023 repeats known events: the Frankfort bulk sample was mined safely, MR83 is now permitted, and the PowerChina MOU (about US$30m) was signed after period end. Auditor is shown as Hall Chadwick, resolving the earlier unknown. Financial figures not visible in the text.
Theta says Mining Right 83 (Beta, CDM and Frankfort mines) is now fully permitted. The September 2023 environmental objection was rejected, with quarterly water testing imposed. This resolves the open MR83 appeal and meets a condition for project financing; funding is still to be finalised.
Theta replied to ASX's 9 February price query, saying it held unannounced information: talks on an EPC MOU with PowerChina subsidiary Yellow River Co. It sought a halt as the MOU was unfinished. Funding for upfront EPC payments still under discussion, update expected by Q2 2024.
Theta signed a non-binding MOU naming PowerChina subsidiary Yellow River Co. as preferred builder of the Stage One TGME plant and tailings facility, estimated at US$30m on a cost basis. Most is payable after completion; the formal contract is targeted for Q2 2024 and depends on securing upfront funding.
ASX notice that Theta's suspension would lift immediately after the company's TGME Gold Mine Project announcement. Administrative only, no new substance.
At Theta's request, its shares were suspended from 13 February pending an announcement on the TGME Gold Mine Project, after a trading halt from 9 February. The company asked for trading to resume by 14 February.
ASX paused trading in Theta shares pending a further announcement. The notice gives no reason. It is the first step of the halt that preceded the 14 February PowerChina announcement.
Chairman Bill Guy's presentation at the Indaba mining conference in Cape Town repeats the feasibility study (1.08Moz recovered over 12.9 years) and the 6.1Moz resource. No new information is visible in the text.
Theta issued 4,464,831 shares at 10.7 cents to the convertible loan holders in lieu of cash interest. The interest totalled A$477,737, so interest was paid in shares rather than cash, a small dilution.
Theta issued 2.3m performance options to two employees, exercisable at $0.12 or $0.17 with expiry in 2025 or 2027 and vesting on hurdles such as decision to mine and production. It also cancelled 1.9m expired performance options.
2Invest AG exercised another 1,000,000 options at $0.066, about A$66,000 on the stated price, to fund the Frankfort bulk sample. This continues 2Invest's run of small option exercises.
2023 AGM presentation repeats known figures: feasibility study to recover 1.08Moz over a 12.9-year mine life and a 6.1Moz gold resource. No new results are visible in the text provided.
2Invest AG exercised 1,000,000 options at $0.068, about A$68,000 on the stated price, with proceeds going to the Frankfort bulk sample. A further small exercise by the same holder, following its 5m options in September.
Following EGM approval, Theta will sign investor relations consultancy deals with Golden Asia and High Gift. They get 20m and 10m options at $0.12, expiring 31 March 2025, exercisable only after a 10-day VWAP above $0.30. Golden Asia also gets a A$50,000 signing fee.