Stockle - the stock oracle

Theta Gold Mines

ASX:TGM
No current share price held for this company.
No price history held for this listing yet.
Market cap
—
Shares on issue
—
Story beats
180 since 2011
Last event
18 Sept 2026

Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

25 June 2026drilling progress report▲ Good

Construction update: over 50% of plant concrete poured, gold room and mill steel going up, ball mill due on site end July 2026, crushing plant end September 2026. Tailings facility upgrade groundworks started. Continues the build toward first gold in 2027.

Discuss in chat

3 Feb 2026resource reserve update▲ GoodMajor

Revised feasibility study (Minxcon): 13.1-year mine life, post-tax NPV10 US$455m (A$689m), IRR 77%, AISC US$1,181/oz at US$2,884 gold, peak funding US$77m. It reinstates a base case including Inferred resources, retracted in Oct 2025; reserve plan unchanged at 514koz.

Discuss in chat

27 Nov 2025drilling progress report▲ Good

Construction update: retaining-wall excavations done, all but one base cast, gold room platform started, and over 12,000 cubic metres moved. Company says works are on schedule and within budget, with end-2026 commissioning unchanged.

Discuss in chat

23 Oct 2025drilling progress report▲ Good

Contractors are fully mobilised at TGME and bulk earthworks are ramping up, with civil works started at the carbon-in-leach section. Over 120 people are on site. Plant commissioning is still targeted for end-2026 and production Q1 2027.

Discuss in chat

30 Sept 2025resource reserve update▲ GoodMajor

The optimised feasibility study (delivered by Minxcon) shows a 14.5-year mine life, post-tax NPV US$504m (up from US$219m in 2022) and US$1.2bn free cash flow at US$2,710 gold, with peak funding US$79m. The 514koz reserve case follows; the base case was later retracted.

Discuss in chat

30 July 2024drilling result▲ GoodMajor

Lab tests found gold is recoverable from historic rock dumps (about 95% recovery) but only 58.95% from the main tailings dam sample. This resolves the awaited recovery results; 174,000oz of surface gold may support early cashflow, which the company is still only considering.

Discuss in chat

7 May 2024drilling result▲ Good

Drilling on the TGME Main tailings dam confirmed expected gold grades: 46 of 80 samples at or above 1g/t, including 8 at 2 to 4.11g/t. Metallurgical recovery results are still awaited. PowerChina is said to be satisfied with the grades, supporting its due diligence.

Discuss in chat

27 Mar 2024drilling progress report▲ Good

PowerChina's contractor finished 407m of drilling on TGME tailings dams for metallurgical testing. Tailings hold about 140,000oz gold (141,000oz total JORC). Theta is considering adding tailings recovery to bring forward early cashflow ahead of underground development. This follows the February early-cashflow idea.

Discuss in chat

19 July 2023drilling progress report▲ GoodMajor

Drill and blast has started at Frankfort for the 3,000-ton bulk sample to be trucked to Pan African's Barberton plant. Theta expects processing to finish in Q3 2023, with payment based on gold content afterwards.

Discuss in chat

27 July 2022resource reserve update▲ GoodMajor

The definitive feasibility study for the TGME underground project shows pre-tax NPV10 of US$324m (A$432m) at US$1,642/oz, 12.9-year life, 1.24Moz mined and 558koz reserve. Peak capital US$77m, first gold Q2 2024, subject to funding and permits. Funding remains unsecured; further equity raises are planned.

Discuss in chat

6 Apr 2022drilling result▲ GoodMajor

Rietfontein metallurgical testing shows 89.5% gold recovery (above the 80% assumed in the PFS), completing metallurgical work on all four mines. The feasibility study is about 85% complete, due Q2 2022. Chair hopes mine life extends to about 10 years.

Discuss in chat

13 Jan 2022resource reserve update▲ GoodMajor

Rietfontein is added to the underground feasibility study: 1,334kt of ore at 6.82g/t for 293koz (107koz Indicated, 186koz Inferred), over about 7.6 years at 180ktpa. Recovery is assumed at 80% pending testwork, no reserve is declared, and the DFS is now expected Q2 2022.

Discuss in chat

7 Dec 2021drilling result▲ GoodMajor

Trial mining at Frankfort is complete. Long-hole mechanised stoping with 15m panels suited the narrow 0.6-6.0m reef, with 85% of blasted rock cast to the cleaning drive and minimal dilution. The company calls it a key de-risking step; the DFS is still expected Q1 2022.

Discuss in chat

8 Apr 2021resource reserve update▲ GoodMajor

Maiden underground Ore Reserve of 419koz at 5.49g/t (Beta, Frankfort, CDM), lifting global reserve to 580koz. Delivers the Q1 2021 promise, but the open-pit reserve fell from 205koz to 161koz, which the text attributes to combined open-pit and underground studies.

Discuss in chat

14 Dec 2020resource reserve update▲ GoodMajor

Board approved an underground pre-feasibility study on the Beta/Frankfort mines (575koz M&I resource), due Q1 2021, aiming for a first underground maiden reserve to add to the 205koz open-pit reserve. Advances the underground acceleration plan; no reserve declared yet.

Discuss in chat

18 Nov 2020drilling result▲ GoodMajor

Bulk samples from underground faces gave CIL gold recoveries of 94% at Rietfontein and 91% at Beta and Vaalhoek, well above expectations per the company. Preliminary results feed the underground pre-feasibility study; Frankfort sample recovered poorly and needs more work. Supports the plan to accelerate underground production.

Discuss in chat

30 July 2020drilling progress report● Neutral

Geotechnical drilling and a geophysical survey have started at the Starter Theta pit, covering waste dump and pollution dam areas, with design engineering due by end-September. Trial mining is still planned for late 2020, and COVID lockdowns have not affected site works.

Discuss in chat

20 Apr 2020resource reserve update▲ GoodMajor

Optimised Theta open-pit schedule adds 40,000oz over the May 2019 study: 260koz to plant over 6.5 years, 600ktpa, capex US$31.4m (was US$34.3m), NPV5 US$85m (was US$50m), IRR 123% (was 65.1%), AISC US$855/oz, at US$1,500/oz gold.

Discuss in chat

16 May 2019resource reserve update▲ GoodMajor

Global resource rises to 6.03Moz (44.8Mt at 4.18g/t) from 5.75Moz. The Theta Project open-cut resource grows to 870koz from 600koz, and a maiden Probable Ore Reserve of 205koz (2.31Mt at 2.76g/t) is declared, the company's first reserve.

Discuss in chat

29 Apr 2019drilling result▲ Good

Phase 2 Columbia Hill RC drilling finished in late March: 58 holes for 3,554m, with over 95% hitting 1g/t or better, including 3m at 16.04g/t. The deposit remains open to the west. Drilling has paused so the feasibility study can finish later in Q2.

Discuss in chat

4 Mar 2019drilling progress report● Neutral

Feasibility study scope now includes a Columbia Hill section as a starter pit alongside Theta Hill, and completion slips to early Q2 2019. Two RC rigs are drilling Columbia Hill. Permitting for open-cut mining in MR83 is under way.

Discuss in chat

4 Mar 2019drilling result▲ Good

Columbia Hill drilling extended into March after strong shallow gold intercepts, including 3m at 5.05g/t and 2m at 13.52g/t, with results up to 13.5g/t. Columbia Hill is being added to the feasibility study; revised resource and reserve still due early Q2 2019.

Discuss in chat

21 Jan 2019drilling result▲ Good

First-phase resource drilling at Theta Hill is nearly complete, with over 7,400m drilled in Q4 2018. Results include 11m at 2.1g/t and 1m at 27.5g/t at Theta Hill, plus more shallow gold at Columbia Hill and Scammells. Feasibility study and reserves still planned for early 2019.

Discuss in chat

29 Nov 2018drilling result▲ Good

New RC drilling at Theta Hill and Columbia Hill shows shallow high-grade gold, e.g. 3m at 19.4g/t at Theta Hill and 4m at 12.53g/t and 16m at 3.27g/t at Columbia Hill. Over 2,500m drilled since September; results feed the Q1 2019 feasibility resource update.

Discuss in chat

15 Oct 2018resource reserve update▲ GoodMajor

Theta Hill scoping study: about 67kozpa for 7.6 years (509koz recovered), AISC about US$569/oz, peak capital about US$16m, post-tax NPV7.5 about US$152m. Plant refurbishment is estimated at US$11.1m. About 83% of the mined resource is Inferred, and funding is not secured.

Discuss in chat

26 Sept 2018resource reserve update▲ GoodMajor

Maiden Theta Hill open-cut resource of 4.48Mt at 4.14g/t for 600koz (85% Inferred) lifts group JORC resources to 5.75Moz (23% Measured and Indicated), up 2.0Moz in 12 months. This is the second upgrade due in September. Reserves are targeted for early 2019 and a feasibility study for Q1 2019.

Discuss in chat

28 Aug 2018drilling result▲ GoodMajor

RC hole DG4LT19 returned 16m at 7.36g/t gold from 38m at DG4, a standout Lower Theta result. Two RC rigs continue; second resource upgrade and Scoping Study are now due by end September 2018, with the earlier July resource target slipping.

Discuss in chat

18 June 2018drilling result▲ Good

More Theta Hill and DG4 Lower Theta assays, best 9.3g/t over 0.9m and 6.5g/t over 3m. Maiden resource for Theta North expected to be relatively modest, due July 2018, with more drilling needed for Indicated status. Over 500 samples at lab.

Discuss in chat

22 May 2018drilling progress report● Neutral

Third rig (RC) now drilling at Theta Hill; Rietfontein dewatering continues, water now just below the 4 level adit hanging wall. Company sponsors the October 2018 South African Gold Panning Championships at Pilgrim's Rest. No new results.

Discuss in chat

10 May 2018drilling result▲ Good

Theta Hill diamond hole DDBH21 hit 1m at 126g/t gold in Bevetts Reef; Trench E at DG4 returned 38m at 1.28g/t. An RC rig returns to site, funded by the new A$5m placement. A further resource upgrade follows drilling completion.

Discuss in chat