27 Nov 2025drilling progress report▲ Good
Construction update: retaining-wall excavations done, all but one base cast, gold room platform started, and over 12,000 cubic metres moved. Company says works are on schedule and within budget, with end-2026 commissioning unchanged.
The 571,425 SPP shares were issued on 24 November at 21c. Shareholders approved 30m unlisted options (20c, 25c, 30c, 18 months) for Golden Asia and High Gift as compensation for earlier financial-support guarantees to contractors.
The share purchase plan closed raising only A$120,000 (571,425 shares at 21c), far below the roughly A$2m targeted. Director Byron Dumpleton took A$30,000. Attaching options remain subject to approval at the AGM.
What it means for a shareholder
571,425 new shares at $0.210 to raise about $120,000. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Theta ordered two 900kW ball mills from South African firm MechProTech for the TGME plant, to be delivered within 25 weeks. Site team is now 137. This is a first major equipment order, supporting the end-2026 commissioning target. Order value not stated.
Options prospectus lodged for free attaching options: up to 24.0m Placement Options and 4.0m SPP Options, one per 2.38 shares. It is the disclosure document for the options already announced with the October raising; no new funding.
The share purchase plan and options prospectus opened. Eligible holders can buy shares at 21c, with one free option per 2.38 shares (A$0.32 exercise, 18 months, subject to approval). Offers close 17 November 2025.
The SPP offer booklet lets eligible shareholders apply for up to A$30,000 of shares at 21c with no brokerage, closing 17 November 2025. It restates the funding package, including cornerstone tranches and the convertible loan conversion.
Contractors are fully mobilised at TGME and bulk earthworks are ramping up, with civil works started at the carbon-in-leach section. Over 120 people are on site. Plant commissioning is still targeted for end-2026 and production Q1 2027.
21 Oct 2025capital raising announcement▲ GoodMajor
A third cornerstone tranche adds US$6m (~A$9.3m) at 15.5c, led by existing 15.5% holder Ruihua, subject to shareholder approval. Holders of the 2023 convertible loans agreed to convert into 44.0m shares plus 10m options, also subject to approval.
The placement and first cornerstone tranche completed, bringing in US$12.9m (~A$19.6m): 57.1m shares at 21c and 49.1m shares at 15.5c (24-month escrow). Attaching options need shareholder approval. The timetable has been revised.
What it means for a shareholder
57.1m new shares at $0.210 to raise about $12.9m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Theta secured US$33.9m (~A$51.4m) of equity and debt: a A$12m placement at 21c, US$15m from cornerstone investors at 15.5c, US$1m from a director-linked entity, and a US$10m loan. Free options attach, and a ~A$2m share purchase plan is planned. This builds on the IDC loan for construction.
Theta asked to extend its voluntary suspension by one day, to 7 October 2025, pending a funding transaction announcement. Administrative continuation of the 3 October suspension.
Theta's shares were suspended at its own request after a 1-3 October trading halt, pending an announcement on a funding transaction and the TGME project. This follows the 30 September feasibility study and precedes the 7 October raising.
After consulting ASX, Theta retracted the base-case production target and financials in its 30 September feasibility study, because inferred resources made up 54% of the 1.31Moz target. The 514koz reserve-case target is not challenged. This reverses the headline NPV and cash flow figures.
3,800,000 shares were issued on exercise of employee options at 12c, raising A$456,000 for earthworks, civils and water management. The options vested after the decision to mine and a 12-month role condition.
What it means for a shareholder
3.8m new shares at about A$0.120 to raise about A$456,000. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
The 2025 Annual Report says construction has begun at TGME, MR83 is renewed to 2038 and an optimised feasibility study (post-tax NPV US$503m at US$2,710 gold) is complete. The company aims for cash flow in 2027. The study's base case was retracted on 3 October.
The optimised feasibility study (delivered by Minxcon) shows a 14.5-year mine life, post-tax NPV US$504m (up from US$219m in 2022) and US$1.2bn free cash flow at US$2,710 gold, with peak funding US$79m. The 514koz reserve case follows; the base case was later retracted.
Appendix 4G governance checklist for the year to 30 June 2025, pointing to the corporate governance statement in the annual report. Administrative filing with no new business information.
Bulk earthworks and civil works have begun at TGME, with contracts signed with PICM and Mainpro. RM Process and Eco Elementum are owners' engineers. Initial plant commissioning is targeted for end 2026. Debt syndication is expected to firm after the updated feasibility study, and institutional investors have agreed to support construction payments.
Hansjoerg Plaggemars joined the board as a non-executive director, representing Deutsche Balaton, Delphi and Sparta Group. Richie Yang moves from non-executive to Executive Director on A$240,000 a year, rising to A$300,000 once gold sales begin.
Lenders on the ~A$5m 2023 convertible loans agreed to defer maturity to 30 September 2026. Theta pays a 3% deferral fee and penalty interest in shares (A$719,205), repays 50% of the interest by 31 December 2025, drops the royalty, and conversion is at a 15% discount to the 10-day VWAP.
Updated investor presentation for the Noosa Mining Conference, 23-25 July 2025. The visible text is cover letter and disclaimers; no new figures are visible. Slide 13 was later retracted.
Theta retracted slide 13 of its 22 July presentation, which showed updated forecast financials. Because assumptions have materially changed since the 2022 study and no revised feasibility study is complete, investors should not rely on it.
2,750,000 shares were issued on conversion of the same number of performance rights, which vested on the decision to mine. Administrative follow-up to the 1 July notice.
The US$4m Ruihua placement is complete: 47,337,278 shares and 23,668,639 unlisted options issued, arranged by Golden Asia. Consultants also received 1,869,231 shares, held in escrow for 3 months. This closes the 30 June raise.
The decision to mine met the vesting condition for 2,750,000 performance rights and 2,900,000 options (12c exercise, expiring 30 Sep 2025) issued to directors and employees in December 2022. The rights convert to shares by 4 July.
30 June 2025capital raising announcement▲ GoodMajor
Board approved a decision to mine the TGME Gold Project and Theta raised US$4m (~A$6.2m) from Ruihua at 13c, with 47.3m shares plus 23.7m free options. Bank co-lender syndication behind the US$35m IDC loan is now live. Funds go to earthworks and civils.
Pre-construction work is complete: the old plant is decommissioned and the site is ready for bulk earthworks. Moore Debt Advisory was appointed to find co-lenders alongside the US$35m IDC facility. Full construction remains subject to completing funding.
The Industrial Development Corporation of South Africa approved a loan of up to US$35m (about A$53.8m), 7-year term with 18-month repayment moratorium, subject to conditions and final documents. MR83 was also renewed to 2038. This is the first concrete debt backing against the US$77m capital need.