Each one in plain English, with the numbers worked through for a shareholder.
21 Sept 2023annual report● Neutral
FY2023 annual report recaps the Feasibility Study and the 23.8Mt at 2.02% Cu resource. Optimisation work includes doubling mining equipment size to cut labour and capex and delay underground development. No FID yet, citing inflation and labour shortages.
Appendix 4G governance checklist lodged with the annual report, pointing to where corporate governance disclosures sit. Administrative filing with no new company information.
Nicholas Spencer is appointed CEO, with over 30 years in mining development, ending the CEO search. Chris Dippenaar replaces CFO Amy Treble, who resigned. KGL also lodged a federal submission seeking copper's inclusion on the Critical Minerals list.
June 2023 quarter: cash $22.5M, up from $13.2M after the entitlement offer. Draft letter of intent issued to preferred mining contractor; plant capacity raised from 1.6 to 2.0Mtpa. Interviews under way for CEO, Project Director and Finance Director; a new drilling contractor started in July.
First six 2023 Jervois holes extend mineralisation. Rockface KJCD556D2 hit 12.1m at 1.64% Cu and D3 5.6m at 3.10% Cu; Marshall 3.5m at 1.96% Cu; Reward infill up to 14.7m at 2.50% Cu. Supports the push for a longer mine life.
23 May 2023capital raising announcement● NeutralMajor
The entitlement offer raised about $13.5M at $0.12, a 67% take-up, short of the up to $20.2M sought but above the $9M minimum. Funds continue Jervois de-risking and drilling. KGL may place the remaining shortfall within three months at no less than $0.12.
The entitlement offer opened 4 May and closes 18 May, with the offer booklet sent to eligible shareholders. Terms are unchanged: 10-for-27 at $0.12, up to about $20.2M. Administrative step in an already announced raising.
Letter telling ineligible shareholders (outside Australia and New Zealand) they cannot take part in the $0.12 entitlement offer; their entitlements lapse with no payment. Administrative notice. KMP is stated at about 26.13%, Wood entities 9.24%, Marshall Plenty 7.27%.
Investor presentation for the 10-for-27 entitlement offer at $0.12, raising up to about $20.2M. Repeats the offer terms and Jervois project background already announced on 26 April; the visible text is mostly disclaimers and contents.
March 2023 quarter: cash $13.2M, down from $14.6M. Two rigs are drilling since 1 March, final 2022 Reward infill results are in, and contract term sheets are being prepared. Project commencement is subject to market conditions.
Proposed 10-for-27 non-renounceable entitlement offer at $0.12 to raise up to about $20.2M, not underwritten, with a $9M minimum. KMP, Denis Wood's entities and Marshall Plenty have committed $8.6M. Price is well below the $0.37 raised in 2022. Funds project work and drilling into 2024.
Update says an accelerated drilling program began 1 March 2023, aiming to extend mine life to 15+ years. Reward infill holes returned results such as 9.3m at 2.68% Cu. The project will start only when labour and materials supply can be assured, so no firm start date.
Brian Gell, with over 40 years in construction and mineral processing projects, joins as independent non-executive director from 4 April 2023. Steven Rooney has resigned as COO; Gell will help find a Project Director. Partly fills the open director search.
Half-year accounts to 31 December 2022 recap the Feasibility Study and Bellbird resource upgrade. Ian Williams resigned as director on 28 November 2022. The company intends to move to FID if project finance and shareholder equity can be secured, subject to market conditions.
December 2022 quarter: cash $14.6M, down from $18.1M. Mostly repeats the Feasibility Study and the Rockface and Marshall Deeps results. Pre-FID work focuses on growing the resource, cost optimisation and risk management, with construction in 2023 subject to FID and market conditions.
Reward hole KJCD557 at Marshall Deeps hit 2.00m at 4.32% Cu from 661m, a step-out of more than 200m south of previous drilling. Follow-up drilling is planned for 2023; more drilling is needed before any resource can be reported.
AGM presentation repeats the Feasibility Study results (NPV A$241M, A$298M capex, 11.75-year life). It cites 455M shares, A$131M market cap and $18M cash at 30 September, and says funding options are being considered. No new project figures.
Re-release of the 10 November Feasibility Study to add JORC Table 1 Sections 1-3, which were first released on 14 September 2022. The company states no new information and no other changes to the study.
Feasibility Study completed: 11.75-year mine life (up from 7.5-8 in the Dec 2020 PFS), Ore Reserves up 25% to 11.7Mt at 2.10% Cu, pre-production capex A$298M (PFS A$200M), after-tax NPV8 A$241M, IRR 20.7% at US$4.23/lb. FID targeted early 2023.
Denis Wood will be paid $40,000 a month as Executive Chairman, backdated to 18 May 2022. Jeff Gerard's company is engaged as a consultant on the Feasibility Study, paid $50,000 with $50,000 more on completion. Ian Williams will not seek election at the AGM.
September 2022 quarter: cash $18.1m, down from $23.3m. The Feasibility Study is now targeted for Q4 2022, with the reserve statement being certified for a 10-year-plus mine life. Contracts move to 2023. Mostly repeats the Bellbird and Rockface results.
Annual report for the six-month transitional period to 30 June 2022. The Executive Chairman says the Feasibility Study is being drawn to a close after Bellbird infill drilling, and cites the Glencore offtake and the 23.8Mt, 481.2kt copper resource. No new figures visible.
Appendix 4G governance checklist lodged with the annual report, pointing to the corporate governance statement on pages 8-15. Administrative filing with no new resource, financing or project information.
Rockface hole KJCD556 hit 12.38m at 2.60% Cu from 978m, 120m below earlier drilling, matching downhole electromagnetic predictions. The mineralisation remains open at depth. It needs more drilling before entering the resource, with follow-up planned for 2023.
Bellbird resource rose 14% to 129kt copper (6.69Mt at 1.93%), with the project's first Measured resource. Total Jervois resource is now 23.8Mt with 481.2kt copper, up from 465.6kt. The open pit design is 85% Measured, supporting the reserve work.
June 2022 quarter: cash $23.3m after the $23.04m raising. The mine plan is being simplified, deferring underground mining, to cut costs while targeting a 10-year-plus mine life. Infill assays are awaited, contracts are pushed to 2H 2022, and financing talks continue.
Final assays from a 23-hole Reward program: 11.21m at 1.71% Cu at Reward East, and hole KJCD529 found two new zones at depth, best 4.42m at 2.21% Cu from 763m. Bellbird infill drilling (16 holes) is complete, with assays awaited.
Shareholders approved the issue of shares to KMP Investments (the 6.5M top-up from the entitlement offer) at the 28 June EGM, with 99.5% of votes cast in favour. Resolves the open approval thread.
Ian Williams, a former corporate lawyer and director of New Hope and Lindsay Australia, joins as independent non-executive director from 14 June 2022, sitting on the audit and risk and remuneration committees.
AGM presentations say the Feasibility Study will be delayed: the new mine plan needs more infill drilling to meet JORC Reserve rules. Targets are an end-2022 investment decision, development in 1H 2023 and copper production in 2024. Cash raised $23.2m, no debt.