The story so far
The events that changed the company's story, in plain English, each written against everything known about the company at the time. The dot shows whether it was good, bad or neutral for shareholders.
2026
- 15 Oct
KGL's Board approves the Final Investment Decision for Jervois, resolving the long-targeted FID thread. First concentrate remains targeted for H1 2028, capital costs are said to stay consistent with the Baseline Economic Model, and about 60% of project cost is under executed contracts.
other
- 1 Oct
KGL awards Sedgman the design, procurement and construction contract for the 2.0Mtpa Jervois processing plant, resolving the EPC thread open since August. Scope is increased, but terms are said to match the Baseline Economic Model's capital cost and schedule. FID is flagged for coming weeks.
contract award
- 19 Aug
KGL signs a ~A$36M contract with Northern Transportables for the Jervois accommodation village. Long-lead mill procurement and drilling have begun. The Sedgman EPC contract is still being finalised. FID stays targeted for Q3 CY2026, with commissioning in H1 CY2028.
contract award
- 30 July
Shareholders approve all EGM resolutions on a poll, including the ~A$180M placement at A$0.20 and share issues to KMP and directors Gerard, Purnamasidi and Deguara. This clears the last condition on the A$300M raising, which funds Jervois alongside the Wheaton stream.
security holder rights change
- 24 July
The entitlement offer closes with valid applications for ~333M shares (~A$66.6M); the remaining ~264.6M shares (~A$52.9M) go to the underwriters as shortfall. KMP takes ~41M shortfall shares, lifting it to 36.2%. The A$180M placement still needs shareholder approval.
capital raising announcement
- 29 June
The ~A$180M conditional placement bookbuild is completed at A$0.20 per share (~902M shares), a 25.2% discount to the last price of A$0.2675. KMP expects to put in ~A$65M and Wheaton joins the register. It needs shareholder approval at an EGM on 30 July.
capital raising announcement
- 25 June
KGL launches a A$300M equity raising: a A$180M conditional placement (~902M shares) and a A$120M entitlement offer at 1-for-1.29 (~598M shares). With Wheaton's stream, it is expected to fully fund Jervois. KMP may rise from 33.2% to 36.2%; Wheaton up to A$35M.
capital raising announcement
- 18 June
KGL receives the first US$16M tranche of the US$32M Early Deposit under the Wheaton stream, lifting available cash to about A$28M (from A$5.5M at 31 May). The second tranche is planned for late September 2026, subject to FIRB and early-works evidence.
debt financing
- 24 Apr
The updated baseline economic model lifts Jervois post-tax NPV8 to A$839M (from A$405M) and IRR to 30%, using higher metal prices. Construction capex rises to A$439M and commissioning moves to H1 2028. Further funding is still required.
resource reserve update
- 2 Apr
KGL signs a US$300M silver and gold streaming agreement with Wheaton: US$275M upfront (US$32M early deposit) plus a US$25M cost-overrun facility. Copper stays unencumbered. This is the first major funding for Jervois; Wheaton can join a future equity raise up to A$35M. Capex and revenue are expected to rise.
debt financing
2025
- 18 Dec
Sam Strohmayr, a former Glencore Zinc Australia COO, is appointed CEO from 27 January 2026 on $450,000 a year including super. This ends the CEO search running since Jeff Gerard became executive chairman in January 2025. A Darwin office will open in early 2026.
director officer appointment
- 31 Oct
KGL raises about A$11M in a placement of about 78.57M shares at $0.14, well above the $0.095 offer price in April. RCF rises to about 9.9%. Funds go to enabling works ahead of FID and working capital. A five-member Project Steering Committee is formed, including two RCF nominees.
capital raising announcement
- 24 Sept
Resource Capital Fund joins the register with 8.32% via an off-market share purchase. KGL reports several non-binding finance term sheets received, an open-cut mine plan optimisation, an open-cut mining tender shortlist, and enabling works targeted for late 2025/early 2026. It is also reviewing bismuth in concentrate.
joint venture update
- 23 Apr
KGL appoints Cutfield Freeman & Co and amicaa Advisors as joint corporate advisors to arrange financing for Jervois, following the February Feasibility Study Update (NPV8 A$405M). Options include strategic partners, offtake-linked investment and project debt, targeting 2027 production. This starts the financing thread flagged earlier.
material agreement
- 3 Apr
The entitlement offer raised about $4.2M at $0.095, a 55% take-up against up to $7.7M sought. Applications cover about 44.2M new shares, to be allotted 7 April 2025. KGL may place the shortfall within three months at not less than $0.095.
capital raising announcement
- 6 Mar
KGL launches a 1-for-8 entitlement offer at $0.095 to raise up to about $7.7M, with a $3M minimum and no underwriting. KMP has committed to take up its full entitlement (about $2.7M). Funds go to financing advisers, project execution and overheads.
capital raising announcement
- 10 Feb
The updated Jervois Feasibility Study shows post-tax NPV8 of A$405M (up from A$241M in 2022), IRR 24%, capex A$362M (up from A$298M) and a 10-year mine life. Ore Reserves are 14.38Mt @ 1.77% Cu. Commissioning is targeted for H1 2027; financing is the next step.
resource reserve update
- 21 Jan
CEO Philip Condon resigns, with his employment ending 21 January 2025, only about six months after he took the role. Chairman Jeff Gerard becomes Executive Chairman while a CEO search runs. RPMGlobal is appointed independent technical engineer for lenders, and Axiom Project Services supplies project personnel.
director officer appointment
2024
- 25 Nov
Jervois resource rises 17.4% to 27.45Mt, with contained copper up from 472kt to 513kt, though grade slips from 2.02% to 1.87% Cu. Underground resource grew 4.1Mt. The Feasibility Study Update is nearing completion, with an independent technical expert report required first.
resource reserve update
- 5 Aug
The entitlement offer raised about $8.08M at $0.10 a share, a 54% take-up against up to $15.1M sought, with KMP contributing $4.79M. Funds are meant to finish the Feasibility Study Update and continue drilling. KGL may place the shortfall within three months.
capital raising announcement
- 29 July
Rockface Deeps hole KJD627D1 hit a massive sulphide zone of 5.08m at 6.74% Cu, 18.41% Zn, 8.42% Pb at 1,013m. Two infill holes also hit high-grade copper. KGL says this may be a new high-grade domain, subject to further infill drilling; KJD627D2 assays are pending.
drilling result
- 8 July
KGL proposes a 4-for-15 entitlement offer at $0.10 a share to raise up to about $15.1M, with a $6M minimum and no underwriting. KMP Investments commits to its full $4.8M entitlement. Funds go to the feasibility update, drilling and deep exploration, targeting production in 2027.
capital raising announcement
- 5 July
Philip Condon, a mining executive with 35+ years' experience, is appointed permanent CEO from 29 July 2024 on $418,125 a year. He has worked at KGL for a month as GM Projects. This ends the CEO search that began with Spencer's January resignation; Kylie Anderson's interim role presumably ends.
director officer appointment
- 23 May
Reward resource updated to 13.16Mt at 1.79% Cu for 234.9kt copper, including a maiden Measured 2.63Mt at 1.91% Cu (50.3kt Cu). Reward and Bellbird open pits are now 67% Measured, meeting the 2024 upgrade target and helping financing. Rockface is next.
resource reserve update
- 21 Mar
Executive Chairman Denis Wood resigns from 31 March 2024 due to health issues. Company Secretary Kylie Anderson becomes interim CEO at $40,000 a month, and director Jeff Gerard becomes Independent Chairman. A permanent CEO search continues.
director officer appointment
- 30 Jan
CEO Nick Spencer resigned effective 30 January 2024, about four months after his appointment was announced. The board resumes its CEO search; work on the optimised feasibility study and drilling continues.
director officer appointment
2023
- 8 Nov
Deep Rockface hole KJCD575W1 hit 5.0m at 2.43% Cu, the deepest copper at Jervois; KJCD556D4 found zinc-rich massive sulphide, 4.1m at 3.59% Cu and 20.49% Zn. Extent of the zinc-rich zone is uncertain. A 2km deep hole has started.
drilling result
- 20 Sept
Nicholas Spencer is appointed CEO, with over 30 years in mining development, ending the CEO search. Chris Dippenaar replaces CFO Amy Treble, who resigned. KGL also lodged a federal submission seeking copper's inclusion on the Critical Minerals list.
director officer appointment
- 23 May
The entitlement offer raised about $13.5M at $0.12, a 67% take-up, short of the up to $20.2M sought but above the $9M minimum. Funds continue Jervois de-risking and drilling. KGL may place the remaining shortfall within three months at no less than $0.12.
capital raising announcement
- 26 Apr
Proposed 10-for-27 non-renounceable entitlement offer at $0.12 to raise up to about $20.2M, not underwritten, with a $9M minimum. KMP, Denis Wood's entities and Marshall Plenty have committed $8.6M. Price is well below the $0.37 raised in 2022. Funds project work and drilling into 2024.
capital raising announcement
- 19 Jan
Reward hole KJCD557 at Marshall Deeps hit 2.00m at 4.32% Cu from 661m, a step-out of more than 200m south of previous drilling. Follow-up drilling is planned for 2023; more drilling is needed before any resource can be reported.
drilling result
2022
- 10 Nov
Feasibility Study completed: 11.75-year mine life (up from 7.5-8 in the Dec 2020 PFS), Ore Reserves up 25% to 11.7Mt at 2.10% Cu, pre-production capex A$298M (PFS A$200M), after-tax NPV8 A$241M, IRR 20.7% at US$4.23/lb. FID targeted early 2023.
resource reserve update
- 27 Sept
Rockface hole KJCD556 hit 12.38m at 2.60% Cu from 978m, 120m below earlier drilling, matching downhole electromagnetic predictions. The mineralisation remains open at depth. It needs more drilling before entering the resource, with follow-up planned for 2023.
drilling result
- 14 Sept
Bellbird resource rose 14% to 129kt copper (6.69Mt at 1.93%), with the project's first Measured resource. Total Jervois resource is now 23.8Mt with 481.2kt copper, up from 465.6kt. The open pit design is 85% Measured, supporting the reserve work.
resource reserve update
- 18 May
Managing Director Simon Finnis resigned effective 20 May 2022. Chair Peter Hay and director Denis Gately will leave at the 31 May AGM. Denis Wood becomes Executive Chairman, Jeff Gerard joins 31 May, and a CEO search has begun. Feasibility Study remains the focus.
director officer appointment
- 10 May
Entitlement offer closed raising $23.04m (95.2% take-up) at $0.37, from 62.27M applications. Resolves the 13 April raising near the maximum. KMP's extra 6.5M top-up shares need shareholder approval; shortfall may be placed within three months.
capital raising announcement
- 13 Apr
KGL proposes a 1-for-6 non-renounceable entitlement offer at $0.37 to raise up to $24.2m, not underwritten, with a $9.9m minimum. KMP Investments and Denis Wood intend to take up $8.1m. Funds go to FEED, the Feasibility Study and working capital.
capital raising announcement
- 23 Mar
Combined Jervois resource rises 14% to 465.6kt contained copper (22.87Mt at 2.04% Cu), up from 410kt in 2020. Indicated copper rises to 319.5kt. The estimate excludes Reward South. Feasibility Study stated to be on schedule for Q2 2022.
resource reserve update
- 22 Mar
Binding offtake with Glencore for 100% of Jervois copper concentrate, delivered to its Mount Isa smelter, minimum 5 years from commercial production. Conditional on finance by 30 Sept 2025 or production by 31 Dec 2025. Terms will feed the Feasibility Study.
material agreement
- 7 Mar
Rockface resource rises 4% to 108.3kt contained copper (3.53Mt), grade 3.07% Cu (down from 3.17%), now 87% Indicated. Completes the drilling and resource work for the Feasibility Study, which management says remains on track for mid-2022.
resource reserve update
- 27 Jan
Bellbird resource rises 10% to 113.4kt contained copper (5.76Mt, tonnes up 28%), but grade falls to 1.97% Cu from 2.30%. Rockface update expected in four to six weeks. Engineers expect more mill feed than earlier designs, which management says could lengthen mine life.
resource reserve update
- 10 Jan
Reward resource rises 20% to 244kt contained copper (13.58Mt at 1.80% Cu), with two new higher-grade shoots. The Feasibility Study slips again, from Q1 2022 to mid-2022, to include the Bellbird and Rockface updates and cope with COVID and industry challenges.
resource reserve update
2021
- 21 Dec
New copper discovery 'Cox's South' between Rockface and Reward: hole KJCD482 returned 1.92% Cu over 2.53m, tied to a 700m by 500m conductor. Exploration target is 2-3Mt at 1.5-2.3% Cu (conceptual, not a resource). Follow-up hole planned early 2022.
drilling result
- 8 Dec
Rockface hole KJCD481D6 assayed 20.5% Cu and 302 g/t Ag over 4.21m, including a record 61.4% Cu. Two more holes (D7, D8) hit massive sulphides awaiting assay, extending the zone to at least 160m. This confirms the earlier visual estimate for D6.
drilling result
- 10 Nov
Assays confirm Rockface hole KJCD481D3: 23.6% Cu and 503 g/t Ag over 3.5m, including 40.9% Cu, the highest assay ever at Jervois. This resolves the earlier visual estimate. A further hole, D6, shows visual massive sulphides; four intercepts span over 85m.
drilling result
- 11 Oct
Rockface hole KJCD481D3 hit visually estimated 90% copper sulphides over 3.02m true thickness, open at depth and to the west-south-west. Only a visual estimate, assays pending. Management says it could expand the Rockface resource and extend the mine plan.
drilling result
- 27 Aug
The Jervois Feasibility Study is extended, and final investment decision moves to Q1 2022 from the earlier second-half 2021 target. Cost increases and COVID drilling and contractor constraints are cited. An updated resource estimate is due November 2021.
other
- 4 Aug
Executive Chairman Denis Wood, chairman since November 2015, retires on 30 August 2021 citing his health. CEO Simon Finnis becomes Managing Director, and Peter Hay becomes acting chair. The board has begun searching for a new chairman.
director officer appointment
- 5 July
Simon Finnis, formerly Metro Mining CEO, becomes KGL CEO on a $450,000 salary, with options tied to final investment decision and first production. Steve Mallyon joins as non-executive director. This fills the CEO and director vacancies flagged earlier.
director officer appointment
- 14 May
KGL placed the 5.2m entitlement shortfall shares at 70c, a 66% premium to the 42c offer price, raising $3.64m from institutional and sophisticated investors. Funds go mainly to the current drilling campaign. Allotment is expected 20 May 2021.
capital raising announcement
- 19 Mar
The entitlement offer raised $9.57m at 42c, about 81.3% of the amount offered, bringing the total raising to $21.57m with the placement. KGL may place the shortfall within three months at not less than 42c. A second rig is planned for April; development aimed at second half 2021, subject to a final investment decision.
capital raising announcement
- 22 Feb
KGL raised about $12m in an institutional placement at 42c (28.57m shares) and launched a 1-for-13 entitlement offer at 42c to raise up to $11.77m, total about $23.77m. Funds go to the Jervois feasibility study, financing and exploration. A CEO is to be recruited.
capital raising announcement
- 7 Jan
NT Government approved the Jervois Mining Management Plan, which the chairman calls the major outstanding approval before development. This resolves the thread open since April 2020. Feasibility study is under way, drilling is about to start, and project financing and concentrate marketing talks have begun.
regulatory community update
2020
- 2 Dec
PFS and maiden Ore Reserve released: 9.4Mt @ 2.41% Cu Probable Reserve, 7.5-year mine life, about 30,000tpa copper. Pre-tax NPV8 A$177m, IRR 23.1%, pre-production capital A$200m. Board approved moving to a Feasibility Study and restarting drilling to target a 10-year life.
resource reserve update
- 15 Sept
Jervois resource upgraded to 20.97Mt @ 2.03% Cu, containing 426,200t copper (up 30%) with 68% Indicated. Grade nearly doubled from 1.07% and tonnage fell 31%, versus the July 2019 estimate of 26.6Mt @ 1.47%. Reward South is excluded. PFS still due Q4 2020.
resource reserve update
- 5 Aug
The entitlement offer raised $3.83m (about 96% of the $3.99m target) at 16c, including $1.38m of top-up applications. KMP and Denis Wood took up their full entitlements. KGL may place the remaining shortfall within three months at not less than 16c.
capital raising announcement
- 9 July
KGL launches a 2-for-25 entitlement offer at 16c, an 8.6% discount, to raise about $3.99m (about 24.94m shares). Funds pre-development modelling and costings and sustains the company to project financing. KMP and Denis Wood intend to take up their full entitlements.
capital raising announcement
- 17 Mar
Reward South discovery: KJD415 hit 26.5m @ 0.98% Cu, 285.5g/t Ag, a new zone open in all directions. All nine Reward holes hit copper below the pit. Drilling has halted and the site closed for COVID-19; project financing delays are expected.
drilling result
2019
- 30 Dec
The entitlement offer closed raising only $3.83m (16.66m shares) against the $8.2m target. KMP's $2.11m (9.2m shares at 23c) was placed as shortfall, lifting the total to $5.94m. The raising fell about $2.3m short of target.
capital raising announcement
- 4 Dec
Seven more Reward holes hit high-grade copper just below and south of the proposed pit, including KJCD395 at 30m (estimated true width) @ 3.60% Cu. A new conductor south of the pit showed chalcopyrite. The 2019 drilling program is complete, with some assays outstanding.
drilling result
- 18 Nov
KGL launches a 1-for-8 non-renounceable entitlement offer at 23c to raise about $8.2m (about 35.7m shares), a 6.12% discount to the last close. Funds a drill rig, mining and geotechnical studies and the Mine Management Plan ahead of project financing. KMP, Marshall Plenty and Denis Wood intend to take up their full entitlements.
capital raising announcement
- 17 Oct
Bellbird drilling confirms a second high-grade zone, the East Lode, with the highest grade ever at Jervois: 1m @ 34.27% Cu. The Main Lode returned 8.0m @ 5.01% Cu, suggesting it may extend south. Six of seven holes hit their target lodes; results are still being evaluated.
drilling result
- 4 Oct
NT EPA completed its assessment and recommended the NT Government approve Jervois, which can proceed in an environmentally acceptable manner with conditions. This resolves the supplementary EIS thread. Chairman calls it the last major regulatory step before Mine Management Plan approval; construction now targeted for Q2 2020, later than end-2019.
regulatory community update
- 22 Aug
Jervois resource updated to 26.6Mt @ 1.47% Cu, containing 390,600t copper (from 385,200t). Indicated rises to 255,000t, now 65% of total (from 50%), with Reward Indicated up 240% and Rockface up 34%. A step toward the Ore Reserve.
resource reserve update
- 29 July
June quarter report: sufficient bore water for the project has been sourced, resolving a key open hurdle. The supplementary EIS was lodged in late July. Infill drilling gave high-grade copper, including 25.25m @ 2.67% Cu at Reward just below the planned pit floor.
quarterly activities report
- 26 Feb
KGL raises $6.5m at 30c (21.67m shares): $3.8m from Ernie Thrasher's Marshall Plenty, $1.7m from KMP, $1.0m from ASM funds. Funds infill drilling, an Ore Reserve estimate and water drilling. Supplementary EIS now due by end-June; construction possible late 2019, subject to approvals and financing.
capital raising announcement
- 23 Jan
Jervois copper resource updated to 385,200t at 1.49% on 25.8Mt, with Indicated rising 25% to 192,800t (over half the total) mainly from Rockface. The EIS public review was positive, but extra drilling is needed for a sustainable water source; supplementary EIS now expected mid-2019.
resource reserve update
2018
- 22 Oct
KGL lodged the draft Environmental Impact Statement for Jervois with the NT EPA. An eight-week public review runs to 14 December, then a supplementary report is due early 2019. Described as the last major outstanding approval; resolves the lodgement thread.
regulatory community update
- 30 Aug
KGL raises about $5.7m at 38c (15.02m shares, 12.8% premium), including $3m from ASM Connaught House funds, with a $2m share purchase plan at 33c to follow. Funds keep two rigs on site six months for exploration, mainly northern Reward. Draft EIS due in November; updated resource and maiden Rockface reserve targeted for Q4.
capital raising announcement
- 12 June
John Gooding (ex-Highlands Pacific CEO) and Fiona Murdoch join the board, and Paul Richardson becomes Project Director based at Jervois. Chris Bain resigns at end of June after almost five years. Adds mining and project-development experience as KGL targets construction next year.
director officer appointment
- 18 May
Jervois resource upgraded: contained copper up 18% to 384,800t, grade up 43% to 1.53% Cu on 25.2Mt (down 17% in tonnes, mainly from a higher 1% underground cut-off). Rockface is included for the first time, with over 90,000t of copper at close to 3%. Resolves the planned resource update.
resource reserve update
- 15 Feb
KGL raised $6.73m in a placement at 40c: 12.5m shares to Ernie Thrasher's entity ($5m) and 4.32m to KMP ($1.73m), a 5% premium to the prior close. It funds two rigs through 2018 and the EIS. Rockface and Reward drilling also continued to hit copper.
capital raising announcement
2017
- 14 Dec
Rockface assays extend high-grade copper, e.g. KJCD222 10.7m @ 4.38% Cu and KJCD218 3.35m @ 5.27% Cu, with wider lower-grade zones elsewhere. DHEM suggests Conductor 6 extends east. Results are to underpin the next resource estimate; drilling ends the following week.
drilling result
- 12 Dec
Two more Reward holes hit high-grade copper: KJD220W1 9.57m @ 5.11% Cu, 2.44g/t Au, and KJD223 8.16m @ 5.03% Cu, 3.35g/t Au, including 1.12m @ 15.24% Cu, 21.52g/t Au. Continues the Reward success from September; both rigs pause until early 2018.
drilling result
- 19 Oct
The entitlement offer closed 92% subscribed: 17.1m shares, about $5.1m of the $5.5m sought. The first $5.6m placement tranche is done; $1.3m depends on the 23 October EGM. The company may place the shortfall at 30c or more within three months.
capital raising announcement
- 25 Sept
Reward hole KJD216 assayed 11.63m @ 4.2% Cu from 636.1m, including 2.27m @ 11.14% Cu, confirming the visual result of 30 August. Drilling has restarted with a second rig due. Gravity work also identified new targets.
drilling result
- 13 Sept
KGL announced a $12.4m raise at 30c: a $6.9m placement (RCF Opportunities $3.0m, KMP $1.7m, Chairman Wood $1.2m subject to approval) plus a 1-for-11 entitlement offer of up to $5.5m. Funds more Jervois drilling; pro-forma cash $17.1m.
capital raising announcement
- 4 Sept
Rockface KJCD215 assayed 8.24m @ 9.21% Cu including 4.57m @ 14.00% Cu, plus 14.17m @ 4.74% Cu, with grade increasing at depth. KJCD214 returned 11.5m @ 1.73% Cu. Resolves the pending KJCD215 and KJCD214 assays.
drilling result
- 30 Aug
Reward hole KJD216 visually shows 12m of mineralisation from 636m, including 1.4m massive sulphide, 95m below the deepest previous Conductor R1 intercept. Looks like Rockface-style mineralisation. Visual only; assays expected in coming weeks.
drilling result
- 25 Aug
The NT Government granted a further mining lease (ML30829), so approved leases now cover all currently planned mining and processing. The EIS Terms of Reference were finalised, revised for a larger project than the 2015 pre-feasibility study, and EIS preparation is well under way.
regulatory community update
- 1 Aug
KJCD212, the deepest and most easterly Rockface hole, assayed 9.62m @ 3.18% Cu including 3.36m @ 5.43% Cu at Conductor 8. DHEM suggests mineralisation extends further east and deeper. KJCD215 shows strong visual mineralisation, assays pending; follow-up drilling planned.
drilling result
- 24 May
Denis Wood became Executive Chairman, having done some CEO functions during the year since May 2016 without a CEO; no extra pay. An in-house geology team under Adriaan Van Herk was formed. A further $1.6m R&D refund was received, taking total refunds above $4.6m.
director officer appointment
- 29 Mar
The NT Government awarded Jervois Major Project status through a Project Facilitation Agreement, requiring government and KGL to work together on approvals. It supports the approvals path; the company still plans to expand the resource before development.
regulatory community update
- 27 Mar
KGL is buying the adjoining Unca Creek tenement (EL28082) for $500,000 cash, almost trebling the Jervois project area from 37.9 to 110.8 km². It placed 2,702,702 shares at 37c to raise $1m, including from KMP Investments. Completion awaits NT Government transfer.
asset acquisition disposition
- 14 Mar
The SPP closed with applications for 9,188,161 shares from 280 holders, raising $2.48m at $0.27, short of the $3m maximum. Funds go to Jervois exploration; a nine-hole Rockface program began the previous week.
capital raising announcement
- 20 Feb
KGL launched a Share Purchase Plan to raise up to $3m at $0.27 a share (up to $15,000 each), funding a nine-hole Rockface program from March 2017. This follows the Jan 2016 raising at 9.5c; an unmarketable-parcel sale facility is also offered.
capital raising announcement
- 9 Feb
KJCD203 assayed 28m @ 5.08% Cu (incl. 14m @ 8.89%) from 435m; KJCD201 10.05m @ 8.99% Cu from 645.65m. A new Conductor 8, the strongest yet, points east. The board is planning accelerated drilling and a resource update.
drilling result
2016
- 10 Nov
KGL received a further $2.1m R&D Tax Incentive refund, taking recent refunds to $3m. The Chairman says this funds exploration well into 2017, including new DHEM conductor drilling at Rockface and at Reward, the largest known resource area at Jervois.
other
- 19 Sept
KJCD197 assays: 9.4m @ 11.53% Cu from 535.4m (Conductor 3) and 15m @ 7.11% Cu from 558m (Conductor 5); combined 37.6m @ 5.98% Cu. Grades rise with depth, making it Rockface's best result yet; two more holes under way.
drilling result
- 2 Aug
KJCD195 assayed 10.5m @ 8.76% Cu, 42.9g/t Ag, 0.51g/t Au from 478.4m, much higher grade than the earlier Rockface holes. New conductors identified, including the largest yet (Conductor 5); KJCD196 was weaker.
drilling result
- 9 May
Rockface hole KJCD182 returned 9m @ 2.91% Cu, 17.6g/t Ag from 284m and 6m @ 1.6% Cu from 296m. Company says width and grade are continuous across three holes, with early signs of copper grade improving with depth.
drilling result
- 5 May
The CEO position is made redundant and Simon Milroy's employment ended on 4 May 2016, following a review of how the company allocates its funds. The Chairman says the aim is reducing costs and maximising exploration spending.
director officer appointment
- 26 Apr
Rockface assays: KJCD183 returned 16m @ 3.34% Cu, 16.7g/t Ag from 362m, among the best Jervois copper grades. Downhole EM confirms a large conductor (145m x 145m) below the hole, a target for future drilling; KJCD182 results pending.
drilling result
- 29 Mar
First Green Parrot RC results confirmed shallow high-grade mineralisation: KJCD179 returned 7m @ 3.15% Cu, 27.24% Pb, 13.01% Zn, 333g/t Ag from 39m, and KJC177 returned 17m @ 1.68% Cu, 10.46% Pb from 54m. The drilling aims to upgrade the Inferred resource, and further results are expected.
drilling result
- 28 Jan
The entitlement offer closed with applications for 18.1m shares from 285 holders; KMP and Pegasus took full entitlements. Chairman Denis Wood underwrites the 13.35m-share shortfall, so about $3m is raised before costs. This resolves the raising.
capital raising announcement
2015
- 29 Dec
KGL launches a two-for-nine entitlement offer at 9.5c to raise up to $3m, fully underwritten by Chairman Denis Wood. Cash was $1.4m in December 2015. This is the funding the company lacked after the PFS; funds go mostly to exploration.
capital raising announcement
- 22 Dec
Citing low commodity prices, KGL is cutting administrative costs: John Taylor leaves the board, Simon Milroy steps off the board but stays as CEO, and board fees fall 30%. Denis Wood becomes Chairman, with the workforce also reduced.
director officer appointment
- 22 Oct
Hole KJCD171 at Rockface assayed 13m @ 2.14% Cu, 12.5g/t Ag from 255m, plus 2m @ 2.83% Cu. This resolves the pending assays from September and is the best result of the IP-target program. Off-hole conductors extend 300m below the resource; Rockface is not in the PFS.
drilling result
- 16 Oct
The completed PFS shows Jervois with an 8.25-year life, 21,000tpa copper, C1 cost US$0.88/lb (previously US$1.51/lb), A$189.5m pre-production capex, NPV A$248m, IRR 35% and 3.2-year payback. This resolves the optimisation work. 43.5% of the mining inventory is Inferred, and no Ore Reserve is declared.
resource reserve update
- 29 July
Jervois resource rises 21% to 30.5Mt @ 1.07% Cu, 23g/t Ag, holding 327,000t copper and 22.6Moz silver. Indicated resources up 36% to 11.5Mt; lead-zinc up 59% to 190,000t. This delivers the July update promised and feeds the PFS due October.
resource reserve update
- 22 May
Chairman Andrew Daley, a director since 2005, resigned for personal reasons with immediate effect. Non-executive director Chris Bain is acting Chairman until a replacement is chosen.
director officer appointment
- 15 Jan
Deep hole KJD010W1 assays confirm mineralisation to 860m vertical depth, including 7m @ 2.07% Cu from 1,100m and 2m @ 12.02% Pb. This resolves the open deep-hole thread; three rigs return in February, with a 9,000m RC program.
drilling result
2014
- 8 Dec
Pre-feasibility study update: 2Mtpa, 7-year mine, ~21,000tpa Cu, capex A$189m, C1 cost US$1.51/lb. Board approved a $2.7m extra drilling and metallurgy program, funded from cash, targeting $100-200m more free cash flow before seeking an equity partner.
investor presentation
- 23 Oct
First deep diamond hole at Reward (KJD010W1) hit copper sulphide at 800m vertical depth, 300m below the base of the current resource, including a 10m zone of veins and semi-massive sulphide. Assays are due in 3-4 weeks. Suggests resource could grow at depth.
drilling result
- 15 Sept
Jervois resource rises 85% to 25.3Mt at 1.1% Cu, holding 280,000t copper (up 64%) and 18Moz silver. It also includes 113koz gold and first resources for Cox's Find and Rockface. An exploration target of 50-150kt copper is added. This delivers the long-awaited update.
resource reserve update
- 8 Aug
Reconnaissance drilling found a new shallow copper zone at Morley, east of East Reward (14m @ 2.01% Cu), the fourth parallel trend at northern Jervois. Deep Marshall drilling also extended mineralisation 110m south and 90m below prior drilling. Further drilling is planned from September.
drilling result
- 30 June
Jervois presentation restating the 13.5Mt @ 1.3% Cu resource, with an update due August and PFS September 2014. It outlines a strategy of bringing in a partner for 30-40% project equity to fund deep drilling and the feasibility study, with KGL staying majority owner.
investor presentation
- 27 Mar
EM surveys found conductors including one extending 500m north of Reward in unexplored ground, so Phase 2 drilling starts immediately. The resource update moves from May to August, with the PFS to follow shortly after. This delays the earlier timetable.
drilling result
- 21 Mar
First assays for East Reward in KJCD058: 19m @ 1.95% Cu from 408m, including 2m @ 5.86% Cu. The zone is open to the north and at depth. Extension drilling is planned to bring it into the resource, with follow-up of an EM conductor in April.
drilling result
- 21 Feb
The Murchison gold project sale has settled, with KGL receiving the $15m cash. KGL paid a further $1m to the DOCA creditor fund (on top of $3m in 2013), finalising its DOCA obligations. Remaining funds go to Jervois.
asset acquisition disposition
- 10 Feb
Hole KJCD058 found a new parallel copper zone, East Reward, about 50m east of the existing Reward resource; assays pending. Reward intervals include 14m @ 1.29% Cu. Phase 2 extension drilling is planned from March to bring it into the resource.
drilling result
- 3 Feb
Hole KJCD045 returned an 8m massive sulphide zone at 6.65% copper equivalent, and KJCD048 a further 57m zone at 1.26% copper equivalent below/beside the high-grade interval. The zone is open along strike and down dip; an EM survey is planned for February.
drilling result
2013
- 27 Dec
Binding agreement to sell the Murchison Gold Project for $15m cash, resolving the long-running plan to divest it. Needs Foreign Investment Review Board approval and other conditions; completion expected early February 2014. Proceeds will fund Jervois.
asset acquisition disposition
- 9 Dec
Re-assays lift KJCD048 lead to 19.63% over 18m, copper equivalent to 11.3%. A further 8m massive sulphide zone was hit in KJCD045, 90m north and 50m deeper, indicating the high-grade zone stays open.
drilling result
- 4 Dec
Assays for KJCD048 give 18m @ 0.88% Cu, 15.66% Pb, 3.77% Zn, 726g/t Ag from 287m, about 10.3% copper equivalent, in a previously untested zone about 70m below the existing resource. Follows the 22 November sulphide announcement.
drilling result
- 22 Nov
Diamond hole KJCD048 at Marshall hit a zone over 10m wide of massive sulphides below the existing Inferred resource, with assays due next week. A 13-hole Rockface programme is approved and a third rig added.
drilling result
- 8 Nov
First Jervois exploration results from the new drilling: Rockface returned 24m @ 1.47% Cu from 160m and 9m @ 1.21% Cu, with Morley also hitting copper. Rockface and Morley are called new discoveries; about 8,000m of the 20,000m programme is done and follow-up drilling is planned.
drilling result
- 6 Sept
The 20,000m diamond and RC drilling programme at Jervois has started, with Pinnacle Drilling's two rigs. It aims to substantially increase the resource, and targets reprocessed IP anomalies near Marshall, Reward and Bellbird. Results are not yet available.
drilling spud
- 5 Sept
Robust Resources can earn 51% of CJSC Kentor, which holds Bashkol, by spending A$2m by end 2017, and a further 19% for A$5m by end 2021. A 2,000m drilling programme starts this month. KGL (80% owner) can then focus on Jervois.
farm in farm out agreement
- 23 Aug
Andash sale proceeds received in full, lifting cash to about $14.3m (company now named KGL Resources). $3m goes into trust under the Murchison deed, which is no longer under administrators' control. A 20,000m Jervois drill programme starts 1 September.
asset acquisition disposition
- 11 July
Creditors accepted Kentor's Deed of Company Arrangement for the Murchison subsidiary. Kentor pays $3m into a fund, all creditor claims are extinguished, and control of Murchison returns to Kentor. The deed depends on the Andash sale. Trading resumes.
debt default or forbearance
- 9 July
Shares resume trading 11 July. Andash sale vote is set for 8 August, with A$13.5m due at settlement; A$1.5m deposit already received must be repaid if the vote fails. Cash is only A$0.8m, which the company says would be insufficient to carry on business.
other
- 4 June
Murchison has been put on care and maintenance after stockpile processing ended; its future is undecided. Andash due diligence is done and Robust paid an extra A$500,000 deposit. Kentor expects to seek shareholder approval for the sale, and hold its AGM, in mid-July.
asset acquisition disposition
- 1 May
Kentor signed a binding term sheet to sell Andash to Robust Resources for A$15m (A$1m deposit now, A$14m on completion), targeted for end of June. It needs shareholder approval, due diligence and Robust raising funds. Kentor will focus on Jervois, a strategy change from the Andash development plan.
asset acquisition disposition
- 19 Apr
On the administrators' instructions, open-cut and underground mining at Murchison has been suspended, with processing continuing from existing stockpiles. Kentor shares stay suspended until further notice. This follows the 28 March administration appointment.
production update
- 10 Apr
Geodynamics and Kentor Energy report an initial inferred geothermal resource of 269 PJth at Savo Island, enough in the P50 case for 37 MWe for 30 years. This completes Stage One, giving Geodynamics 25% and operatorship. Exploration drilling targeted for the 2014 dry season.
resource reserve update
- 28 Mar
ASX suspends Kentor shares at the company's request after the financing facility was not obtained and the Murchison subsidiary entered voluntary administration. The company says it cannot say how long the suspension will last; other financing options are being assessed.
listing compliance notice
- 28 Mar
Kentor failed to win final approval for a finance facility needed to fund Murchison, so administrators (Ferrier Hodgson) were appointed to subsidiary Kentor Minerals (WA), which holds the mine. The mine keeps operating for now; shares requested into suspension. Andash and Jervois subsidiaries are not affected.
bankruptcy or receivership
2012
- 20 Dec
Alliance and New Alliance (Murchison) resource rose to 945.5kt at 2.40g/t gold, contained gold up 37% since May 2011. Reserve work and permitting are nearly done, with mining planned to start in the March quarter 2013.
resource reserve update
- 21 Nov
Kentor farms out the Savo geothermal project (licence granted March 2012) to Geodynamics. Geodynamics can earn 25% for $350,000 of studies, then 45% more for $4.65m, reaching 70%. Stage One must finish before September 2013. This acts on the earlier 'may divest' thread.
farm in farm out agreement
- 7 Nov
Jervois resource rises to 13.5Mt at 1.3% copper, holding 170,416t copper (up 13% from 150,500t) and 11.6Moz silver (up 20%). It adds a maiden 69,000oz gold resource, with 60% of copper now Indicated. This delivers the October update; feasibility is under way.
resource reserve update
- 19 Oct
Revised Murchison five-year plan lifts average gold output from 24,000 to 30,700oz a year and cuts cash costs from $1,223 to $1,075/oz. Output so far has been below plan, from low stockpile grades and higher mining costs. A new mining contractor starts 1 November.
production update
- 19 Oct
Murchison NOA 7/8 resource rose to 130,500oz gold, up 43,000oz since May 2011. A first Probable Ore Reserve of 43,560oz (310,487t at 4.36g/t) was declared. A scoping study shows an underground mine life of 26 months, still open at depth.
resource reserve update
- 24 Sept
EMAS concluded Andash as designed is environmentally sound, with its report given to the Commission. New Kyrgyz laws in force from 17 September improve tenure and land access, and exempt gold from income tax in favour of a revenue tax. Site access is still not granted.
regulatory community update
- 22 Aug
Rights issue result: applications covered 15.5m of 34.2m shares offered ($9.3m), leaving a shortfall of about 10.3m shares. KMP underwrites 8.3m shares ($5.0m) and would hold 27.3%. The board invited KMP to nominate a director and says $20.5m has been raised in total.
capital raising announcement
- 13 Aug
Murchison poured its first gold, a 1.13kg dore bar of about 36.3oz, around 90% gold. It is Kentor's first gold production, meeting the end-July first pour target roughly two weeks late, and the mill is running above design throughput.
production update
- 2 Aug
Murchison mill reached its 260,000 tpa design rate within three weeks of first ore, with the first gold pour expected within days. Because of the expected re-rating as a producer, the rights issue closing date was extended to 17 August 2012, other terms unchanged.
production update
- 2 Aug
New high grade shallow copper zone found at Jervois, 80m west of Marshall: hole RJ242 intersected 32m at 1.1% copper, 60.4g/t silver from surface. Assays below 68m are pending. It may add shallow open-cut potential to the feasibility study.
drilling result
- 17 July
Kentor raised A$6.2m via a 10.0m-share placement at $0.62, then announced a 5-for-17 non-renounceable rights issue at $0.60 to raise about $20.5m. KMP, the 14.7% holder, underwrites about $5m of any shortfall. Funds go to Murchison and Jervois.
capital raising announcement
- 20 Apr
On 18 April the Kyrgyz Government asked Parliament to amend the 2011 decree so Andash permits are not revoked, but to require an independent international environmental review. Activity stays suspended until the review and community issue are resolved; committee to consider on 24 April.
regulatory community update
- 3 Apr
Jervois scoping study found strong returns: pre-production capex $234m at 1.5Mtpa (NPV $36.5m, IRR 12%) up to $310m at 2.5Mtpa (NPV $198.7m, IRR 25%). Cash costs are $1.79/lb to $1.61/lb. Company proceeds straight to a feasibility study.
resource reserve update
- 14 Mar
The Kyrgyz Government has asked Parliament to reconsider the June 2011 resolution against Andash. A parliamentary committee, mostly supportive, wants the Government's position clarified by 10 April. Local community approval and site access are still required.
regulatory community update
- 12 Mar
Kentor Energy, a 100% subsidiary, was granted a 3-year geothermal prospecting licence on Savo island, Solomon Islands, to supply power to Honiara. This replaces the discontinued Central Asian geothermal work; a 20MW plant is targeted for 2015-16, with a possible later divestment.
asset acquisition disposition
- 5 Mar
Open pit mining contract at Burnakura awarded to Minepower, with mining due to start in late March subject to final approvals, first at the Reward pit. Plant refurbishment is said to be on schedule for June commissioning.
contract award
- 27 Feb
Drilling inside the planned Lewis pit at Burnakura hit 5m at 102.2g/t gold from 43m (including 1m at 474.5g/t) and 17m at 9.6g/t. Current mined-grade estimate is 1.65g/t, so the company says grade and output could exceed forecasts.
drilling result
- 7 Feb
Board approved Phase 1 of the Murchison Gold Project (Burnakura and Gabanintha), with production due June 2012 at 24,000oz gold a year over three and a half years. Capital is $14.8m ($2m spent); forecast cash cost is $1,223/oz.
material agreement
- 13 Jan
Jervois Inferred Resource rises to 11.9Mt at 1.3% copper and 25.2 g/t silver, holding 150,500t copper and 9.66Moz silver, up 33% and 27% on the 8.8Mt maiden estimate. Exploration target of 50-100kt copper added; scoping study due April, feasibility study planned.
resource reserve update
2011
- 18 July
Maiden Inferred Resource at Gabanintha (WA) of 4.5Mt at 1.4g/t for 203,000oz gold, plus 450,000t at 0.5% copper. Group resources now total 1.4Moz gold, 191,000t copper and 7.6Moz silver. Completes the three Jinka resources.
resource reserve update
- 8 July
Kentor will not take up its option to buy the Aktash gold-copper deposit, saying it has higher funding priorities in Australia and at Andash. It says it recouped the option fee and funds spent. This ends the Aktash thread opened in November 2010.
asset acquisition disposition
- 5 July
Maiden Inferred Resource at Jervois (NT) of 8.8Mt at 1.3% copper and 26.7g/t silver, holding 113,000t copper and 7.6Moz silver, to 200m depth. Diamond drilling continues and a pre-feasibility study starts. This delivers the resource work planned after the Jinka acquisition.
resource reserve update
- 28 June
A Kyrgyz Parliament resolution appears adopted calling for Andash to be suspended and its permits revoked; Kentor expects the Government to reject it, and the Minister says there is no cause for early licence cancellation. A Chui court ruling found for the Prosecutor, which would lift Kentor's AMC stake from 80% to 100%, subject to a 30-day appeal. Kentor still plans to offer 20% to the Government.
regulatory community update
- 30 May
First Burnakura (WA) Inferred Resource of 10.6Mt at 1.5g/t for 516,000oz gold, including 3.2Mt at 2.9g/t for 298,000oz at a higher cut-off. A feasibility study has begun, targeting production by June 2012 at about 300ktpa. This follows the Jinka takeover.
resource reserve update
- 20 May
Kentor warns the Andash timetable will most likely be delayed: village opposition is blocking site access, and the Commission may never report. OVOS approval is expected at the end of the third quarter. Production is required by June 2012 under the mining licence.
regulatory community update
- 17 May
Drilling to start next week at Jervois (NT), acquired via Jinka: 11 diamond holes (1,800m) and 26 RC holes (3,000m), aimed at a first JORC resource. Results shown are historical holes, not new ones. Market cap fell to A$132m.
drilling scheduled
- 12 May
Kentor held 93.78% of Jinka's shares at 11 May, passing the 90% level, and Kentor's directors replaced Jinka's, except Dr Ruane. Plans include resource estimates within three months, Jervois drilling and a Burnakura plant feasibility study.
business combination
- 28 Apr
Kentor held 66.98% of Jinka at 27 April, declared its offer unconditional and extended it by 7 days to 13 May 2011. The 90% acceptance condition no longer applies, so accepting holders will be paid whatever the final level.
business combination
- 1 Apr
Kentor will make an agreed all-cash takeover offer for unlisted Jinka Minerals: 19.5c per share, with options at 3.9c and 9.6c. Total about A$12.8m including related-party debt, from surplus cash. Adds Western Australian and Northern Territory projects, diversifying outside Central Asia. Needs 90% acceptance.
asset acquisition disposition
- 21 Mar
Kentor accepted Macquarie's committed US$50m debt offer: 3-year amortising loan, 4.75% over LIBOR, optional US$6m hedging, drawdown scheduled Q4 2011. Conditions include court and Commission outcomes. Site access is now awaited, with construction taking 12 months from access, so the March 2011 start has slipped.
debt financing
- 4 Feb
Kyrgyz Government is setting up a three-member parliamentary Commission of Enquiry on Andash, with a final report due 1 March 2011. Kentor agreed to suspend on-site activities during the review; off-site work continues. A favourable outcome would keep the schedule. New hurdle for the permits thread.
regulatory community update
- 20 Jan
The Talas Oblast Court rejected ICT's appeal, leaving the ruling that invalidated the minority transfers in place. The 20% not held by Kentor must be offered to the Kyrgyz Government. Kentor says its 80% is unaffected, and calls ICT's separate claim meritless.
regulatory community update
2010
- 14 Dec
The rights issue was completed, raising the maximum A$51.8m at 13c. Applications for entitlements totalled A$46.1m (about 87% of holders), and the A$5.6m shortfall goes to the committed party. With the placement and proposed debt, Andash is fully funded.
capital raising announcement
- 3 Dec
Kyrgyz authorities extended Andash licence obligations by a year: the processing plant is now due by June 2012, citing 2010's political instability. This gives schedule relief and addresses the earlier request to amend the mining licence timing. New licence agreements are to be signed.
regulatory community update
- 30 Nov
Kentor finished drilling at Kurgan (five holes, 615m, 70km from Andash). Gold is widespread, but grades and thicknesses were generally below those needed for a profitable development. Whether to continue in 2011 is undecided. This resolves the awaited Kurgan results, which were disappointing.
drilling result
- 15 Nov
Kentor announced a A$13.4m placement of about 86.5m shares at 15.5c (subject to shareholder approval) plus a 3-for-5 rights issue at 13c to raise A$51.8m, committed by investors. Total A$65.2m completes Andash equity funding alongside the US$50m Macquarie debt.
capital raising announcement
- 9 Nov
Andash approvals are still waiting on a new Kyrgyz government and the village council; Kentor hopes to hold its 2012 schedule. The court ruling would return the 20% minority stake to Kentor's subsidiary, which must offer it to the government for about A$1,000, undermining the Aurum 10% option.
regulatory community update
- 3 Nov
Kentor completed due diligence and signed a binding option agreement with Turan Metals to acquire Aktash, 8km from the planned Andash plant, after drilling 1,500m. This converts the July letter of intent; the 2-5Mt exploration target remains conceptual.
material agreement
- 1 Nov
Board decided to proceed with full-scale development of Andash (capex US$96m, 70koz gold a year, US$29/oz cash cost). Production is targeted for early 2012, with remaining permits expected by year-end. Debt is with Macquarie (US$50m); offtake agreements are under negotiation.
other
- 21 Oct
Independent consultants set an Exploration Target of 5-10Mt at 1-1.5g/t gold for Andash Zones 2 and 3, within about 1.5km of the planned pit. It is conceptual, not a resource, but management says it could add 2-3 years of mine life.
resource reserve update
- 4 Oct
Macquarie Bank was mandated to provide US$50m debt for Andash (capex US$96m), as flagged for the September quarter. It is an indicative term sheet only, with no compulsory hedging. Macquarie must still complete due diligence and approvals before a committed offer.
debt financing
- 31 Aug
Rights issue completed at 6.5c, raising the maximum A$8.3m. Applications totalled A$10.9m, so top-up and shortfall applicants will be scaled back. This completes the raising announced on 29 July alongside the A$4.2m placement.
capital raising announcement
- 29 July
Kentor completed a placement of about 55 million shares at 7.7c to raise A$4.2m, and announced a 2-for-7 non-renounceable rights issue at 6.5c to raise about A$8.3m, with A$7.2m already undertaken. Funds go to Andash development.
capital raising announcement
- 21 July
Kentor signed a Letter of Intent for an 18-month exclusive option to buy 100% of Aktash, 8km from the planned Andash plant. Exploration Target is 2-5Mt at 2-3.5g/t gold (conceptual only, no resource). Option fees US$200k per period; 1,500m drilling required.
asset acquisition disposition
- 23 June
Kentor secured a nine-month exclusive option to buy Aurum's remaining 10% of Andash for US$1.8m, extendable six months for US$150,000. This replaces the terminated US$2.2m deal and would lift Kentor to 90%.
asset acquisition disposition
- 4 June
Updated Andash economics: output rises to 70,000oz gold and 7,400t copper a year, capital falls to US$96m from US$102m, cash cost US$29/oz, NPV US$130m. But financing delays could push development back up to 6 months, with commissioning now March quarter 2012.
resource reserve update
- 11 May
Kentor bought the main 6MW ball mill for Andash from Outotec at a fixed Euro price, over US$1m below the feasibility study budget. It is 10% larger than planned, raising throughput. Most payment is not due until despatch in 2011.
contract award
- 21 Apr
Kentor and Aurum terminated the agreement to buy Aurum's 10% of Andash, because the new Kyrgyz government has placed a moratorium on certain title transfers. Both still intend to complete and are drafting a revised agreement. This reverses the 31 March deal.
asset acquisition disposition
- 31 Mar
Kentor agreed to buy Aurum's remaining 10% of Andash for US$2.2m, payable by 30 July 2010, lifting its stake to 90%. Conditional on due diligence and a pre-emption waiver by local holder ICT. This resolves the earlier Aurum 10% thread.
asset acquisition disposition
- 31 Mar
Definitive Feasibility Study: initial capital US$102.36m (versus US$55.4m in 2007), 60,000oz gold and 6,800t copper a year over 6.5 years, cash cost US$38/oz, NPV US$107m. Reserves 540koz gold. Site works start April, production late 2011.
resource reserve update
- 15 Jan
Savoyardy resource rises 15% to 41,000oz (210,000t at 6.1g/t), over half now Indicated. This delivers the December upgrade expected; the Board's earlier decision to skip early small-scale mining stands, with expanded 2010 drilling planned.
resource reserve update
2009
- 23 Dec
Kentor completed buying Kaldora, which holds 80% of Andash, paying Aurum US$10m plus US$5m for the fleet on 22 December. Development is planned for 2010 and production for 2011. The Board dropped early small-scale Savoyardy mining in favour of enlarging its resource.
asset acquisition disposition
- 14 Dec
Raised A$28m by placing 215m shares at 13 cents, to buy Andash, buy the mining fleet, update the feasibility study and start development. A$25m needs shareholder approval on 15 December. The Macquarie debt facility will not be needed. Savoyardy options are under review.
capital raising announcement
- 27 Nov
Kentor accepted a committed offer from Macquarie Bank for a US$15m facility to fund the Andash purchase, subject to final documentation. It remains one of several options, and a shareholder meeting is set for 15 December.
debt financing
- 13 Nov
Aurum shareholders approved the sale of Andash to Kentor on 12 November, clearing the way for completion on 22 December. Cost is US$15m including the mining fleet. This resolves the Aurum vote; Kentor funding and shareholder approval remain.
farm in farm out completion
- 27 Oct
The share purchase plan raised about $3.1m at 9 cents with no scale-back, shares allotted 30 October. It follows the A$2.0m September placement and funds Andash, Savoyardy and corporate costs.
capital raising announcement
- 26 Oct
Kentor and Aurum signed the Share Purchase Agreement for 80% of Andash, price US$14.85m, completion set for 22 December 2009. Aurum shareholders vote 12 November. Financing is still being finalised. Construction is planned for Q3 2010 and commissioning for Q3 2011.
material agreement
- 20 Oct
Kentor exercised its option to buy Andash; payment to Aurum is due late December 2009. Total cost is US$15m including the mining fleet. Financing is still being finalised and Aurum shareholders vote in early November. Kentor says the weaker US dollar cuts the cost by about A$2.4m.
farm in farm out completion
- 12 Oct
GRD Minproc engaged for a definitive feasibility study update on Andash, due March 2010, to refresh cost estimates and aim to improve gold recovery and concentrate grades. Replaces the 2007 Wardell Armstrong study as the basis for the 2011 production target.
contract award
- 8 Oct
The Kyrgyz government declined its pre-emptive right over Andash, resolving the strategic-asset law concern. The board will exercise the option (due by December) subject to funding and Kentor and Aurum shareholder approval. Price is US$10m, plus US$5m for a separate fleet option.
regulatory community update
- 28 Sept
Andash due diligence completed positively. Aurum agreed to extend the option three months for US$300,000, of which US$150,000 offsets the US$10m price (plus US$5m for mining fleet). Board approves conditional exercise, subject to funding, Kyrgyz waiver of pre-emption right, and both companies' shareholder approval. Feasibility update due March 2010.
material agreement
- 18 Sept
Raised A$2.0m by placing 22.2m shares at 9 cents, a 14.4% discount to the 5-day average. That is more than double July's 4 cent price. A share purchase plan for about 900 holders follows, funding Andash due diligence and feasibility update, Savoyardy and corporate costs.
capital raising announcement
- 16 July
First Andash ore reserve: 540,000oz gold and 63,000t copper, prepared by Wardell Armstrong using US$525/oz gold. The resource, unchanged at about 680,000oz, converts to reserve at a high rate. Still under option, with due diligence under way and 2011 start-up targeted.
resource reserve update
- 14 July
Raised A$1.05m by placing 26.15m shares at 4 cents, about an 11% discount to the recent average price. Funds go to Andash due diligence, Savoyardy and corporate costs. 13.7m shares issue now; 12.45m need shareholder approval around 27 August.
capital raising announcement
- 30 June
Kentor pays US$100,000 for a three-month option to buy 100% of Kaldora, holding 80% of the Andash gold-copper project, for US$10m, plus a fleet option for US$5m. Resource is 680,000oz gold and 77,000t copper. Needs Aurum shareholder approval; extendable by three months for US$150,000.
asset acquisition disposition
- 12 May
Positive Savoyardy pre-feasibility study: about 10,000oz a year for three years, capital about US$1.2m, operating cost about US$370/oz. Company will spend about US$500,000 on pre-development to October, with a development decision late 2009 and 2010 start. Also gained an option to buy 100% from Manas.
material agreement
- 10 Mar
Strategy narrows to Savoyardy: the Chaarkuduk and Yangidavan base metals licences will be relinquished given low metal prices. Akbel sale talks continue but are not near conclusion, with an impairment of about A$2.8m expected. Kurgan and Bashkol exploration continues.
other
- 12 Feb
Savoyardy metallurgy finished: 94% gold recovery into a concentrate of about 50g/t, using simple gravity and flotation, for sale to third parties. Pre-feasibility study now due April 2009, aiming at small-scale production in 2010. Resolves the open metallurgy thread.
other
- 8 Jan
Maiden Savoyardy inferred resource: 35,500oz (160,000t at 6.76g/t gold, 3g/t cut-off, hand mining assumed). It confirms the drilling program that began in 2008. Resource remains open along strike; more drilling planned in 2009 and early production options will be examined.
resource reserve update
2008
- 18 Sept
Kentor terminated the Khantau MOU with Arya Overseas. It cited significant issues found in due diligence plus capital market turmoil, judging a capital-intensive project imprudent. This ends the US$30m Kazakhstan deal; focus returns to Savoyardy, geothermal and base metals.
material agreement termination
- 18 Aug
Kazakh consent obtained to release Khantau data: best intersection 154.5m at 44.1% Fe2O3, 0.6% Cu, 1g/t Au; mineralisation continuous over 400m, open along strike and down dip. 26 magnetic anomalies over 40km. Follows the 31 July MOU; results are the vendor's drilling, partly unverified.
drilling result
- 31 July
Kentor signed an MOU for the Khantau iron oxide copper gold project in southern Kazakhstan (276 sq km). It would pay US$30m for the right to earn up to 51%, with a six-month exclusivity period. A new commodity and country, and a large commitment against recent A$4m raise (inference). Subject to due diligence and shareholder approvals.
material agreement
- 17 June
First two 2008 underground Savoyardy holes returned 9.4m at 13.3g/t gold and 5.5m at 12.8g/t gold. Ten holes (915m) are drilled; more assays are due early July. A maiden JORC resource is still targeted for end of 2008.
drilling result
- 3 June
Placement completed: A$4m raised by issuing 26.6m shares at 15 cents, a 14.5% discount to the recent volume-weighted average price. Managed by Bell Potter; Acorn Capital joins as a shareholder. Funds go to Kyrgyz exploration including Savoyardy. Priced below December's 18c placement.
capital raising announcement
- 12 Mar
Panax Geothermal exercised its option to enter the Kyrgyz geothermal joint venture after a six-month evaluation. It can earn 51% by spending A$5m over four years, and a further 10% for A$1m more. Resolves the September 2007 MOU.
farm in farm out completion
- 10 Mar
Kyrgyz subsidiary was granted new Chaarkuduk (228 sq km, lead/gold) and Kurgan (310 sq km) licences, plus a re-issued Bashkol licence now including two uranium occurrences. The Inylchek geothermal licence was extended to 823 sq km (Akshirak). Craig Irvine joined as General Manager, Exploration.
regulatory community update
2007
- 17 Dec
Placement completed: A$1.35m raised from Far East Capital clients by issuing 7.5m shares at A$0.18, higher than June's A$0.13 placement. Funds go to Savoyardy and Akbel drilling, the new Kyrgyz base metal projects and Dunmarra uranium.
capital raising announcement
- 13 Dec
Best Savoyardy result to date: 15m at 14.2g/t gold from 21m in hole SVD_PD_07, including 2m at 43.9g/t, plus 6.5m at 7.9g/t in SVD_PD_11. The intercept is shallow, only 21m down the hole, extending the earlier high-grade results.
drilling result
- 10 Dec
A 149 sq km prospecting licence (Chunkei) was granted to the 80%-owned Kyrgyz subsidiary in Naryn for lead, zinc and other minerals. Soviet-era lead occurrences average around 20% lead on surface; geophysics is planned, with drilling in 2008. A second base metals permit alongside Yangidavan.
regulatory community update
- 7 Dec
Kentor's 80%-owned Kyrgyz subsidiary was granted a 160 sq km licence in southern Batken for non-radioactive minerals, targeting the Jilisu base metal prospect. Soviet-era sampling reported 8m at 14.6% lead and 272.9g/t silver; drilling is planned for the northern summer. Opens a base metals thread.
regulatory community update
- 27 Nov
Kentor's Dunmarra Uranium lodged three more Northern Territory licence applications, lifting the area applied for to 6,000 sq km. The April 2007 heads of agreement is dropped, so no securities will be issued and Dunmarra stays 100% owned, not 55%.
asset acquisition disposition
- 3 Oct
First Savoyardy hole SVD_PD_09 returned 14m at 15.1g/t gold, about 8m true thickness, roughly 20m below the Soviet adit. Part of a 23-hole program. Early confirmation of the Soviet-era high grades; other holes are still awaiting assay.
drilling result
- 6 Sept
Diamond drilling has started at Savoyardy, a 1,500m program to outline a first JORC resource. It tests 300m of strike to about 90m depth, following Soviet-era workings that showed high-grade gold. Follows the August target; results are the next step.
drilling spud
- 5 Sept
Kentor signs a non-binding MOU with Panax Geothermal to explore its four Kyrgyz geothermal licences. After a 6-month evaluation, Panax can earn 51% by spending A$5m over four years, with an option for 10% more for A$1m. Panax funding lets Kentor focus elsewhere (inference).
joint venture update
- 19 June
Placement completed: A$2.6m raised from Far East Capital clients through 20 million shares at A$0.13, scaled back from demand above that. Funds target Dunmarra uranium, Savoyardy drilling and geothermal. Resolves the raising approved at the AGM, which lifts cash well above the A$868k at March.
capital raising announcement
- 24 May
Perseus announces a joint venture letting Kentor earn 70% of its Savoyardy gold licence in southern Kyrgyzstan by spending US$6m by March 2012. Kentor must spend US$500k by March 2008 to stay in. Effective after due diligence by 23 June 2007.
farm in farm out agreement
- 24 May
Kentor signs a Heads of Agreement to earn 70% of Perseus's Savoyardy gold licence by spending US$6m by March 2012, with US$500k minimum by March 2008. Soviet-era work found gold in trenches and adits; no significant drilling has been done. Adds an advanced gold project.
farm in farm out agreement
- 8 May
Simon Milroy, a mining engineer formerly with Pan Australian Resources in Laos, is appointed Managing Director and CEO from 14 May 2007. He replaces Royle, with McKinnon having been interim CEO. The chair calls it a 'revitalization'.
director officer appointment
- 23 Apr
Heads of Agreement to earn up to 80% of five Northern Territory uranium licence applications (3,020 sq km) via a new subsidiary; Kentor starts at 55%, issuing 1m shares and A$100k at completion, and funding up to A$4m more. Conditional on a capital raising for which AGM approval is sought.
farm in farm out agreement
- 11 Apr
Kentor lodged applications for five geothermal exploration licences in Kyrgyzstan, targeting hot granite above 250°C to generate power for export to China. Areas range from 22 to 3,455 sq km. Only verbal assurance of approval so far. A new direction beyond gold.
asset acquisition disposition
- 23 Feb
Managing Director David Royle resigned for personal reasons, leaving 30 March; Hugh McKinnon becomes CEO until the Akbel drilling review is done. The RD1500 rig is now drilling at Akbel; 1,950m drilled so far, at least 1,050m still needed for licence commitments.
director officer appointment
2006
- 15 Dec
Raised A$625,000 from a placement of 5 million shares at A$0.125 to Haywood Securities clients, plus 2.5 million options subject to approval at the May 2007 AGM. Funds Akbel drilling into 2007 and follows cash of A$1.5M at September.
capital raising announcement
- 31 July
Akbel drilling resumed 20 July after a five-week suspension; six holes are planned by year end. Uzunbulak, Karabalta, Barkol and Kyldoo will be farmed out or relinquished after no medium-sized targets were found, and Perseus left the Kyldoo JV. Effort narrows to Akbel-Bashkol.
quarterly activities report
- 11 Jan
Kyrgyz authorities granted two successor licences to the Ertash licence: Akbel (365 km², four years) and Bashkol (1,259 km², two years). Kentor says this adds certainty to its programs along the Kumtor Trend.
regulatory community update