15 Oct 2026other▲ GoodMajor
KGL's Board approves the Final Investment Decision for Jervois, resolving the long-targeted FID thread. First concentrate remains targeted for H1 2028, capital costs are said to stay consistent with the Baseline Economic Model, and about 60% of project cost is under executed contracts.
KGL receives the second US$16M Wheaton payment, completing the US$32M Early Deposit after FIRB approval and early-works evidence. This closes the open late-September tranche thread. A further US$243M in four tranches remains, conditional on construction milestones.
KGL awards Sedgman the design, procurement and construction contract for the 2.0Mtpa Jervois processing plant, resolving the EPC thread open since August. Scope is increased, but terms are said to match the Baseline Economic Model's capital cost and schedule. FID is flagged for coming weeks.
Corporate Governance Statement and Appendix 4G lodged with the annual report, as required by the listing rules. Administrative compliance filing with no new business information.
KGL releases its FY2026 Annual Report and sets the AGM for 24 November 2026. The chairman says Jervois is fully funded to production with about A$689M of funding, with first copper concentrate targeted in 2028. Largely restates known facts.
S&P Dow Jones Indices' September quarterly rebalance adds KGL to the All Ordinaries index, effective 21 September 2026. It is an index notice, not a company announcement, and carries no new business information.
Gerard Hutchinson joins as independent non-executive director, chairing a newly created Audit & Risk Committee. A Remuneration Committee is also set up, chaired by Lindi Deguara. This adds a fifth director and formalises governance as Jervois nears FID.
KGL signs a ~A$36M contract with Northern Transportables for the Jervois accommodation village. Long-lead mill procurement and drilling have begun. The Sedgman EPC contract is still being finalised. FID stays targeted for Q3 CY2026, with commissioning in H1 CY2028.
30 July 2026security holder rights change▲ GoodMajor
Shareholders approve all EGM resolutions on a poll, including the ~A$180M placement at A$0.20 and share issues to KMP and directors Gerard, Purnamasidi and Deguara. This clears the last condition on the A$300M raising, which funds Jervois alongside the Wheaton stream.
EGM script and slides recap CEO Strohmayr's background, the April 2026 economics (post-tax NPV8 A$839M) and the funding bridge. A$689M total sources against A$439M construction capital leaves a ~A$70M buffer. Targets FID and major contracts in Q3 CY2026. Mostly restates known facts.
24 July 2026capital raising announcement● NeutralMajor
The entitlement offer closes with valid applications for ~333M shares (~A$66.6M); the remaining ~264.6M shares (~A$52.9M) go to the underwriters as shortfall. KMP takes ~41M shortfall shares, lifting it to 36.2%. The A$180M placement still needs shareholder approval.
The A$120M entitlement offer opens at A$0.20, with 1 new share for every 1.29 held on the 30 June record date. It closes 22 July 2026. Offer booklet and forms released; this is the mechanical step of the already announced raising.
29 June 2026capital raising announcement▲ GoodMajor
The ~A$180M conditional placement bookbuild is completed at A$0.20 per share (~902M shares), a 25.2% discount to the last price of A$0.2675. KMP expects to put in ~A$65M and Wheaton joins the register. It needs shareholder approval at an EGM on 30 July.
Presentation supporting the A$300M raising at A$0.20 per share: A$120M entitlement offer and A$180M conditional placement needing shareholder approval. KMP has pre-committed ~A$39.7M of its entitlement; the offer is underwritten by Argonaut and Bell Potter. Restates the raising already announced.
25 June 2026capital raising announcement▲ GoodMajor
KGL launches a A$300M equity raising: a A$180M conditional placement (~902M shares) and a A$120M entitlement offer at 1-for-1.29 (~598M shares). With Wheaton's stream, it is expected to fully fund Jervois. KMP may rise from 33.2% to 36.2%; Wheaton up to A$35M.
KGL receives the first US$16M tranche of the US$32M Early Deposit under the Wheaton stream, lifting available cash to about A$28M (from A$5.5M at 31 May). The second tranche is planned for late September 2026, subject to FIRB and early-works evidence.
KGL's registered office and principal place of business moves to Level 1, 5 Gardner Close, Milton, Queensland, from Eagle Street, Brisbane. Administrative notice only, with no project or financial information.
May 2026 corporate presentation restates the Wheaton package, baseline economics and a 771M share count at A$0.29 (about A$224M market cap). Wheaton funding remains conditional on FIRB approval and other conditions. No new announcements.
CEO Sam Strohmayr receives 500,000 shares plus 500,000 performance rights; the CFO gets 500,000 and the Company Secretary 250,000 rights. Rights vest on raising the remaining funding to FID and a 20-day VWAP above $0.325. Issued under LR 7.1.
The updated baseline economic model lifts Jervois post-tax NPV8 to A$839M (from A$405M) and IRR to 30%, using higher metal prices. Construction capex rises to A$439M and commissioning moves to H1 2028. Further funding is still required.
KGL signs a US$300M silver and gold streaming agreement with Wheaton: US$275M upfront (US$32M early deposit) plus a US$25M cost-overrun facility. Copper stays unencumbered. This is the first major funding for Jervois; Wheaton can join a future equity raise up to A$35M. Capex and revenue are expected to rise.
Half-year accounts to 31 December 2025 restate the quarterly's progress: enabling works, optimisation, short-listed funding partners and the $11M raising. The stated aim is FID, financing close and construction start during 2026. Ms Deguara joined the board 28 November 2025.
18 Dec 2025director officer appointment▲ GoodMajor
Sam Strohmayr, a former Glencore Zinc Australia COO, is appointed CEO from 27 January 2026 on $450,000 a year including super. This ends the CEO search running since Jeff Gerard became executive chairman in January 2025. A Darwin office will open in early 2026.
AGM presentation recapping the year: FSU25, the $4.2m entitlement offer, the $11m placement, 3D modelling and a shortlisted CEO. It says the placement covers corporate costs to mid-2026 and stage 1 enabling works. Mostly restates known facts.
Lindi Deguara is appointed independent non-executive director, effective after the 28 November 2025 AGM, adding a fourth director. The chairman says a CEO shortlist exists and an announcement is expected soon, continuing the open CEO search.
31 Oct 2025capital raising announcement▲ GoodMajor
KGL raises about A$11M in a placement of about 78.57M shares at $0.14, well above the $0.095 offer price in April. RCF rises to about 9.9%. Funds go to enabling works ahead of FID and working capital. A five-member Project Steering Committee is formed, including two RCF nominees.
What it means for a shareholder
78.6m new shares at $0.140 to raise about $11.0m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
October 2025 investor presentation on the fully permitted, 100%-owned Jervois copper project, citing a 29Mt @ 1.8% Cu resource. It accompanies the A$11M placement announced the same day; the visible text shows no new results.
FY2025 annual report: contained copper in the resource rose 8% to 510kt, with 213koz gold and 23Moz silver. Staff and admin costs fell $1.2M (28%) and exploration costs fell $2.7M (20%). Funding talks cover strategic investment, offtake, debt and streaming; no financing is yet secured. Registry is now MUFG.
Appendix 4G for FY2025 stating the corporate governance statement is on pages 16-23 of the annual report. Administrative compliance form with no new information.
Resource Capital Fund joins the register with 8.32% via an off-market share purchase. KGL reports several non-binding finance term sheets received, an open-cut mine plan optimisation, an open-cut mining tender shortlist, and enabling works targeted for late 2025/early 2026. It is also reviewing bismuth in concentrate.