222 since 2006
Last event
15 Oct 2026

Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

10 Aug 2010drilling spud▲ Good

Drilling began at Kurgan 1, 70km south-west of Andash, following up six gold lodes found by 2009 surface sampling (best channel results 7.3g/t over 3m and 5m). The first program is four holes totalling 600m, extended if results are positive.

Discuss in chat

30 July 2010quarterly activities report● Neutral

June quarter report restates improved Andash economics (70koz gold, capex A$96m, US$29/oz), the Aktash option and the placement and rights issue. Drilling has started at Kurgan. A bank is still expected to be mandated for debt in the September quarter; first production targeted early 2012.

Discuss in chat

29 July 2010admin correction● Neutral

Rights issue timetable shifted by two days for a Sydney public holiday: record date 9 August, closing 26 August, new shares trading 6 September 2010. Terms are unchanged.

Discuss in chat

29 July 2010capital raising announcement● Neutral

Offer document for the 2-for-7 non-renounceable rights issue at 6.5c per share, raising about A$8.32m. Closes 24 August 2010 (later amended). Unclaimed entitlements cannot be sold. It formalises the raising announced the same day.

Discuss in chat

29 July 2010capital raising announcement● NeutralMajor

Kentor completed a placement of about 55 million shares at 7.7c to raise A$4.2m, and announced a 2-for-7 non-renounceable rights issue at 6.5c to raise about A$8.3m, with A$7.2m already undertaken. Funds go to Andash development.

What it means for a shareholder

55.0m new shares at $0.077 to raise about $4.2m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.

Create a free account to see this worked out for your own holding.

Discuss in chat

21 July 2010asset acquisition disposition▲ GoodMajor

Kentor signed a Letter of Intent for an 18-month exclusive option to buy 100% of Aktash, 8km from the planned Andash plant. Exploration Target is 2-5Mt at 2-3.5g/t gold (conceptual only, no resource). Option fees US$200k per period; 1,500m drilling required.

Discuss in chat

19 July 2010investor presentation● Neutral

July investor presentation repeats the Andash story: 70koz gold a year, US$29/oz cash cost, US$96.6m capital, aiming for 50% debt and 50% equity. Cash was A$10.4m at 31 March 2010. Reports 59.6m options; no new results.

Discuss in chat

30 June 2010regulatory community update▲ Good

Kyrgyz referendum on 27 June approved a new constitution, with about 70% turnout and over 90% in favour; parliamentary elections are due by 10 October. Kentor says Andash is unaffected, with a debt mandate expected in the September quarter and commissioning in March 2012.

Discuss in chat

23 June 2010asset acquisition disposition● NeutralMajor

Kentor secured a nine-month exclusive option to buy Aurum's remaining 10% of Andash for US$1.8m, extendable six months for US$150,000. This replaces the terminated US$2.2m deal and would lift Kentor to 90%.

Discuss in chat

16 June 2010price query● Neutral

ASX queried the share price fall from 8.9c to 6.4c. Kentor said it knew of no undisclosed information, attributing nothing beyond press reports of ethnic violence in southern Kyrgyzstan, which it says does not directly affect Andash in the north.

Discuss in chat

4 June 2010resource reserve update▲ GoodMajor

Updated Andash economics: output rises to 70,000oz gold and 7,400t copper a year, capital falls to US$96m from US$102m, cash cost US$29/oz, NPV US$130m. But financing delays could push development back up to 6 months, with commissioning now March quarter 2012.

Discuss in chat

28 May 2010agm notice● Neutral

Chairman's and Managing Director's AGM addresses. They say the Kyrgyz change of government has not significantly affected activities, but project financing has slowed as investors and lenders take stock. A financing strategy is being prepared. Market cap is around $35m.

Discuss in chat

11 May 2010contract award▲ GoodMajor

Kentor bought the main 6MW ball mill for Andash from Outotec at a fixed Euro price, over US$1m below the feasibility study budget. It is 10% larger than planned, raising throughput. Most payment is not due until despatch in 2011.

Discuss in chat

30 Apr 2010quarterly activities report● Neutral

March quarter report restates the Andash feasibility study and senior hires. Project financing will now run past the planned June 2010 as lenders assess Kyrgyzstan's situation. Referendum set for 27 June, elections 10 October. Market cap fell to $37m.

Discuss in chat

30 Apr 2010annual report● Neutral

2009 Annual Report, mostly repeating known points: Andash 80% bought in December 2009, advancing to 90%, Ore Reserve 540koz gold, A$28m placement, Savoyardy resource up 15%. Production targeted for 2011. Financial figures are not in the extract.

Discuss in chat

21 Apr 2010asset acquisition disposition▼ BadMajor

Kentor and Aurum terminated the agreement to buy Aurum's 10% of Andash, because the new Kyrgyz government has placed a moratorium on certain title transfers. Both still intend to complete and are drafting a revised agreement. This reverses the 31 March deal.

Discuss in chat

14 Apr 2010regulatory community update● Neutral

Chairman's letter explains the Kyrgyz change of government and restates directors' confidence in Andash. It repeats that there has been no impact on activities and the mobile fleet is almost commissioned. The extract is truncated, so later content is not stated.

Discuss in chat

9 Apr 2010regulatory community update● Neutral

After the April uprising in Kyrgyzstan, Kentor says all staff are safe and there has been no impact on activities. Fleet commissioning continues and Andash site works are still due later in April. Interim government's 10-point plan indicates business as usual.

Discuss in chat

31 Mar 2010asset acquisition disposition▲ GoodMajor

Kentor agreed to buy Aurum's remaining 10% of Andash for US$2.2m, payable by 30 July 2010, lifting its stake to 90%. Conditional on due diligence and a pre-emption waiver by local holder ICT. This resolves the earlier Aurum 10% thread.

Discuss in chat

31 Mar 2010security holder rights change● Neutral

Cancellation of 2.5m expired unlisted options, taking unlisted options to 56.6m. Administrative notice only.

Discuss in chat

31 Mar 2010resource reserve update▲ GoodMajor

Definitive Feasibility Study: initial capital US$102.36m (versus US$55.4m in 2007), 60,000oz gold and 6,800t copper a year over 6.5 years, cash cost US$38/oz, NPV US$107m. Reserves 540koz gold. Site works start April, production late 2011.

Discuss in chat

31 Mar 2010annual report● Neutral

Statutory accounts for the year to 31 December 2009, with the directors' report listing the board and their holdings. The extract provided has no financial figures, so nothing further can be stated.

Discuss in chat

30 Mar 2010director officer appointment● Neutral

Gerard Kelly appointed Chief Financial Officer and Kelvin Russell General Manager Corporate Finance, previously a consultant to Kentor. Hires prepare for Andash development, with site works due next month.

Discuss in chat

18 Mar 2010joint venture update▲ Good

Andash progress update: feasibility update due end of March, EPCM contract being negotiated, key Kyrgyz staff appointed, fleet recommissioning begun, site works due next month and exploration drilling expected in the June quarter.

Discuss in chat

1 Mar 2010investor presentation● Neutral

Schroder conference presentation largely repeats the Andash story. It flags that the updated study is expected to show higher capital and operating costs but better recoveries and production, due March 2010. No new results.

Discuss in chat

16 Feb 2010regulatory community update● Neutral

Review of historical results on the Andash licence compiled two of six other prospects so far: Chonkyshto (historical 23m at 3.29g/t gold) and Jerganak (copper-gold). These are old explorers' results, not new drilling.

Discuss in chat

12 Feb 2010director officer appointment▲ Good

Guy Cordingley appointed General Manager Operations for Andash, a metallurgist with Freeport and Nui Phao experience. Site works are due in April, and project financing is to be progressed in the current half, with early bank interest described as positive.

Discuss in chat

4 Feb 2010drilling result● Neutral

Final 2009 Bekbulaktor (Bashkol licence) bedrock sampling gave best results of 3m at 11.6g/t gold, in fault zones, within a 1.7km anomalous granite zone. Work was cut short by snow; systematic fault sampling is planned from mid-2010.

Discuss in chat

29 Jan 2010quarterly activities report● Neutral

December quarter report covers the completed Andash purchase, the A$28m raise, the feasibility update due March 2010 and site works planned for April. Issued capital is 393m shares. Mostly repeats earlier announcements.

Discuss in chat

15 Jan 2010resource reserve update▲ GoodMajor

Savoyardy resource rises 15% to 41,000oz (210,000t at 6.1g/t), over half now Indicated. This delivers the December upgrade expected; the Board's earlier decision to skip early small-scale mining stands, with expanded 2010 drilling planned.

Discuss in chat