Stockle - the stock oracle

KGL Resources

ASX:KGL
No current share price held for this company.
No price history held for this listing yet.
Market cap
—
Shares on issue
—
Story beats
222 since 2006
Last event
15 Oct 2026

Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

26 May 2011other▼ Bad

At the AGM the Chair says Andash will most likely be delayed: site access now expected later in 2011, a delay of several months, because a vocal local minority opposes it and the village council has not agreed access. Commissioning is still 12 months from site access. Repeats the 20 May update.

Discuss in chat

20 May 2011regulatory community update▼ BadMajor

Kentor warns the Andash timetable will most likely be delayed: village opposition is blocking site access, and the Commission may never report. OVOS approval is expected at the end of the third quarter. Production is required by June 2012 under the mining licence.

Discuss in chat

17 May 2011drilling scheduled▲ GoodMajor

Drilling to start next week at Jervois (NT), acquired via Jinka: 11 diamond holes (1,800m) and 26 RC holes (3,000m), aimed at a first JORC resource. Results shown are historical holes, not new ones. Market cap fell to A$132m.

Discuss in chat

16 May 2011investor presentation● Neutral

May 2011 corporate presentation covering Andash (US$96m capex, US$29/oz, base case NPV US$130m), the Macquarie US$50m debt and about US$71m cash, and the Jinka assets. Says Kentor holds over 94% of Jinka. Repeats known facts.

Discuss in chat

12 May 2011business combination▲ GoodMajor

Kentor held 93.78% of Jinka's shares at 11 May, passing the 90% level, and Kentor's directors replaced Jinka's, except Dr Ruane. Plans include resource estimates within three months, Jervois drilling and a Burnakura plant feasibility study.

Discuss in chat

4 May 2011other● Neutral

Jinka's Supplementary Target's Statement dated 4 May 2011. Only the cover page is provided, so its content is not stated. Administrative document in the takeover process.

Discuss in chat

29 Apr 2011quarterly activities report● Neutral

March quarter: Andash preparation continued, but local on-site activity was suspended during the Commission review, and on-site works are now expected mid-year. Kentor holds 68% of Jinka. Market cap A$154m. Cash figure is not in the text provided.

Discuss in chat

28 Apr 2011business combination▲ GoodMajor

Kentor held 66.98% of Jinka at 27 April, declared its offer unconditional and extended it by 7 days to 13 May 2011. The 90% acceptance condition no longer applies, so accepting holders will be paid whatever the final level.

Discuss in chat

27 Apr 2011annual report● Neutral

2010 Annual Report describes the year as the shift from explorer to mine developer at Andash: US$96m capex, US$29/oz cash cost, A$65.2m equity raised and a US$50m Macquarie debt commitment. Chair says production is 12 months from site access. Largely restates known facts.

Discuss in chat

27 Apr 2011regulatory community update● Neutral

Kyrgyz Supreme Court did not decide the minority participants' appeal but ordered the case retried in the Chui court, date not set. Kentor says its 80% AMC holding is unaffected. ICT's separate claim against Kentor was left without consideration after ICT twice failed to appear.

Discuss in chat

21 Apr 2011other● Neutral

Kentor cancels 1,000,000 unlisted options (expiry 4 June 2015) after an employee resigned. Unlisted options fall to 58.6 million. Administrative only.

Discuss in chat

21 Apr 2011business combination▲ Good

Jinka's Target's Statement: each Jinka director recommends accepting Kentor's offers, absent a superior proposal. Offer period runs to 6 May 2011 unless extended. Only the opening pages are provided, so the detailed reasons are not shown here.

Discuss in chat

21 Apr 2011business combination▲ Good

Kentor reports a 33.66% relevant interest in Jinka at 19 April, from early acceptances of its 19.5c-a-share offer. It will give notice of the status of the offer conditions on 28 April. Shows early support for the takeover.

Discuss in chat

6 Apr 2011investor presentation● Neutral

MD interview restates the Jinka takeover rationale and Andash status: still awaiting the Commission's determination, which asked Kentor to resume community dealings. Says the A$12.8m Jinka cost is covered by about A$71m cash, with the US$50m Macquarie facility available for Andash. Mostly repeats known facts.

Discuss in chat

1 Apr 2011other● Neutral

Intermin Resources, Jinka's largest holder (35% of shares and options), says it will accept Kentor's offer for 19.9% of Jinka's shares, worth about A$1.16m. Third-party release confirming the support already described by Kentor.

Discuss in chat

1 Apr 2011investor presentation● Neutral

Presentation on the Jinka offer: A$7.8m for all shares and options plus repayment of A$4.95m loans, funded from existing cash. Describes Burnakura, Gabanintha and Jervois projects. Repeats the announced terms.

Discuss in chat

1 Apr 2011business combination● Neutral

Formal Bidder's Statement for the Jinka takeover: 19.5c per share, offer dated 6 April and closing 6 May 2011 unless extended. Jinka directors recommend acceptance absent a superior proposal. Formalises the 1 April announcement with no new terms.

Discuss in chat

1 Apr 2011asset acquisition disposition● NeutralMajor

Kentor will make an agreed all-cash takeover offer for unlisted Jinka Minerals: 19.5c per share, with options at 3.9c and 9.6c. Total about A$12.8m including related-party debt, from surplus cash. Adds Western Australian and Northern Territory projects, diversifying outside Central Asia. Needs 90% acceptance.

Discuss in chat

30 Mar 2011annual report● Neutral

Statutory financial report for the year to 31 December 2010, including the directors' report and director details. The text provided is only the opening pages, so no financial results can be stated here.

Discuss in chat

21 Mar 2011debt financing● NeutralMajor

Kentor accepted Macquarie's committed US$50m debt offer: 3-year amortising loan, 4.75% over LIBOR, optional US$6m hedging, drawdown scheduled Q4 2011. Conditions include court and Commission outcomes. Site access is now awaited, with construction taking 12 months from access, so the March 2011 start has slipped.

Discuss in chat

10 Mar 2011regulatory community update● Neutral

Kentor says the Macquarie US$50m debt is still being negotiated as a Committed Letter of Offer. The Commission of Enquiry report, expected 1 March, has not been issued. Both items remain open, so the Andash schedule is still uncertain.

Discuss in chat

4 Mar 2011other● Neutral

S&P index notice listing Kentor Gold among additions to the All Ordinaries index, effective 18 March 2011. Not a company announcement and carries no operational or financial news.

Discuss in chat

25 Feb 2011regulatory community update● Neutral

A minority participant has appealed to the Kyrgyz Supreme Court over the invalidation of its AMC holding. No hearing date is set for this or for ICT's separate claim. Kentor says its 80% is unaffected and the ICT claim has no merit. Continues the minority dispute.

Discuss in chat

8 Feb 2011investor presentation● Neutral

MD interview says Andash is not suspended, only on-site community activities for a month, and the project remains on track for March 2012 commissioning if construction starts in March. Macquarie due diligence expected this month. The only outstanding approval is the environmental licence (OVOS). Mostly restates known facts.

Discuss in chat

4 Feb 2011regulatory community update▼ BadMajor

Kyrgyz Government is setting up a three-member parliamentary Commission of Enquiry on Andash, with a final report due 1 March 2011. Kentor agreed to suspend on-site activities during the review; off-site work continues. A favourable outcome would keep the schedule. New hurdle for the permits thread.

Discuss in chat

31 Jan 2011quarterly activities report● Neutral

Appendix 5B: cash at 31 Dec 2010 was A$71.4m, up from A$14.5m after A$61.5m raised in the quarter. Operating and investing outflow A$4.1m; A$9.8m forecast next quarter. Savoyardy interest fell from earning 70% to 0%: Kentor has withdrawn from the Manas JV.

Discuss in chat

28 Jan 2011quarterly activities report▲ Good

December quarter report: Andash decision to develop, A$65.2m raised, engineering 80% complete, second ball mill bought, licence extended to June 2012. Construction still targeted for March 2011, commissioning early 2012. Savoyardy status and minority ruling also covered. Mostly repeats known facts.

Discuss in chat

20 Jan 2011regulatory community update● NeutralMajor

The Talas Oblast Court rejected ICT's appeal, leaving the ruling that invalidated the minority transfers in place. The 20% not held by Kentor must be offered to the Kyrgyz Government. Kentor says its 80% is unaffected, and calls ICT's separate claim meritless.

Discuss in chat

31 Dec 2010other● Neutral

Kentor's December 2010 securities trading policy for directors and staff, setting closed periods and bans on trading with price-sensitive information. Administrative document with no operational or financial news.

Discuss in chat

31 Dec 2010regulatory community update● Neutral

A Bishkek court suspended ICT's claim against Kentor and Kaldora until ICT's appeal in the Talas case is decided. That appeal hearing was adjourned to 14 January 2011. No change to Kentor's 80%.

Discuss in chat