Each one in plain English, with the numbers worked through for a shareholder.
3 Nov 2010material agreement▲ GoodMajor
Kentor completed due diligence and signed a binding option agreement with Turan Metals to acquire Aktash, 8km from the planned Andash plant, after drilling 1,500m. This converts the July letter of intent; the 2-5Mt exploration target remains conceptual.
Board decided to proceed with full-scale development of Andash (capex US$96m, 70koz gold a year, US$29/oz cash cost). Production is targeted for early 2012, with remaining permits expected by year-end. Debt is with Macquarie (US$50m); offtake agreements are under negotiation.
A Kyrgyz court reportedly invalidated transfers among Andash's minority (20%) shareholders for breaching strategic objects law. Kentor says its 80% is unaffected, as it complied. This bears on the Aurum 10% option thread; official court documents are still awaited.
Independent consultants set an Exploration Target of 5-10Mt at 1-1.5g/t gold for Andash Zones 2 and 3, within about 1.5km of the planned pit. It is conceptual, not a resource, but management says it could add 2-3 years of mine life.
October corporate presentation repeats known Andash economics, reserves (540koz gold), the Macquarie US$50m debt mandate and Aktash option terms. It quotes NPV of US$270m at current prices. No new results or decisions.
Kentor says Kyrgyz elections passed peacefully and Andash's mining licence is issued. Two permits remain: a renewed environmental permit and Kopuro Bazaar village council approval, which could delay the project. Both are expected by year-end; first production still targeted early 2012.
Surface sampling at Bekbulaktor on the Bashkol licence returned 36m at 2.71g/t gold and 24m at 1.7g/t gold, open in three directions. The company plans a 2011 program to identify drill targets; some assays still awaited. Early-stage, no drilling yet.
ASX queried a rise from 10.5c to 19.5c. Kentor knew of no undisclosed information, citing peaceful Kyrgyz parliamentary elections, higher gold and copper prices, the Macquarie mandate, a stronger Australian dollar and a newsletter buy recommendation. It confirmed listing rule compliance.
Macquarie Bank was mandated to provide US$50m debt for Andash (capex US$96m), as flagged for the September quarter. It is an indicative term sheet only, with no compulsory hedging. Macquarie must still complete due diligence and approvals before a committed offer.
Melbourne presentation repeats the Andash economics, Aktash option terms and Kyrgyz political recovery. It says a bank is expected to be mandated for US$50m of project debt within two weeks, targeting 50% debt and 50% equity. No new results.
Half-year to 30 June 2010: loss A$2.16m, cash A$5.8m, A$5.8m spent on Andash. About A$12.5m of equity proceeds are expected in Q3. Directors say going concern is supported by the raisings. Panax is stated to have withdrawn from the geothermal JV in March 2010.
Confirmation to ASX that 127,989,487 rights issue shares were allotted on 1 September 2010, bringing issued capital to 575,952,690 shares. Top-up applications were capped at A$20,000. Largest holder is ANZ Nominees with 13.16%; Macquarie holds 3.66%.
31 Aug 2010capital raising announcement▲ GoodMajor
Rights issue completed at 6.5c, raising the maximum A$8.3m. Applications totalled A$10.9m, so top-up and shortfall applicants will be scaled back. This completes the raising announced on 29 July alongside the A$4.2m placement.
Kentor despatched the rights issue offer document to eligible shareholders; the 2-for-7 offer at 6.5c closes 26 August 2010. No new terms; this is an administrative mailing.
Drilling began at Kurgan 1, 70km south-west of Andash, following up six gold lodes found by 2009 surface sampling (best channel results 7.3g/t over 3m and 5m). The first program is four holes totalling 600m, extended if results are positive.
Rights issue timetable shifted by two days for a Sydney public holiday: record date 9 August, closing 26 August, new shares trading 6 September 2010. Terms are unchanged.
Offer document for the 2-for-7 non-renounceable rights issue at 6.5c per share, raising about A$8.32m. Closes 24 August 2010 (later amended). Unclaimed entitlements cannot be sold. It formalises the raising announced the same day.
29 July 2010capital raising announcement● NeutralMajor
Kentor completed a placement of about 55 million shares at 7.7c to raise A$4.2m, and announced a 2-for-7 non-renounceable rights issue at 6.5c to raise about A$8.3m, with A$7.2m already undertaken. Funds go to Andash development.
What it means for a shareholder
55.0m new shares at $0.077 to raise about $4.2m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
21 July 2010asset acquisition disposition▲ GoodMajor
Kentor signed a Letter of Intent for an 18-month exclusive option to buy 100% of Aktash, 8km from the planned Andash plant. Exploration Target is 2-5Mt at 2-3.5g/t gold (conceptual only, no resource). Option fees US$200k per period; 1,500m drilling required.
July investor presentation repeats the Andash story: 70koz gold a year, US$29/oz cash cost, US$96.6m capital, aiming for 50% debt and 50% equity. Cash was A$10.4m at 31 March 2010. Reports 59.6m options; no new results.
Kyrgyz referendum on 27 June approved a new constitution, with about 70% turnout and over 90% in favour; parliamentary elections are due by 10 October. Kentor says Andash is unaffected, with a debt mandate expected in the September quarter and commissioning in March 2012.
23 June 2010asset acquisition disposition● NeutralMajor
Kentor secured a nine-month exclusive option to buy Aurum's remaining 10% of Andash for US$1.8m, extendable six months for US$150,000. This replaces the terminated US$2.2m deal and would lift Kentor to 90%.
ASX queried the share price fall from 8.9c to 6.4c. Kentor said it knew of no undisclosed information, attributing nothing beyond press reports of ethnic violence in southern Kyrgyzstan, which it says does not directly affect Andash in the north.
Updated Andash economics: output rises to 70,000oz gold and 7,400t copper a year, capital falls to US$96m from US$102m, cash cost US$29/oz, NPV US$130m. But financing delays could push development back up to 6 months, with commissioning now March quarter 2012.
Kentor bought the main 6MW ball mill for Andash from Outotec at a fixed Euro price, over US$1m below the feasibility study budget. It is 10% larger than planned, raising throughput. Most payment is not due until despatch in 2011.
2009 Annual Report, mostly repeating known points: Andash 80% bought in December 2009, advancing to 90%, Ore Reserve 540koz gold, A$28m placement, Savoyardy resource up 15%. Production targeted for 2011. Financial figures are not in the extract.
Kentor and Aurum terminated the agreement to buy Aurum's 10% of Andash, because the new Kyrgyz government has placed a moratorium on certain title transfers. Both still intend to complete and are drafting a revised agreement. This reverses the 31 March deal.
Chairman's letter explains the Kyrgyz change of government and restates directors' confidence in Andash. It repeats that there has been no impact on activities and the mobile fleet is almost commissioned. The extract is truncated, so later content is not stated.
After the April uprising in Kyrgyzstan, Kentor says all staff are safe and there has been no impact on activities. Fleet commissioning continues and Andash site works are still due later in April. Interim government's 10-point plan indicates business as usual.
31 Mar 2010asset acquisition disposition▲ GoodMajor
Kentor agreed to buy Aurum's remaining 10% of Andash for US$2.2m, payable by 30 July 2010, lifting its stake to 90%. Conditional on due diligence and a pre-emption waiver by local holder ICT. This resolves the earlier Aurum 10% thread.