Each one in plain English, with the numbers worked through for a shareholder.
3 July 2012resource reserve update▲ Good
Heap leach test work at Murchison shows predicted gold recoveries of 44% to 91%, with the main low-grade deposits at 60% or better. Heap leach completion is estimated at $7.5m, using equipment bought from Indee for $1.1m. It follows the Phase 2 plan.
July 2012 company presentation restating known facts: Murchison production from mid-2012, Jervois feasibility targeting 2014 and Andash awaiting local approval. It shows cash of $27.4m at 30 March 2012 and 5.8m unlisted options.
More Jervois diamond drilling copper results, including 21.4m at 3.0% copper at Marshall and 4.2m at 6.6% copper at Reward. Diamond tails are on target for mid-July and the RC rig is due to demobilise soon.
NOA 7&8 drilling program is complete, with results such as 11m at 4.0g/t gold. Resource modelling will begin to try to add them to the mine plan. Murchison wet commissioning of the plant began 25 June, with milling expected in early July.
Jervois metallurgical drilling returned near-surface copper-lead-zinc-silver results, including 60m at 1.73% copper and 113.3g/t silver. The MD expects gold can be included in an upgraded resource. Diamond drilling finishes mid-July; RC drilling nearly done.
High-grade gold from RC drilling at NOA 7&8, Burnakura, including 8m at 9.9g/t and 3m at 13.9g/t. These pits are not in the current mine plan; the company says they may add resources and underground potential at NOA 2.
AGM addresses. The Chairman attributes the recent share price fall partly to uncertainty over Andash, says the Board remains frustrated after waiting at least 18 months for approval, but intends to keep its equity and pursue development. Murchison is on schedule for mid-year start-up.
More near-surface Jervois copper results, including 53.5m at 1.08% copper (RJ202) and 12m at 3.72% copper (RJ206). Twin holes continue to match historical drilling, supporting confidence in the resource ahead of the feasibility study.
The Kyrgyz Government's minister told a 15 May parliamentary committee meeting of plans for an independent international environmental audit of Andash. Kentor will cooperate; the company calls this a step towards final local approval. No site access or timing yet.
Mining is underway at Murchison and the crushing circuit is commissioned, with 3,000t of stockpiled ore crushed. Grinding circuit commissioning starts in June; the project is stated to be on budget and on schedule for a mid-year start-up.
First 2012 feasibility-study hole at Jervois Reward returned 33.8m at 1.79% copper and 28.48g/t silver, twinning a historical hole. Mineralisation extends beyond current resource blocks, suggesting resource growth; drilling is due to finish in July.
RC drilling at Federal North, Burnakura, returned high-grade gold such as 5m at 5.10g/t and 2m at 12.10g/t. It is not in the current resources or mine plan; drilling at nearby Federal City is to follow before resources are updated.
High-grade gold intersected near the historic Alliance pit at Murchison, including 9m at 4.1g/t and 11m at 3.6g/t. Alliance is not in the Phase 1 mine plan but is likely to be added after resource modelling; resource update due in the June quarter, with a reserve estimate in the September quarter.
March quarter report restating known events: Jervois scoping study, Murchison approval and mid-2012 start-up, and Government moves on Andash. Jervois 2.5Mtpa case gives about 26,000t copper a year. Share capital is shown as 1,062.1 million shares, consistent with earlier records.
2011 Annual Report, titled 'Into Production 2012'. It restates known points: global resources of 1.4Moz gold, 0.23Mt copper and 9.7Moz silver, Murchison production mid-2012, and Andash awaiting site access with 2013 production if approved. The text provided shows no new financial figures.
20 Apr 2012regulatory community update● NeutralMajor
On 18 April the Kyrgyz Government asked Parliament to amend the 2011 decree so Andash permits are not revoked, but to require an independent international environmental review. Activity stays suspended until the review and community issue are resolved; committee to consider on 24 April.
More high-grade gold from drilling at Burnakura's planned Lewis pit, including 1m at 55.3g/t and 2m at 56.4g/t. This extends the earlier Lewis results; mining there is due in the second half of 2012, and plant construction stays on schedule for mid-year.
MD interview restating the Jervois scoping study and feasibility plans. Murchison is on budget for mid-year commissioning, and Andash has no Government decision yet by the 10 April deadline. Largely restates known facts.
Jervois scoping study found strong returns: pre-production capex $234m at 1.5Mtpa (NPV $36.5m, IRR 12%) up to $310m at 2.5Mtpa (NPV $198.7m, IRR 25%). Cash costs are $1.79/lb to $1.61/lb. Company proceeds straight to a feasibility study.
Full-year statutory accounts for the year to 31 December 2011. The text provided covers only the directors' report and director details, with no financial figures readable, so no results are stated here.
The Kyrgyz Government has asked Parliament to reconsider the June 2011 resolution against Andash. A parliamentary committee, mostly supportive, wants the Government's position clarified by 10 April. Local community approval and site access are still required.
12 Mar 2012asset acquisition disposition▲ GoodMajor
Kentor Energy, a 100% subsidiary, was granted a 3-year geothermal prospecting licence on Savo island, Solomon Islands, to supply power to Honiara. This replaces the discontinued Central Asian geothermal work; a 20MW plant is targeted for 2015-16, with a possible later divestment.
Open pit mining contract at Burnakura awarded to Minepower, with mining due to start in late March subject to final approvals, first at the Reward pit. Plant refurbishment is said to be on schedule for June commissioning.
Drilling inside the planned Lewis pit at Burnakura hit 5m at 102.2g/t gold from 43m (including 1m at 474.5g/t) and 17m at 9.6g/t. Current mined-grade estimate is 1.65g/t, so the company says grade and output could exceed forecasts.
Interview with the MD restating the four-stage Murchison plan, Phase 1 capital of $14.8m and June production. Andash still awaits social licence; Jervois scoping study due next month. Largely restates known facts.
Investor presentation repeating known facts: Andash awaiting final approvals, Jervois 150,500t copper Inferred resource, and Murchison Stage 1 restart in June 2012 for $14.8m. Murchison total Inferred resource is shown as 719,000oz gold. No new announcements.
Board approved Phase 1 of the Murchison Gold Project (Burnakura and Gabanintha), with production due June 2012 at 24,000oz gold a year over three and a half years. Capital is $14.8m ($2m spent); forecast cash cost is $1,223/oz.
Clarifies the quarterly report: Burnakura is a staged development, Stage 1 an expansion and restart of the CIL plant, Stage 2 adds heap leach. Stage 1 feasibility study due within two weeks; Stage 2 in April 2012.
December quarter report: Jervois resource lifted to 150,500t copper and 9.66Moz silver. Burnakura feasibility study is nearing completion for a mid-2012 start; Andash awaits a formal village social licence meeting. Largely restates known announcements.