27 Sept 2011investor presentation● Neutral
September investor presentation restating Andash economics (capex US$96m, cash cost US$29/oz), the Burnakura expansion phases and the Jervois and Gabanintha resources. Says Andash is fully funded and flags project financials as under review. Mostly known facts.
MD interview restating known plans: Jervois updated resource before year end, a four-phase Burnakura plan with mid-2012 restart at 250,000 tpa, and a Burnakura study due in October. Cash is A$43.7m. No new results.
Written Chui court decision found for the General Prosecutor that the 20% minority transfer in Andash was invalid. Kentor must re-register Andash as 100% owned by Kaldora, then offer the 20% to the Kyrgyz Government. Further appeal is still possible.
Contract let to refurbish and recommission the Burnakura plant and move Indee Gold equipment to site; equipment is arriving. Stage one targets 250,000 tpa, with mid-2012 first gold still on track. A 60-hole air core program started and an 8,000m RC program is planned for October.
Jervois diamond hole returned 72m at 3.27% copper, 51.33 g/t silver and 1.16 g/t gold from 414m (about 16m true width), the best result to date. Reward mineralisation is open at 450m depth; an updated resource will follow remaining assays.
Half-year to 30 June 2011: loss of A$933,549 and cash of A$43.7m, after the Jinka purchase. Directors say cash plus the undrawn US$50m Macquarie facility can fund the expected Andash development cost. Burnakura stage one now targets 250,000 tpa.
Regional RC drilling at Jervois found new copper-silver mineralisation, best 6m at 3.18% copper, 23.55 g/t silver and 0.45 g/t gold from 59m (hole RJ194), between known resources. Diamond drilling is due to finish next month, with more results to come.
First three Jervois diamond holes hit copper-silver below the 200m base of the 8.8Mt resource, best 8.1m at 2.56% copper and 13.45 g/t silver. Management says a considerably larger resource is possible; updated estimate follows drilling, due to finish in September.
Maiden Inferred Resource at Gabanintha (WA) of 4.5Mt at 1.4g/t for 203,000oz gold, plus 450,000t at 0.5% copper. Group resources now total 1.4Moz gold, 191,000t copper and 7.6Moz silver. Completes the three Jinka resources.
8 July 2011asset acquisition disposition● NeutralMajor
Kentor will not take up its option to buy the Aktash gold-copper deposit, saying it has higher funding priorities in Australia and at Andash. It says it recouped the option fee and funds spent. This ends the Aktash thread opened in November 2010.
MD interview on the Jervois resource: open along strike and down dip, an updated resource expected before year end, pre-feasibility under way, and a Gabanintha resource due next week. Repeats announced facts. Only part of the text is provided.
Maiden Inferred Resource at Jervois (NT) of 8.8Mt at 1.3% copper and 26.7g/t silver, holding 113,000t copper and 7.6Moz silver, to 200m depth. Diamond drilling continues and a pre-feasibility study starts. This delivers the resource work planned after the Jinka acquisition.
A Kyrgyz Parliament resolution appears adopted calling for Andash to be suspended and its permits revoked; Kentor expects the Government to reject it, and the Minister says there is no cause for early licence cancellation. A Chui court ruling found for the Prosecutor, which would lift Kentor's AMC stake from 80% to 100%, subject to a 30-day appeal. Kentor still plans to offer 20% to the Government.
Kentor bought a heap leach plant and equipment from Range River Gold (in administration) for A$1.3m from cash, to help restart Burnakura at a larger capacity and possibly add a heap leach operation. Production is still aimed at 2012.
Interview with the MD on the Jinka assets: Burnakura plant restart targeted for June 2012 via a four-month feasibility study, Jervois seen as potentially most valuable long term, and Gabanintha and Jervois resources due about end of June. Andash remains main focus. Mostly restates known plans.
Updated company constitution, amended 26 May 2011 (the AGM date). Only the contents pages are provided, so the nature of the changes is not stated. Administrative document.
First Burnakura (WA) Inferred Resource of 10.6Mt at 1.5g/t for 516,000oz gold, including 3.2Mt at 2.9g/t for 298,000oz at a higher cut-off. A feasibility study has begun, targeting production by June 2012 at about 300ktpa. This follows the Jinka takeover.
At the AGM the Chair says Andash will most likely be delayed: site access now expected later in 2011, a delay of several months, because a vocal local minority opposes it and the village council has not agreed access. Commissioning is still 12 months from site access. Repeats the 20 May update.
Kentor warns the Andash timetable will most likely be delayed: village opposition is blocking site access, and the Commission may never report. OVOS approval is expected at the end of the third quarter. Production is required by June 2012 under the mining licence.
Drilling to start next week at Jervois (NT), acquired via Jinka: 11 diamond holes (1,800m) and 26 RC holes (3,000m), aimed at a first JORC resource. Results shown are historical holes, not new ones. Market cap fell to A$132m.
May 2011 corporate presentation covering Andash (US$96m capex, US$29/oz, base case NPV US$130m), the Macquarie US$50m debt and about US$71m cash, and the Jinka assets. Says Kentor holds over 94% of Jinka. Repeats known facts.
Kentor held 93.78% of Jinka's shares at 11 May, passing the 90% level, and Kentor's directors replaced Jinka's, except Dr Ruane. Plans include resource estimates within three months, Jervois drilling and a Burnakura plant feasibility study.
Jinka's Supplementary Target's Statement dated 4 May 2011. Only the cover page is provided, so its content is not stated. Administrative document in the takeover process.
Kentor held 66.98% of Jinka at 27 April, declared its offer unconditional and extended it by 7 days to 13 May 2011. The 90% acceptance condition no longer applies, so accepting holders will be paid whatever the final level.
2010 Annual Report describes the year as the shift from explorer to mine developer at Andash: US$96m capex, US$29/oz cash cost, A$65.2m equity raised and a US$50m Macquarie debt commitment. Chair says production is 12 months from site access. Largely restates known facts.
Kyrgyz Supreme Court did not decide the minority participants' appeal but ordered the case retried in the Chui court, date not set. Kentor says its 80% AMC holding is unaffected. ICT's separate claim against Kentor was left without consideration after ICT twice failed to appear.
Jinka's Target's Statement: each Jinka director recommends accepting Kentor's offers, absent a superior proposal. Offer period runs to 6 May 2011 unless extended. Only the opening pages are provided, so the detailed reasons are not shown here.
Kentor reports a 33.66% relevant interest in Jinka at 19 April, from early acceptances of its 19.5c-a-share offer. It will give notice of the status of the offer conditions on 28 April. Shows early support for the takeover.