2 Mar 2026drilling progress report▲ Good
Phase 1 construction is about 92% complete (85% on 16 February), with nanofiltration plant assembly on schedule. First lithium chloride concentrate is targeted for H1 2026 and the first shipment for H2 2026.
Each one in plain English, with the numbers worked through for a shareholder.
2 Mar 2026drilling progress report▲ Good
Phase 1 construction is about 92% complete (85% on 16 February), with nanofiltration plant assembly on schedule. First lithium chloride concentrate is targeted for H1 2026 and the first shipment for H2 2026.
16 Feb 2026drilling progress report▲ Good
Nanofiltration plant has arrived at Hombre Muerto West and on-site assembly has begun; sylvinite ponds are complete. Phase 1 is about 85% built, with first processed brine expected early Q2 2026 and first lithium chloride concentrate in H1 2026.
15 Dec 2025drilling progress report▲ Good
Phase 1 nano-filtration plant has been assembled and tested in Sydney and is in transit, expected in South America early 2026; liners on Ponds 4 and 5 are complete. Galan is starting to evaluate lifting Phase 1 from 4,000 tpa back toward about 5,400 tpa LCE. First production still H1 2026.
10 Sept 2025drilling progress report▲ Good
Phase 1 construction at Hombre Muerto West progresses: Pond 4 design is complete (sized for 4,000 tpa LCE) and Authium's nano-filtration plant is being built in Sydney, with 99% sulphate removal in testwork. Delivery is due December 2025, commissioning January 2026, first production H1 2026.
29 Jan 2025resource reserve update▲ GoodMajor
Candelas resource grows more than 150% to 1.6Mt LCE (from 685kt in 2019), lifting Galan's total to 9.5Mt LCE. HMW is unchanged at 7.9Mt, which differs from the 8.6Mt total booked in March 2024. Galan says it ranks in the global top 10.
27 Mar 2024resource reserve update▲ GoodMajor
Total resource rises 18% to 8.6Mt LCE at 859mg/L Li (previously 7.3Mt), mainly from adding the Catalina tenure (~1.3Mt LCE). The HMW Measured category is 4.7Mt LCE at 866mg/L. This is Galan's fourth major upgrade since the March 2020 maiden resource.
9 Jan 2024drilling progress report▲ Good
Pond 1 earthworks are almost complete and liner installation has started (5%). Pond 2 earthworks are 10% done and nine production wells are built against six needed for Phase 1. Pond fill is still expected in Q1 2024; a Glencore site visit is being planned.
21 Dec 2023drilling progress report▲ Good
Pond 1 is 85% complete, with liner installation due before year end and fill still expected in Q1 2024. The Phase 2 environmental impact assessment has been lodged with Catamarca, and Glencore due diligence continues.
6 Dec 2023drilling progress report▲ Good
Construction update: Pond 1 is 65% complete, liners are on site with installation due late December, and pond fill remains expected in Q1 2024. Glencore technical due diligence has begun, a step toward the prepayment facility.
4 Oct 2023farm in farm out agreement● NeutralMajor
Galan signs a binding 50/50 JV with Redstone, which manages it, to acquire 100% of the Taiga, Camaro and Hellcat lithium projects (5,187 ha) in James Bay, Quebec, plus an option over the PAK projects (1,415 ha) in Ontario. Adds Canadian exploration alongside Argentina; terms not visible.
3 Oct 2023resource reserve update▲ GoodMajor
Phase 2 DFS for HMW: 21ktpa LCE from H2 2026, post-tax NPV8% US$2 billion, IRR 43%, incremental capex US$278m (total US$382m ex-contingency), opex US$3,510/t. Ore Reserve is 806kt LCE. Offtake/funding talks for Phase 1 are described as advanced.
21 Sept 2023drilling result▼ BadMajor
Greenbushes South maiden program finished at eight diamond holes for 3,885m, with final assays showing no significant lithium mineralisation. The company says the pegmatite exploration model is validated and further drilling is being planned closer to the Donnybrook-Bridgetown Shear Zone.
2 Aug 2023drilling scheduled▲ GoodMajor
Galan sets an exploration target of 500kt to 1.5Mt LCE at 953-988 mg/L for the newly consolidated Catalina tenure, which overlaps 5,954 hectares of HMW tenements. About 1,000m of three-hole drilling is planned. This is conceptual, not a resource.
3 July 2023resource reserve update▲ GoodMajor
Phase 1 DFS for HMW: 5.37ktpa LCE as 6% lithium chloride from H1 2025, post-tax NPV8% US$460m, IRR 36%, capex US$104m before contingency, opex US$3,963/t. Funding will likely be required, possibly dilutive. Phase 2 (20ktpa) DFS now due September 2023.
1 May 2023resource reserve update▲ GoodMajor
HMW resource rises about 14% to 6.6Mt LCE at 880 mg/l, with 4.7Mt (72%) Measured, up from 5.8Mt in October 2022. Including Candelas, total is 7.3Mt at 852 mg/l. Third upgrade since March 2020's 1.08Mt.
6 Mar 2023drilling spud● NeutralMajor
Maiden 2,500m drilling has started at Greenbushes South, about 3km from the Greenbushes mine. The site team notes minerals associated with lithium pegmatites near surface. No assay results yet.
1 Mar 2023drilling result▲ GoodMajor
Santa Barbara exploration well SB-01-23 reached 455m, and airlift testing averaged 829 mg/L lithium, extending the HMW resource area to a new tenement. Drilling of three new production wells has started, the first at Rana de Sal I.
27 Feb 2023drilling scheduled▲ Good
Program of works approved for the maiden Greenbushes South drilling, which was pending in December. About 2,500m of diamond drilling is set to start 1 March 2023. Ground geophysics is under way and about 550 more soil samples are submitted.
20 Dec 2022drilling scheduled▲ GoodMajor
Galan identified three maiden drill targets at Fry's Block in Greenbushes South, now 100% owned after the Lithium Australia buyout. A five-hole diamond program is planned from late January 2023, pending program of works approval. No drilling results yet.
24 Oct 2022resource reserve update▲ GoodMajor
HMW resource rises 2.5x (about 158%) to 5.8Mt LCE at 866 mg/l Li, including a first Measured resource of 4.4Mt (76%). Replaces the earlier ~2.3Mt; total with Candelas is 6.5Mt. DFS now guided to Q1 2023, a shift from end-CY2022.
1 Aug 2022drilling result▲ GoodMajor
Greenbushes South: a second, larger outcropping pegmatite found, three outcrops across about 500m x 400m and possibly continuing along strike. First soil assays show lithium up to 215 ppm. Extends the June GS11 find; ground geophysics under way, no drilling yet.
15 June 2022drilling result▲ GoodMajor
Greenbushes South: airborne data identified 18 lithium pegmatite targets, and mapping of the first, GS11, found an outcropping pegmatite lens about 200m x 40m. Assays are pending and further fieldwork is due from July. No drilling yet; follows the March soil results.
31 May 2022drilling progress report▲ Good
Long-term pumping tests begin at HMW across four wells at Pata Pila and Rana de Sal, expected to finish by end Q3 2022. The data feeds the reserve model, and the feasibility study remains on track for end-2022. Follows the May start flagged earlier.
7 Apr 2022drilling result▲ GoodMajor
Diamond hole PP-02-22 at Pata Pila reached 450m, showing sand-dominated, brine-bearing layers with high porosity about 800m east of the earlier hole. It supports resource upside and feeds the Q3 2022 resource update. Brine filling of pilot pond S1 has begun.
31 Mar 2022drilling progress report▲ Good
HMW update: feasibility study on track for end-2022, two pumping boreholes drilled and tested, pilot pond ready for brine filling. A TEM survey found new resource targets; the resource update is now due Q3 2022, with drilling continuing through 2022.
24 Mar 2022drilling result▲ Good
Greenbushes South soil assays (425 soil, 14 rock chip samples) show anomalous pathfinder elements near the Donnybrook-Bridgetown Shear Zone, giving possible pegmatite targets. Airborne geophysics is complete and being processed; no drilling yet. Resolves the awaited soil assays.
13 Dec 2021drilling progress report▲ Good
HMW update: pilot plant evaporation ponds under construction (operational Q1 2022), a rotary rig is drilling at Rana de Sal with a second due January, and a geophysical survey has started. Drilling is expected to finish in H1 2022, followed by a resource update.
9 Dec 2021resource reserve update▲ GoodMajor
Updated HMW economic study lifts pre-tax NPV to US$2,193m from US$1,011m (IRR 37.5%) purely by raising the lithium price assumption to US$18,594/t; capex US$439M and 20,000tpa unchanged. Combined with Candelas, NPV is US$3.4b. Still a preliminary study.
30 Nov 2021resource reserve update▲ GoodMajor
Candelas scoping study (PEA) shows pre-tax NPV of US$1,225m, IRR 27.9%, capex US$408M for 14,000tpa lithium carbonate over 25 years, using a US$18,594/t long-term price. Delivers the scoping study due Q4 2021; preliminary only, not a reserve.
15 Nov 2021drilling result▲ Good
Deep radar survey at Greenbushes South (80% Galan) confirmed the Donnybrook-Bridgetown Shear Zone extends onto the tenements to 40-50m depth, with three possible buried pegmatite-like targets. Over 400 soil samples await assays. Early-stage; no drilling yet.