The story so far
The events that changed the company's story, in plain English, each written against everything known about the company at the time. The dot shows whether it was good, bad or neutral for shareholders.
2026
- 1 Oct
Chairman Richard Homsany resigned effective immediately on 1 October 2026; director Daniel Jimenez, a 28-year SQM lithium executive, becomes Non-Executive Chairman. No reason for the resignation is given. The board says Jimenez is well placed to lead the transition to production.
director officer appointment
- 24 Sept
First lithium chloride concentrate sales are still on track for Q4 CY2026, but the 4 ktpa throughput target now slips to H1 CY2027 (earlier text said within 2026). Severe winter hampered work; Authium plans an extra pressure vessel skid. Phase 1 expansion earthworks to 5.2 ktpa have started, with higher volumes expected H2 2027.
production update
- 28 May
Wet commissioning is complete and first processed lithium chloride is in the final evaporation ponds at Hombre Muerto West. Concentrate is expected in about 3 months, with sales in H2 2026. Stabilised production is not yet achieved; 4 ktpa is the target.
production update
- 1 Apr
Phase 1 construction at Hombre Muerto West is complete, and the project moves to testing and commissioning. Brine inventory is about 10,000t LCE. Production starts at 4 ktpa with the 5.2 ktpa expansion targeted for H1 2027; first concentrate H1 2026, shipment H2 2026.
production update
- 29 Jan
Galan raises A$40M at A$0.41 per share (2% premium to 5-day VWAP), with Clean Elements participating, plus A$1M from directors subject to shareholder approval. Funds expand Phase 1 from 4 to 5.2 ktpa LCE, Greenbushes South exploration and working capital. This is a much higher price than the A$0.11 Clean Elements paid.
capital raising announcement
2025
- 5 Nov
Clean Elements pays the second A$10M tranche early, completing its A$20M placement (A$0.11 per share, per the earlier announcement). Galan says Phase 1 is fully funded, with no debt and access to the US$6M Authium prepayment facility. Clean Elements' Ofer Amir will join the board as a non-executive director before year end.
capital raising announcement
- 21 Oct
Galan is granted exploration licence E70/4889 and three prospecting licences about 2 km along strike from the Greenbushes mine, next to its existing Greenbushes South ground. It is also exploring joint ventures, sales or a spin-off of its Greenbushes South and James Bay exploration assets; no certainty any deal proceeds.
regulatory community update
- 25 Aug
Clean Elements confirms all conditions met for the A$20M placement, after shareholder approval on 22 August. Tranche 1 (A$10M) settles within five business days; tranche 2 (A$10M) by 22 November 2025. Galan says Phase 1 is now fully funded.
capital raising announcement
- 1 Aug
Galan uses its Acuity at-the-market facility to raise A$2M via 15M set-off shares at A$0.133. This reduces Acuity's collateral shares to zero, so the facility cannot be used again; the company does not intend further use in 2025.
capital raising announcement
- 25 July
Argentina's RIGI committee approves the large-investment incentive regime for HMW, resolving the application lodged October 2024. Benefits include a 25% corporate tax rate and 30 years of fiscal stability. Official approvals still to come.
regulatory community update
- 20 June
Galan secures a binding A$20M placement at A$0.11 (21% premium to the A$0.091 close) from existing shareholder Clean Elements, with one A$0.15 three-year option per two shares. Subject to due diligence and shareholder approval; described as final Phase 1 funding. Debt terms were unfavourable.
capital raising announcement
- 16 Apr
Galan signs binding offtake and operating agreements with Authium: 45kt LCE over 6-12 years, US$6M prepayments, and Authium funds the HMW processing plant, removing A$41.5M capex. A ~A$13M placement at A$0.11 plus up to A$4M SPP follows. Replaces Chemphys MOU; first production still H1 2026.
material agreement
- 14 Apr
Galan requested a voluntary trading suspension from 14 April 2025, pending a definitive offtake agreement and capital raise announcement. It was due to last until 16 April at most. Signals a funding deal is close.
listing compliance notice
- 3 Apr
Routine secondary trading notice for 5.7M ATM shares, but it discloses that Galan rejected an unsolicited non-binding US$150M cash proposal from Huayou Cobalt and Renault for HMW and Candelas. The board called it opportunistic and undervaluing, citing near-term offtake and financing.
other
- 31 Jan
December quarter: about 7,900t LCE in ponds, cash A$3.6M, Chemphys US$3M received. First Phase 1 production is now targeted for H1 2026, later than the H2 2025 target, with timing adjusted for financing and offtake talks. Prepayment facility still targets Q1 2025 close.
quarterly activities report
- 29 Jan
Candelas resource grows more than 150% to 1.6Mt LCE (from 685kt in 2019), lifting Galan's total to 9.5Mt LCE. HMW is unchanged at 7.9Mt, which differs from the 8.6Mt total booked in March 2024. Galan says it ranks in the global top 10.
resource reserve update
- 28 Jan
Galan received the US$3M Chemphys placement money via affiliate Latam Resources, after shareholders approved it at the 15 November 2024 AGM. Funds go to Phase 1 work. The offtake prepayment facility is still unsigned, targeting close in Q1 2025.
capital raising announcement
- 6 Jan
Catamarca granted the full Phase 2 mining permit for up to 21,000tpa LCE at HMW, a permit Galan had been pursuing. Expansion still needs project finance and Phase 1 delivery. The company says Phase 2 would be cash flow positive at current prices.
regulatory community update
2024
- 16 Oct
The entitlement offer closed fully subscribed, raising A$13.3M at A$0.105. Eligible holders applied for 60.2M shares and the full 66.5M shortfall was taken up. This completes the A$25M raising begun in September; shares issue 17 October.
capital raising announcement
- 10 Sept
Galan raises about A$12M via a placement at A$0.105, plus a 1-for-4 entitlement offer for up to A$13.3M at the same price. Chemphys takes about A$4.5M, conditional on definitive agreements. Phase 1 is cut to an initial 4,000tpa LCE; first production stays H2 2025.
capital raising announcement
- 27 Aug
Non-binding MOU with Chengdu Chemphys: 23,000t LCE of lithium chloride over the first five years of HMW Phase 1, plus a US$40M offtake prepayment facility. It is subject to definitive agreements, approvals and due diligence. The company also says it could not proceed with the November 2023 offtake/financing option (Glencore term sheet, inferred).
material agreement
- 12 Aug
Galan will not proceed with the EnergyX proposal, ending that thread. It says financing partners are shortlisted, pond inventory is 3,200t LCE, new piping lifts pond flow by up to 50%, and Phase 2 permitting is advancing.
material agreement termination
- 6 Aug
Galan confirms it received an unsolicited, non-binding, conditional proposal from EnergyX for its Argentine assets: US$50M cash plus US$50M in unlisted EnergyX shares, US$50M for construction, and a 10% revenue royalty for 10 years. It is not a takeover bid and would need shareholder approval.
business combination
- 12 July
HMW Phase 1 is about 40% complete with over 2,800t LCE in ponds. Construction has been slowed to preserve cash, so first production moves from H1 2025 to H2 2025. Offtake partners are shortlisted, with a sales agreement and funding package still being sought.
production update
- 24 June
Ross Dinsdale, previously CFO of Mallee Resources, is appointed CFO from 10 July 2024. Galan says his financing background suits its ongoing offtake and funding negotiations. He follows Graeme Fox as CFO in the context.
director officer appointment
- 20 May
Galan has firm commitments for a A$14M placement at A$0.23 per share, a 20.7% discount to the A$0.29 close, with one option (A$0.35, two years) per two shares. Funds support HMW Phase 1 while debt and prepayment funding is negotiated. Directors take about A$1M in a second tranche.
capital raising announcement
- 14 May
Galan draws on the Acuity facility for the first time, raising A$2.25M by setting off 7.95M collateral shares at A$0.283, a 5.7% discount to the A$0.30 close. That is well below the A$0.46 placement price.
capital raising announcement
- 22 Apr
Catamarca's governor signed a commercial agreement supporting permits to sell lithium chloride concentrate locally or export it. It lifts the proposed royalty to 7% and commits Galan to downstream processing after 4 years. Galan says it is a prerequisite for Phase 2 permits; still to be legislated.
material agreement
- 17 Apr
Galan's shares are placed in voluntary suspension at the company's request, pending an announcement on government permitting. The request runs to 19 April or until the announcement is released.
other
- 12 Apr
Galan signs a A$15M standby equity facility with Acuity Capital, available until 31 January 2029, at Galan's discretion with no obligation to use it. It issued 15M collateral shares at nil cash as security. Issue price would be at up to a 10% discount to VWAP.
capital raising announcement
- 27 Mar
The Share Purchase Plan drew just over A$4M of applications against a A$1.5M target, and Galan lifted it to A$4.003M. It will issue 8,702,150 shares (2.2% of capital) at A$0.46, each with a free $0.65 option.
capital raising announcement
- 27 Mar
Total resource rises 18% to 8.6Mt LCE at 859mg/L Li (previously 7.3Mt), mainly from adding the Catalina tenure (~1.3Mt LCE). The HMW Measured category is 4.7Mt LCE at 866mg/L. This is Galan's fourth major upgrade since the March 2020 maiden resource.
resource reserve update
- 31 Jan
Galan raises A$18M from institutions at A$0.46, a 14.8% discount to the last close, with one free $0.65 five-year option per share. Directors take A$1.5M subject to approval, and a A$1.5M share plan is offered. Funds cover HMW Phase 1 while debt and prepayment talks continue.
capital raising announcement
- 23 Jan
Initial filling of Pond 1 has begun at HMW, with evaporation due to start in about two weeks after a quality test. This is the first step toward the H1 2025 production target. Liner installation is 40% done; a Glencore due diligence site visit is due this week.
production update
2023
- 29 Nov
Galan says it has had many approaches for Phase 2 offtake and funding, and is starting a formal offtake process led by the MD and director Daniel Jimenez. Phase 1 capex is now quoted at US$118.4m and Phase 2 at a further US$310.4m, up from the DFS figures of US$104m and US$278m.
material agreement
- 16 Nov
Galan signs a binding term sheet with Glencore to buy up to 100% of Phase 1 lithium chloride (about 5.4ktpa LCE) for five years from commercial production. Glencore also offers a US$70-100M prepayment facility, subject to conditions including due diligence at its absolute discretion.
material agreement
- 4 Oct
Galan signs a binding 50/50 JV with Redstone, which manages it, to acquire 100% of the Taiga, Camaro and Hellcat lithium projects (5,187 ha) in James Bay, Quebec, plus an option over the PAK projects (1,415 ha) in Ontario. Adds Canadian exploration alongside Argentina; terms not visible.
farm in farm out agreement
- 3 Oct
Phase 2 DFS for HMW: 21ktpa LCE from H2 2026, post-tax NPV8% US$2 billion, IRR 43%, incremental capex US$278m (total US$382m ex-contingency), opex US$3,510/t. Ore Reserve is 806kt LCE. Offtake/funding talks for Phase 1 are described as advanced.
resource reserve update
- 21 Sept
Greenbushes South maiden program finished at eight diamond holes for 3,885m, with final assays showing no significant lithium mineralisation. The company says the pegmatite exploration model is validated and further drilling is being planned closer to the Donnybrook-Bridgetown Shear Zone.
drilling result
- 21 Aug
Full Phase 1 pond construction has started at HMW, with the first earthmoving fleet on site. The first evaporation-ready pond is expected by Q1 2024, with production targeted for H1 2025 at 5.4ktpa LCE. Phase 2 DFS remains on track for September.
regulatory community update
- 8 Aug
Full Phase 1 construction permits granted for 5.4ktpa LCE at HMW, covering ponds, plant, laboratory, 200-man camp and power, plus six more production wells. Main contractor appointment is imminent and pond construction is due to start within two weeks. This resolves the permit thread.
regulatory community update
- 2 Aug
Galan sets an exploration target of 500kt to 1.5Mt LCE at 953-988 mg/L for the newly consolidated Catalina tenure, which overlaps 5,954 hectares of HMW tenements. About 1,000m of three-hole drilling is planned. This is conceptual, not a resource.
drilling scheduled
- 28 July
Galan secured 100% of the Catalina tenure straddling Catamarca and Salta, by issuing 9,756,098 shares to the Salta private owner. This resolves the Catalina border overlap thread in Galan's favour, though the provincial border dispute itself remains unresolved. Dilutive.
asset acquisition disposition
- 24 July
HMW pilot plant produced 350 litres of 6% lithium chloride concentrate on 16 July 2023, low in impurities; samples are ready for potential buyers. This delivers on the earlier pilot concentrate target. Phase 1 full permit and Phase 2 DFS expected Q3 2023.
production update
- 3 July
Phase 1 DFS for HMW: 5.37ktpa LCE as 6% lithium chloride from H1 2025, post-tax NPV8% US$460m, IRR 36%, capex US$104m before contingency, opex US$3,963/t. Funding will likely be required, possibly dilutive. Phase 2 (20ktpa) DFS now due September 2023.
resource reserve update
- 26 June
Catamarca's Mines Minister granted initial Phase 1 permits for Hombre Muerto West on 23 June 2023, covering pre-construction works: camp, top-soil removal and ground testing. Top-soil removal has started; full construction permits are expected in Q3 CY2023. This resolves part of the permit thread.
regulatory community update
- 1 June
Strategy update: initial DFS covers only phase 1, 4ktpa LCE as 6% lithium chloride concentrate (first product H1 2025), with permits due June. Phase 2 DFS for 20ktpa due August 2023. Company says capex ~40% below carbonate.
investor presentation
- 22 May
Galan raised A$31.5M through a placement of 30M shares at A$1.05, a 12.5% discount to the last close. A share purchase plan of about A$5M at the same price follows. Pro-forma cash about A$50M, funding long-lead pilot plant items and Stage 2 DFS. Dilutive.
capital raising announcement
- 1 May
HMW resource rises about 14% to 6.6Mt LCE at 880 mg/l, with 4.7Mt (72%) Measured, up from 5.8Mt in October 2022. Including Candelas, total is 7.3Mt at 852 mg/l. Third upgrade since March 2020's 1.08Mt.
resource reserve update
- 6 Mar
Maiden 2,500m drilling has started at Greenbushes South, about 3km from the Greenbushes mine. The site team notes minerals associated with lithium pegmatites near surface. No assay results yet.
drilling spud
- 1 Mar
Santa Barbara exploration well SB-01-23 reached 455m, and airlift testing averaged 829 mg/L lithium, extending the HMW resource area to a new tenement. Drilling of three new production wells has started, the first at Rana de Sal I.
drilling result
- 8 Feb
Galan says it has moved to 100% title of the Candelas project, with no third-party royalties. It repeats the 2021 PEA (14ktpa, US$1,225m pre-tax NPV) and 685kt LCE resource. Candelas studies will be revisited only after the HMW DFS is complete.
asset acquisition disposition
2022
- 20 Dec
Galan identified three maiden drill targets at Fry's Block in Greenbushes South, now 100% owned after the Lithium Australia buyout. A five-hole diamond program is planned from late January 2023, pending program of works approval. No drilling results yet.
drilling scheduled
- 13 Dec
Galan signed a binding term sheet to buy Lithium Australia's remaining 20% of Greenbushes South for A$2M cash plus A$1M of Galan shares, taking it to 100%. The joint venture ends on completion. LIT gets a first right to negotiate offtake of 20% of Galan's share.
asset acquisition disposition
- 24 Oct
HMW resource rises 2.5x (about 158%) to 5.8Mt LCE at 866 mg/l Li, including a first Measured resource of 4.4Mt (76%). Replaces the earlier ~2.3Mt; total with Candelas is 6.5Mt. DFS now guided to Q1 2023, a shift from end-CY2022.
resource reserve update
- 1 Aug
Greenbushes South: a second, larger outcropping pegmatite found, three outcrops across about 500m x 400m and possibly continuing along strike. First soil assays show lithium up to 215 ppm. Extends the June GS11 find; ground geophysics under way, no drilling yet.
drilling result
- 15 June
Greenbushes South: airborne data identified 18 lithium pegmatite targets, and mapping of the first, GS11, found an outcropping pegmatite lens about 200m x 40m. Assays are pending and further fieldwork is due from July. No drilling yet; follows the March soil results.
drilling result
- 7 Apr
Diamond hole PP-02-22 at Pata Pila reached 450m, showing sand-dominated, brine-bearing layers with high porosity about 800m east of the earlier hole. It supports resource upside and feeds the Q3 2022 resource update. Brine filling of pilot pond S1 has begun.
drilling result
2021
- 14 Dec
Galan awarded the HMW feasibility study to engineering firm Hatch, resolving the open engineering contract thread. Delivery is expected late Q4 2022. This is the key step toward a feasibility study and eventual development decision.
contract award
- 9 Dec
Updated HMW economic study lifts pre-tax NPV to US$2,193m from US$1,011m (IRR 37.5%) purely by raising the lithium price assumption to US$18,594/t; capex US$439M and 20,000tpa unchanged. Combined with Candelas, NPV is US$3.4b. Still a preliminary study.
resource reserve update
- 30 Nov
Candelas scoping study (PEA) shows pre-tax NPV of US$1,225m, IRR 27.9%, capex US$408M for 14,000tpa lithium carbonate over 25 years, using a US$18,594/t long-term price. Delivers the scoping study due Q4 2021; preliminary only, not a reserve.
resource reserve update
- 1 Nov
Catamarca's mining minister granted permits to build the Stage 1 pilot plant and new camp at HMW, which the MD called critical path items. The first small evaporation pond is finished. This resolves the pilot plant permit thread.
regulatory community update
- 29 Sept
First hole of the new HMW campaign, PB-01-21 at Pata Pila, reached 220m. Good cuttings recovery shows at least 40m previously modelled as halite is actually brine-bearing conglomerate, sand and silt, expected to lift future resource estimates. No assays or flow rates yet.
drilling result
- 19 Aug
Galan received the next round of drilling permits for HMW, and earthworks have started at Pata Pila and Rana de Sal with drilling equipment on site. The campaign targets resource expansion, maiden reserves and production well flow tests, funded by the new raise.
drilling scheduled
- 13 Aug
Galan raised A$50M at A$1.15 per share in a two-tranche placement led by Canaccord. Tranche One is A$29.8M (about 25.9M shares); Tranche Two is A$20.2M, subject to shareholder approval. Pro forma cash is about A$65.1M, to fund drilling and feasibility studies. Dilutive but funds development.
capital raising announcement
- 20 July
Galan will start a scoping study on Candelas, its second Hombre Muerto West-area project (685kt LCE resource), after modelling showed brine concentrate up to 6% Li with low impurities, similar to HMW. Results are expected in Q4 2021; HMW feasibility work continues.
other
- 15 July
Galan signed a binding option with a private Argentinian individual to earn 100% of the Casa del Inca III tenement next to Pata Pila at HMW. It will initially acquire 300ha for US$150,000, with US$80,000 deposit paid. Up to 900ha possible.
asset acquisition disposition
- 12 July
First lab proof-of-concept test made lithium carbonate of 99.88% purity from HMW concentrate, above the 99.5% battery-grade minimum. Resolves the pending carbonate conversion testing from earlier updates. It is an early lab result; pilot-scale work is still to come.
flow test result
- 22 Mar
Lab tests lifted HMW lithium chloride concentrate to 6% Li, up 25% from the 4.8% assumed in the December 2020 PEA, with low contaminants. Galan expects to start evaporation pilot work on site in Q2 2021. This resolves the pending lab results and likely explains the 18 March pause (inference).
well test result
- 27 Jan
Galan raised $10M through a placement of 20M shares at $0.50, a 3% discount to the last close, with Thematica taking $4M. Funds go to HMW studies, drilling and piloting, Greenbushes South exploration and working capital. Barclay Wells was lead manager, paid a 6% fee. Existing cash was $4.6M.
capital raising announcement
- 14 Jan
Galan agreed to buy 80% of Lithium Australia's 353 km2 Greenbushes South project in WA for 1,221,000 shares, forming a joint venture. Galan will fund expenditure until a pre-feasibility study. With its own 43 km2 application, ground totals 396 km2. Transfers need regulatory approval.
asset acquisition disposition
2020
- 21 Dec
The HMW PEA shows 20,000tpa of lithium carbonate over 40 years, pre-tax NPV US$1,011m (8%), IRR 22.8% and capex US$439m. Cash cost is US$3,518/t, based on a US$11,687/t price assumption. It is preliminary and does not support reserves. This delivers the Q4 PEA.
resource reserve update
- 17 Nov
HMW Indicated resource rises 65% (895kt) to 2.27Mt LCE at 946mg/l Li after adding Del Condor and an SRK review of porosity data. Combined with Candelas, total inventory is about 2.95Mt LCE. This builds on the June 2020 1.37Mt estimate; PEA is still due.
resource reserve update
- 4 Nov
Galan completed the purchase of 100% of the Del Condor and Pucara projects (1,804 ha) next to HMW, paying CDN$100,000 cash plus 650,000 shares. This closes the open Portofino thread. SRK will update the HMW resource; a geophysics survey is planned for Q1 2021.
asset acquisition disposition
- 12 Oct
Galan raised $3M through a placement of 23,076,924 shares at 13c, a 13.3% discount to the last close of 15c, with bids 50% above target. Thematica Future Mobility took part again. Funds go to HMW scoping and pre-feasibility studies, lab testing and working capital.
capital raising announcement
- 24 Aug
Preliminary pond modelling for HMW shows brine could be concentrated to up to 4.8% Li, versus 3.1% for Candelas. The board now prioritises HMW as the main development project. PEA/scoping results are expected in Q4 2020; lab confirmation is pending.
other
- 24 July
Galan has started a Preliminary Economic Assessment of the HMW project, to be done by Worley Chile to NI 43-101 standard, covering engineering, operating and capital cost estimates for lithium carbonate. It moves the project from resource work toward economics; no results or cost given.
contract award
- 23 June
Galan raised $1.6M in total: a $1.25M placement of 8,928,572 shares at 14c with free $0.25 options expiring 31 Mar 2022, including Thematica Future Mobility, plus $350,000 from Acuity via 2.5M shares at 14c. Funds go to studies, Del Condor/Pucara completion and working capital.
capital raising announcement
- 22 June
HMW resource rises 27% to 1.37Mt LCE at 946mg/l Li after adding Deceo III, and is upgraded from Inferred to 100% Indicated. Combined with Candelas, total inventory is 2.06Mt LCE. This builds on the March maiden resource.
resource reserve update
- 28 Apr
Galan completed purchase of 100% of the 163.5ha Deceo III tenement for US$30,000 under a renegotiated agreement. It sits next to Pata Pila, 100m from hole PP-01-19, and the company says it could extend the resource beyond 1.77Mt LCE.
asset acquisition disposition
- 3 Apr
Galan raised $550,000 through a placement of 3,928,572 shares at 14c, a 3.6% discount, with a free $0.25 option expiring 31 Mar 2022 per share. The whole board and staff participated. Funds go to scoping/PFS studies and working capital; burn rates reduced since January.
capital raising announcement
- 12 Mar
Maiden Inferred resource for Pata Pila and Rana de Sal of 1.08Mt LCE at 946mg/l Li, which the company says exceeds its expectations. Combined with Candelas, total resource rises 158% from 685kt to 1.77Mt LCE at 837mg/l Li. This resolves the pending Western Basin estimate.
resource reserve update
- 26 Feb
Galan signed a binding agreement with Portofino Resources for the right to earn 100% of the Del Condor and Pucara lithium brine projects (1,804 ha) next to its Hombre Muerto West ground. It will pay CDN$100,000 cash and issue 650,000 shares, subject to due diligence.
farm in farm out agreement
- 5 Feb
Nathan McMahon, chairman and a major shareholder since the IPO, retired. Richard Homsany, a corporate lawyer and Toro Energy chair, becomes interim non-executive chairman. The MD says the company is shifting focus from exploration to project development.
director officer appointment
2019
- 9 Oct
Full lab assays for Pata Pila hole 1 all exceed 900mg/l Li. Second hole at Rana de Sal returned 39m at 1,043mg/l Li from 83m, Galan's highest grade so far. Galan says it will accelerate resource estimation for both Western tenements.
drilling result
- 1 Oct
Galan books its maiden JORC resource at Candelas: Indicated 684,850t lithium carbonate equivalent at 672mg/l Li (500mg/l cut-off) in the North Zone, plus an Inferred Central Zone. This far exceeds the 80kt vendor-share trigger and is the basis for the PFS.
resource reserve update
- 11 Sept
Preliminary assays from the first Pata Pila hole, PP-19-01, show lithium above 900mg/l with Mg/Li under 2, from a hole completed at 718m. This confirms the brine zones reported on 6 Sept; management says it could add resources beyond Candelas.
drilling result
- 6 Sept
The first Western Basin hole at Pata Pila, PP-19-01, is at 647m and found three heavy brine zones in field tests (SG above 1.20), including the extension of Livent's production aquifer and two new deeper aquifers. Lab assays are pending; Candelas resource is due this month.
drilling result
- 5 Aug
Galan is raising up to $2M: a $1M placement at 18c (5,555,555 shares) plus a share purchase plan for up to $1M at the same price, each with a free option per two shares ($0.25, expiring 31 Aug 2020). Funds go to resource, PFS and Western drilling. Price is below April's 27.5c placement.
capital raising announcement
- 24 July
Galan received permits to drill 14 holes plus 5 water bores over 18 months in the Western Basin, the permits awaited since drilling paused. First targets are Pata Pila and Rana del Sal, chosen from geophysical anomalies. Access work has started.
regulatory community update
- 22 July
Hole 8 assayed 70.4m at 744 mg/l lithium, with low impurities (Mg:Li 2.65). All five northern Candelas holes now exceed 500 mg/l, confirming at least 3.5km by 2.5km of brine. SRK begins resource work; maiden resource still on track for Q3 2019.
drilling result
- 2 July
Stage 2 drilling is complete. Hole 5 returned 137m at 680 mg/l and hole 6 54m at 510 mg/l lithium, confirming heavy brine over at least 3.5km. Hole 7 hit shallow basement at 248m. The maiden resource for northern Candelas remains on track for Q3 2019.
drilling result
- 16 May
Galan received permits for six more Candelas drillholes (stage 2), aiming for a maiden resource in Q3 2019. Hole 5 finished at 380m in brine over 140m. Hole 4 assayed only 117m at 141 mg/l lithium, a low grade.
regulatory community update
- 30 Apr
Hole 3 assays returned 143m at 784 mg/l lithium from 311m to 454m, with low impurities (Mg:Li about 2.7), close to hole 1's 802 mg/l. Hole 4 reached 488m with only moderately conductive brine. Company says it remains on target for a resource in Q3.
drilling result
- 9 Apr
Galan raised $4.0M through a placement of 14,545,455 shares at $0.275 each to Australian and North American investors. Funds will expand the Candelas drilling, start initial resource work and add working capital. Barclay Wells led the placement.
capital raising announcement
- 4 Apr
Third hole C-03-19, about 2.5 km southeast of hole 1, hit highly conductive brine from about 280 m and was still in brine at 309 m. Hole 2 assays confirmed lower grades of about 93-124 mg/l lithium, which the company attributes to dilution.
drilling result
- 20 Mar
Second hole C-02-19 ended at 662 m, with basement at 632 m. Field tests show weaker brine than hole 1 (specific gravity about 1.045), which the company attributes to possible hot-water dilution. A third hole is planned between the first two.
drilling result
- 11 Mar
Hole 1 brine section extended to 192 m averaging 802 mg/l lithium, with low impurities and check assays from a second lab in line. The second hole is under way at 465 m, about 9.5 km south, with its brine target not yet reached.
drilling result
- 20 Feb
Maiden hole C-01-19 finished at 401 m with brine for 166 m from about 235 m. Extra assays gave 771 and 806 mg/l lithium, with low impurities. The rig moves to a second site about 9.5 km south.
drilling result
- 13 Feb
First assays from Candelas hole 1: 65 m averaging 862 mg/l lithium (235-300 m), with brine to 354 m and low magnesium-to-lithium ratio under 3. This confirms the earlier brine find as lithium-bearing; samples may be diluted by drilling fluid.
drilling result
- 6 Feb
The first Candelas hole (C-01-19) hit highly conductive brine from about 235 m to 300 m, still in brine. Lithium content is unconfirmed until lab results arrive. This is the first drilling evidence for the brine channel after the earlier geophysics.
drilling result
- 22 Jan
Maiden Candelas drilling starts this week after a slight delay while locals were trained. Major Drilling is the contractor and SRK Australia will oversee resource definition and QA/QC, potentially toward a JORC resource. Five holes are planned.
drilling spud
- 2 Jan
Listed $0.14 options expired 31 December 2018: 16,269,109 of 16,450,000 were exercised. The remaining 180,891 shortfall options go to the Barclay Wells underwriter. Funds will go to the maiden drilling campaign; this resolves the option-funding thread.
capital raising announcement
2018
- 13 Dec
Catamarca granted permits for the maiden Candelas drilling, resolving the long-awaited permitting thread. A five-hole programme over ~12-15 km is planned, with the first hole testing the geophysical model to over 400 m; drilling is due early January 2019.
regulatory community update
- 19 Nov
Barclay Wells will underwrite exercise of 11.39M quoted $0.14 options, guaranteeing $1,594,811 before costs (4% fee), to fund Candelas exploration. Drilling permits are in their final stage, with community meetings due within a fortnight; this addresses the earlier funding-of-drilling thread.
capital raising announcement
- 18 Oct
CSAMT over four Western Basin targets, including Catalina and Rana de Sal, shows conductive units consistent with brine, lifting total potential brine area ~24% to ~7,800 ha. Still indirect geophysics. Drilling permits are awaited, hoped for this quarter.
drilling result
- 4 Oct
A second CSAMT survey (25.6 line km, 6 lines) extends the Candelas brine-prospective strike from ~10km to ~15km and the potential brine area to ~6,000 Ha, with layers ~150-400m+ thick. It is indirect geophysics, not drilling, so no brine is confirmed.
drilling result
- 23 July
Dempsey bought the Rana de Sal licence for US$25,000 and optioned the Santa Barbara licences (US$300,000 within three years), and applied for Pata Pila. Pending approvals, brine-prospective area rises ~35% to ~6,900 Ha. Surface samples exceeded 1,000 mg/l Li; more geophysics from August, drilling targeted Q4.
asset acquisition disposition
- 25 June
Dempsey completed the 100% acquisition of Blue Sky Lithium, owner of the Hombre Muerto project. JP Vargas de la Vega becomes Managing Director and Raymond Liu joins the board; Patrick Corr resigned. A court action over the El Deceo tenements is disclosed, which the company disputes and says does not affect Candelas.
asset acquisition disposition
- 6 June
CSAMT survey over about 10 km of the Los Patos delta found very conductive shallow units consistent with brine-saturated rock, interpreted at about 150-400m+ thick. This is indirect geophysics, not drilling or brine samples. A new Candelas X licence application was also added.
drilling result
- 14 Feb
Dempsey issued 7.7M shares in a first placement, a financing condition of the Blue Sky option, diluting holders by 17.1% to 52.79M shares. Proceeds cover due diligence, adviser fees and working capital; a 6% raising fee applied. Issue price is not stated here.
capital raising announcement
- 6 Feb
Dempsey signed an exclusive option to buy 100% of Blue Sky Lithium's Hombre Muerto tenements in Argentina, or the company holding them. It is the first battery-metals project after the earlier search; the chairman calls it a 'potential game changer'. Completion needs further steps.
material agreement
2017
- 6 Sept
Dempsey raised $100,000 via a placement at $0.05 per share with a free listed option for every two shares ($0.14, expiring 31 December 2018). Directors contributed $20,000, subject to shareholder approval. Funds go to working capital and due diligence.
capital raising announcement
2016
- 28 July
Dempsey details its Greenbushes South (Smithfield) lithium project, a 43 km2 licence application about 15 km south of the Greenbushes mine. Exploration will start once the licence is granted. Its first lithium-focused project, alongside the Turkish oil option.
asset acquisition disposition
- 6 June
The shortfall from the entitlement offer was fully placed, adding $265,342 gross (3.4M shares with free options, plus 2.7M options). With the $222,258 taken up earlier, the offer raised about $487,600, its full target.
capital raising announcement
- 8 Mar
Entitlement offer closed having raised $222,258 from eligible shareholders against up to $487,600 sought. Take-up was 2.69M of 6.095M shares. The unsubscribed 3.4M shares and 2.7M options go to a shortfall offer under the prospectus. A fraction of the original target.
capital raising announcement
- 3 Feb
Prospectus for a non-renounceable entitlement offer: one new share per five held at $0.07, with a free $0.14 option expiring 31 December 2018, plus separate options at $0.01. Raises up to about $487,600, closing 26 February 2016. Funds the Petroz acquisition process.
capital raising announcement
- 29 Jan
December 2015 quarter: the $700,000 Petroz loan is paid and Turkish bonds registered. An independent report (RISC) estimates 6.8 MMstb net 2C contingent resources and 6.7 MMstb net prospective resources for Petroz's 75% of the Alasehir licence. Well design under way.
resource reserve update
2015
- 4 Sept
Dempsey signs an option to buy 100% of unlisted Petroz, which holds 75% of the Alasehir oil licence in Western Turkey, for 4M shares plus 16M milestone-based performance shares. It will lend Petroz $700,000 and seeks $590,000 via an entitlement offer. Cash is $875,000. A move from minerals into oil.
asset acquisition disposition
2014
- 30 July
June 2014 quarter: cash $1.24M. Dandaragan tenement surrendered and its data sold to Potash West for 200,000 shares and a 0.4% royalty, ending the earlier farm-in thread. Fraser Range has drawn several joint venture expressions of interest. Company also reviewing opportunities in other sectors.
quarterly activities report
2013
- 19 Nov
Dempsey is priority applicant for Fraser Range tenement E28/2369, about 200 km2 and roughly 40 km north of Sirius Resources' Nova and Bollinger discoveries. A new nickel-copper exploration thread; it is only an application, with approvals and permitting pending.
regulatory community update
- 31 July
June 2013 quarter: Cooljarloo sold to Tronox and Yalgoo Minerals for $93,750 plus a retained royalty of about $3.77 per tonne of valuable heavy minerals, ending the farm-in thread. Applications lodged for Zelika gold/nickel and Ravensthorpe lithium licences.
asset acquisition disposition
- 31 Jan
Dandaragan exploration target set at 2.1 to 3.0 billion tonnes grading 2.5% to 5.0% K2O. This is conceptual, not a resource. Initial Cooljarloo access agreements signed; a Ravensthorpe lithium licence was applied for, a first lithium step.
resource reserve update
2012
- 31 Jan
Maiden Dandaragan aircore drilling (10 holes, 758m) returned potassium up to 52m at 3.61% K2O and phosphorus 2m at 3.17% P; best potassium 6.76% K2O. Cooljarloo desktop studies started. Resolves the planned drilling thread (10 holes rather than 12 planned).
drilling result
2011
- 28 Dec
Dempsey withdrew its planned Winmar takeover bid. Winmar agreed on 29 Nov to issue shares to PXSteel, which Dempsey says breached a key bid condition. This ends the 23 November bid proposal.
business combination
- 23 Nov
Dempsey said it intends to bid for Winmar Resources (iron ore explorer) at 4 Dempsey shares per 7 Winmar shares, with a 50.1% minimum acceptance. Winmar holders would own about 57.5% of the enlarged company if 100% accepted. A new growth-strategy step.
business combination
- 3 Oct
Dempsey will not exercise the Brazilian Cacule manganese option after a small drilling program gave sub-economic results, having spent about A$150,000 on due diligence. This ends the thread that held its shares suspended; a 12-hole Dandaragan drill program is planned for November.
asset acquisition disposition
- 28 June
Dempsey took an option to buy 100% of a Brazilian manganese project for about A$1.56M, after paying a A$118,000 option fee. Its shares were suspended on 21 June and stay suspended until shareholders vote on the option.
asset acquisition disposition
- 6 June
Conditions were satisfied so Dempsey can begin farming in to the Cooljarloo and Dandaragan projects. The Kimba payment for Dandaragan was cut from $25,000 to $8,175.
farm in farm out completion
- 6 June
Dempsey Minerals was admitted to the ASX Official List on 6 June 2011, with quotation of 14,000,001 shares starting 8 June under code DMI.
other
- 29 Apr
Dempsey Minerals issued a prospectus to raise up to $2.5M by issuing up to 12.5M shares at 20 cents each. Funds would explore WA phosphate and mineral sands projects, where it holds farm-in options for up to 75% interests.
capital raising announcement