Each one in plain English, with the numbers worked through for a shareholder.
29 Sept 2021drilling result▲ GoodMajor
First hole of the new HMW campaign, PB-01-21 at Pata Pila, reached 220m. Good cuttings recovery shows at least 40m previously modelled as halite is actually brine-bearing conglomerate, sand and silt, expected to lift future resource estimates. No assays or flow rates yet.
Galan received the next round of drilling permits for HMW, and earthworks have started at Pata Pila and Rana de Sal with drilling equipment on site. The campaign targets resource expansion, maiden reserves and production well flow tests, funded by the new raise.
HMW pond redesign supports up to 25,000 tpa LCE over about 7 million m2 (up from 5.5M), built in two stages to lower initial capex. Two new evaporation tests again gave 6%+ Li. Battery-grade test work delayed by COVID, now due early Q3 2021.
First Greenbushes South field work finds the shear zone hosting the Greenbushes deposit crosses the project. 25 soil and 15 rock chip samples show pathfinder anomalies, arsenic up to 574 ppm and tin up to 27 ppm. Early-stage only, no drilling; more sampling planned.
HMW brine concentration lab testing is 85% complete, with early results matching the evaporation model. COVID-related lab closures caused delays. Final results are expected by end of March. No final result yet.
The HMW PEA shows 20,000tpa of lithium carbonate over 40 years, pre-tax NPV US$1,011m (8%), IRR 22.8% and capex US$439m. Cash cost is US$3,518/t, based on a US$11,687/t price assumption. It is preliminary and does not support reserves. This delivers the Q4 PEA.
HMW Indicated resource rises 65% (895kt) to 2.27Mt LCE at 946mg/l Li after adding Del Condor and an SRK review of porosity data. Combined with Candelas, total inventory is about 2.95Mt LCE. This builds on the June 2020 1.37Mt estimate; PEA is still due.
HMW resource rises 27% to 1.37Mt LCE at 946mg/l Li after adding Deceo III, and is upgraded from Inferred to 100% Indicated. Combined with Candelas, total inventory is 2.06Mt LCE. This builds on the March maiden resource.
Maiden Inferred resource for Pata Pila and Rana de Sal of 1.08Mt LCE at 946mg/l Li, which the company says exceeds its expectations. Combined with Candelas, total resource rises 158% from 685kt to 1.77Mt LCE at 837mg/l Li. This resolves the pending Western Basin estimate.
Galan signed a binding agreement with Portofino Resources for the right to earn 100% of the Del Condor and Pucara lithium brine projects (1,804 ha) next to its Hombre Muerto West ground. It will pay CDN$100,000 cash and issue 650,000 shares, subject to due diligence.
Geophysical surveys at Pata Pila and Rana del Sal are complete, showing highly conductive zones consistent with brine-saturated units that coincide with the high-grade drill intercepts. Results will feed SRK's maiden resource estimates for the Western Basin.
Galan will start CSAMT geophysical surveys over Pata Pila and Rana del Sal to help SRK estimate maiden resources for the Western Basin. It is a preparatory step following the high-grade drilling results.
Full lab assays for Pata Pila hole 1 all exceed 900mg/l Li. Second hole at Rana de Sal returned 39m at 1,043mg/l Li from 83m, Galan's highest grade so far. Galan says it will accelerate resource estimation for both Western tenements.
Galan books its maiden JORC resource at Candelas: Indicated 684,850t lithium carbonate equivalent at 672mg/l Li (500mg/l cut-off) in the North Zone, plus an Inferred Central Zone. This far exceeds the 80kt vendor-share trigger and is the basis for the PFS.
Preliminary assays from the first Pata Pila hole, PP-19-01, show lithium above 900mg/l with Mg/Li under 2, from a hole completed at 718m. This confirms the brine zones reported on 6 Sept; management says it could add resources beyond Candelas.
The first Western Basin hole at Pata Pila, PP-19-01, is at 647m and found three heavy brine zones in field tests (SG above 1.20), including the extension of Livent's production aquifer and two new deeper aquifers. Lab assays are pending; Candelas resource is due this month.
Access preparation is finished and Galan will start its first Western Basin drilling at Pata Pila and Rana del Sal later this week, under permits for 14 holes plus 5 water bores. The Candelas maiden resource is still expected this quarter.
Hole 8 assayed 70.4m at 744 mg/l lithium, with low impurities (Mg:Li 2.65). All five northern Candelas holes now exceed 500 mg/l, confirming at least 3.5km by 2.5km of brine. SRK begins resource work; maiden resource still on track for Q3 2019.
Stage 2 drilling is complete. Hole 5 returned 137m at 680 mg/l and hole 6 54m at 510 mg/l lithium, confirming heavy brine over at least 3.5km. Hole 7 hit shallow basement at 248m. The maiden resource for northern Candelas remains on track for Q3 2019.
Hole 5 interim assays gave 491 to 856 mg/l lithium over 160m from 220m, with low impurities. Hole 6 finished at 422m with brine in field tests, extending brine to at least 3.5km. Winter weather has delayed sampling.
Fifth hole C-05-19 hit highly conductive, dense brine from about 280m and was still in brine at 330m. It lies about 2.4km from hole 1. Field readings only; lab assays are awaited.
Hole 3 assays returned 143m at 784 mg/l lithium from 311m to 454m, with low impurities (Mg:Li about 2.7), close to hole 1's 802 mg/l. Hole 4 reached 488m with only moderately conductive brine. Company says it remains on target for a resource in Q3.
Hole C-03-19 was deepened to 454m after brine continued to the bottom, and brines are now confirmed over about 2.5km of strike. Final samples are due in about a fortnight. The fourth hole has started, about 5.3km south of hole 1.
Third hole C-03-19 finished at 430m, with brine of very high conductivity over about 154m from 276m, per field tests. Lab assays are due next week; the fourth hole is to start shortly, and permits for more holes beyond the approved five are awaited.
Third hole C-03-19, about 2.5 km southeast of hole 1, hit highly conductive brine from about 280 m and was still in brine at 309 m. Hole 2 assays confirmed lower grades of about 93-124 mg/l lithium, which the company attributes to dilution.
Second hole C-02-19 ended at 662 m, with basement at 632 m. Field tests show weaker brine than hole 1 (specific gravity about 1.045), which the company attributes to possible hot-water dilution. A third hole is planned between the first two.
Hole 1 brine section extended to 192 m averaging 802 mg/l lithium, with low impurities and check assays from a second lab in line. The second hole is under way at 465 m, about 9.5 km south, with its brine target not yet reached.
Maiden hole C-01-19 finished at 401 m with brine for 166 m from about 235 m. Extra assays gave 771 and 806 mg/l lithium, with low impurities. The rig moves to a second site about 9.5 km south.
First assays from Candelas hole 1: 65 m averaging 862 mg/l lithium (235-300 m), with brine to 354 m and low magnesium-to-lithium ratio under 3. This confirms the earlier brine find as lithium-bearing; samples may be diluted by drilling fluid.
The first Candelas hole (C-01-19) hit highly conductive brine from about 235 m to 300 m, still in brine. Lithium content is unconfirmed until lab results arrive. This is the first drilling evidence for the brine channel after the earlier geophysics.