27 Oct 2022other● Neutral

Notice that 13,122 shares leave voluntary escrow on 8 November 2022. Administrative; also restates the reporting calendar after the year-end change, with the AGM on 29 November 2022.

Discuss in chat

27 Oct 2022quarterly activities report● Neutral

September 2022 quarterly report: Sorption Demo Plant works started, Insheim 3D seismic began, and the Ried licence was granted. DFS is said to be on track for Q1 2023. Long-lead items were secured for the first drilling project.

Discuss in chat

27 Oct 2022quarterly activities report● Neutral

September 2022 quarter cash flow: cash fell to €158.2m from €175.4m, with operating outflow €5.1m and investing outflow €12.5m. No debt; company reports about 15 quarters of funding at current outgoings.

Discuss in chat

24 Oct 2022well test result▲ GoodMajor

Pilot plant produced lithium hydroxide grading 57.1% LiOH, above the 56.5% battery-grade spec required by offtake customers, with low impurities. Pilot data is now sufficient to complete the Phase 1 DFS, still scheduled Q1 2023; first commercial production now targeted 2025.

Discuss in chat

5 Oct 2022admin correction● Neutral

Vulcan is changing its year end from 30 June to 31 December from 1 July 2022, to align with Germany, giving a six-month transitional year to December 2022. AGM set for 29 November 2022; director nominations close 18 October.

Discuss in chat

28 Sept 2022annual report● Neutral

FY22 Corporate Governance Statement and Appendix 4G. It notes A$276 million raised in FY22, inclusion in the S&P/ASX 300 and the change of reporting currency. Governance disclosure with no new project results.

Discuss in chat

28 Sept 2022annual report● Neutral

FY22 annual report, covering the year to 30 June 2022. Visible text is the chair's message and contents only; chair says A$276 million was raised in FY22 and priorities include delivering the DFS. No new project results are readable.

Discuss in chat

28 Sept 2022annual report● Neutral

Vulcan's first standalone FY22 Sustainability Report, covering ESG strategy, targets and TCFD disclosures. Visible text contains no new project or financial results.

Discuss in chat

28 Sept 2022investor presentation● Neutral

September-October 2022 corporate presentation. Visible text is only disclaimers and risk warnings; no new results are readable.

Discuss in chat

28 Sept 2022annual report● Neutral

Cover release for the FY22 Group Management Report required for the Frankfurt listing. Visible text is administrative with no financial or project results.

Discuss in chat

26 Sept 2022director officer appointment▲ GoodMajor

Cris Moreno will join as Deputy CEO from 1 November 2022, based in Europe. He has over 20 years in major projects, including LNG roles at Santos, Woodside and Shell, and recent lithium work at Northvolt and Aurora Lithium.

Discuss in chat

21 Sept 2022remuneration report● Neutral

Vulcan finished an executive pay review and issued 154,000 performance rights to executives under new short- and long-term incentive plans, including ESG measures. The Managing Director's rights need shareholder approval at the late November AGM.

Discuss in chat

13 Sept 2022regulatory community update▼ BadMajor

Onsite construction began on the Landau Sorption Demo Plant, and 3D seismic crews mobilised at Insheim. A second Taro preliminary environmental approval was granted. DFS completion is now likely Q1 2023, slipping from the H2 2022 target; rigs likely early Q2 2023.

Discuss in chat

16 Aug 2022other● Neutral

Vulcan lodged a notice that it ceased to be a substantial holder on 15 August 2022, as 24,057,288 shares were released from voluntary escrow for nil consideration. Administrative filing tied to the escrow release; no project impact.

Discuss in chat

8 Aug 2022other● Neutral

Notice that 24,056,588 shares will leave voluntary escrow on 15 August 2022. These lock-ups date from the Frankfurt listing and were about 18.46% of shares earlier, so this is the main release of that group, not a new event.

Discuss in chat

28 July 2022quarterly activities report▲ Good

June 2022 quarterly: cash of €175.3m at 30 June (up from €141m in March), after the A$76M Stellantis investment. Licences reached 1,440km2, MVV heat deal signed, pilot plant running 15 months. DFS still reported as progressing; electric rigs ready early 2023.

Discuss in chat

26 July 2022regulatory community update▲ Good

Eight local councils approved Vulcan's 3D seismic survey in Rhineland-Palatinate, planned to start September 2022 to guide Phase 1 drilling. Vulcan also won the Ried licence, lifting its licence area by 277km2 to 1,440km2.

Discuss in chat

12 July 2022investor presentation● Neutral

July 2022 corporate presentation. Visible text is only disclaimers and risk warnings; no new results are readable.

Discuss in chat

11 July 2022other● Neutral

Director interest notices for Annie Liu and Heidi Grön (and a third director) show 4,299 shares each issued on 7 July 2022 from conversion of performance rights, for nil consideration. Routine, not market purchases.

Discuss in chat

8 July 2022farm in farm out agreement▲ GoodMajor

Vulcan signed a binding collaboration with Enel Green Power to scope the Cesano lithium licence in Italy, which will become co-owned 50:50. Separately, the Sorption (DLE) Demo Plant commissioning slipped to late Q4 due to supply chain issues; Taro wells need no full environmental assessment.

Discuss in chat

24 June 2022capital raising announcement▲ GoodMajor

Stellantis agreed a A$76M (€50M) equity investment at A$6.622 per share (about 11.45m shares), becoming the second largest shareholder at 8%. Funds go to production expansion drilling, and its lithium hydroxide offtake was extended five years to 2035.

Discuss in chat

17 June 2022regulatory community update▲ Good

Landau City Council voted to support geothermal production and take a positive stance on lithium extraction from brine, near the Insheim core of Phase 1. Vulcan also gained the Flaggenturm and Fuchsmantel licences, lifting its licence area by 141km2 to 1,163km2.

Discuss in chat

9 June 2022other● Neutral

Vulcan launched its sustainability and ESG framework, noting about 120 staff (up from 70 in 2021), Australian carbon neutral certification and UN Global Compact membership. It sets targets but contains no new project or financial results.

Discuss in chat

18 May 2022investor presentation● Neutral

May 2022 corporate presentation for the Canaccord and Bank of America conferences. Visible text is only disclaimers and risk warnings; no new results are readable.

Discuss in chat

6 May 2022other● Neutral

Notice that 9,675 shares will leave voluntary escrow on 19 May 2022. A trivial release, about 0.007% of the 131.6m shares on issue, with no bearing on the project.

Discuss in chat

28 Apr 2022quarterly activities report● Neutral

March 2022 quarterly: cash and liquid investments of €141m, with the Insheim plant earning €1.7m revenue. Licences grew to over 1,000km2, the LG Energy Solution offtake became binding, and Frankfurt trading began. DFS still due H2 2022; Wedin flags equipment delivery delays.

Discuss in chat

22 Apr 2022admin correction● Neutral

Vulcan lodged an amended Trading Policy approved by the board on 19 April 2022, covering insider trading rules for staff and insiders. Administrative notice with no bearing on the project.

Discuss in chat

20 Apr 2022director officer appointment▲ Good

Mark Skelton joined as a Non-Executive Director, bringing over 35 years of experience including 29 years at BP and Fortescue project roles. The chair says he adds major-project delivery skills, following Dr Hilken's appointment.

Discuss in chat

6 Apr 2022investor presentation● Neutral

April 2022 corporate presentation. Visible text is only disclaimers and risk warnings; no new results are readable.

Discuss in chat

6 Apr 2022material agreement▲ GoodMajor

Vulcan signed a binding 20-year agreement to supply MVV Energie with renewable heat from 2025, 240,000 to 350,000 MWh per year, for Mannheim homes. Its first heat offtake, adding an energy revenue line beside lithium; supply depends on planned Mannheim wells in Phase 2.

Discuss in chat