The story so far
The events that changed the company's story, in plain English, each written against everything known about the company at the time. The dot shows whether it was good, bad or neutral for shareholders.
2026
- 15 Oct
The seventh Lionheart well, LSC-3a, tested the first brine reinjection into the reservoir matrix: about 64 l/s injection capacity under planned conditions versus ~40 l/s assumed in the field plan. Results so far meet or exceed plan; follows the seventh well spud reported in June.
well test result
- 21 Sept
Commercial scale production of VULSORB, Vulcan's lithium-extraction adsorbent, has started with a European tolling partner, making first-fill volumes for Lionheart ahead of commissioning in H2 2028. Manufacture will run over 18-24 months; licensing to third parties is also planned.
production update
- 11 Sept
Vulcan is granted a second lithium production licence, Ilka, covering the Landau permit area, valid six years to 9 September 2032. It follows the March 2026 LiThermEx licence; Vulcan plans to later combine them into one of at least 30 years. Lionheart 2028 target stated on track.
regulatory community update
- 10 Sept
Angus Barker becomes Non-Executive Chair from 12 September 2026. Founder Dr Francis Wedin moves from Executive Chair to a Founder consultancy role focused on growth and business development. The Board says Lionheart being financed and under construction makes it the right time.
director officer appointment
- 3 Sept
Phase Two Project Ludwig PFS, about 60km north of Lionheart: pre-tax NPV8 €2.6bn, IRR 25.0%, capex €1.26bn (15% below Lionheart), 21,100tpa lithium carbonate. Indicated resource rises 91% to 1,251kt LCE. FID is planned after Lionheart start-up.
resource reserve update
- 3 Aug
Amanda Lacaze, who retired as Lynas Rare Earths CEO in June 2026, is appointed independent non-executive director effective 17 August 2026. She will also join the Audit, Risk and ESG Committee.
director officer appointment
- 28 May
Vulcan reaches Financial Close on the €2.2bn Lionheart financing package announced in December 2025. The remaining funds can now be accessed, subject to customary ongoing drawdown conditions expected to be met in line with the construction schedule.
debt financing
- 20 Apr
Vulcan signs a roughly €40m framework agreement with Siemens for engineering, automation and building technology on Lionheart, with a minimum €40m of purchase orders. Described as the final major supply agreement; Siemens Financial Services is also investing €67m in the December 2025 financing.
contract award
- 13 Apr
Rhineland-Palatinate grants a lithium royalty exemption for an initial five years to 31 December 2030, with review a year earlier. Lionheart's upstream facilities are under construction in the state and are set to benefit, following a similar 2009 geothermal exemption.
regulatory community update
- 17 Mar
Vulcan is granted its first lithium production licence (LiThermEx), covering the Insheim area, for an initial six years, with extension to at least 30 years planned. It is the first such licence in the Upper Rhine Valley and Rhineland-Palatinate. More licences are planned for the rest of Lionheart.
regulatory community update
2025
- 29 Dec
The retail offer raises about €147m at A$4.00, with HOCHTIEF taking ~58m shortfall shares. Total equity raised is about €545m (A$973m). HOCHTIEF is expected to hold about 15.41%, so its conditional placement and EGM Resolution 2 are withdrawn.
capital raising announcement
- 4 Dec
The institutional placement and institutional entitlement offer are completed, raising about €398m (A$710m) from ~178m shares at A$4.00, a 34.7% discount to the last ASX price of A$6.13. Settlement is due 10 December; a retail offer of up to about €205m follows, with HOCHTIEF backstopping up to €130m.
capital raising announcement
- 3 Dec
Sedgman and HOCHTIEF are awarded the EPCM contracts for the Landau and Frankfurt plants, estimated at about €72m and likely to rise after full scoping. Payment is on a fee and cost-reimbursable basis; scoping follows financing completion.
contract award
- 3 Dec
Vulcan's board takes a final investment decision on Phase One Lionheart after securing a €2.2bn financing package: €1,185m senior debt, €204m grants, €150m KfW for 14% of GermanSubCo, €133m for 15% of the project entity, and €528m underwritten equity at A$4.00. Construction starts within days.
capital raising announcement
- 19 Nov
The first new Phase One well at Schleidberg (LSC-1) and its sidetrack LSC-1a met expectations. The main reservoir is about 440m thick versus ~380m expected, and brine lithium is ~183 mg/L, consistent with the resource grade. A further sidetrack and production test come next.
drilling result
- 3 Nov
Vulcan secures the permit to build the Landau Lithium Extraction Plant, meaning all major Phase One construction permits are now in hand. The permit is part of the financing requirements, which are targeted for completion in Q4 2025.
regulatory community update
- 17 Oct
JordProxa is awarded about €140m of contracts for lithium extraction, purification and conversion equipment for Phase One. Signing is a condition precedent to financing, targeted for Q4 2025; pricing can be renegotiated if financing is not notified by 31 December 2025.
contract award
- 13 Oct
Vulcan signs a binding offtake with Glencore for 36,000-44,000t of lithium hydroxide over eight years, about 20% of planned output. It is the final offtake needed for Phase One financing, which is targeted for Q4 2025; start of commercial production is during 2028.
material agreement
- 26 Sept
Vulcan signs a fixed lump-sum turnkey contract of about €110m with Turboden and ROM Technik to build the Landau geothermal power plant. It is a condition precedent to financing, and material payments depend on financing being finalised, targeted for H2 2025.
contract award
- 10 Sept
Vulcan receives the permit to build and operate the Central Lithium Plant at Höchst, Frankfurt (up to 24,000t LHM a year). The Li4BAT grant financing deadline moves to 31 December 2025, and offtakes with Umicore, LG and Stellantis are amended, with one last offtake still being negotiated.
regulatory community update
- 5 Sept
Vulcan signs a supply contract with NORAM (NESI) as exclusive electrolysis technology supplier for the Central Lithium Plant in Frankfurt, following NESI's work on the CLEOP pilot plant. Construction contracts are a prerequisite for financing; more contracts are expected in coming weeks.
contract award
- 23 July
Two German government grants totalling up to about €104m (~A$186m) are approved for Li4BAT, supporting the Landau and Frankfurt lithium plants. Payment depends on financing being finalised by 1 September 2025 (extension being sought), construction by January 2026, and a €150m Raw Materials Fund investment by 31 March 2026.
material agreement
- 10 July
Vulcan completes a €30m (~A$53.6m) placement of ~15.8m shares at A$3.40 (7.3% below the 15-day VWAP), with BNP Paribas' Clean Energy Solutions Fund taking €15m. Funds keep critical-path Phase One work going, including extending the EPCm contracts to October 2025. Financing is still targeted for H2 2025.
capital raising announcement
- 7 July
After 3D seismic, the Mannheim lithium brine resource rises 76%, from 1,833kt to 3,225kt LCE (820kt Indicated, 2,405kt Inferred). A maiden geothermal resource is also estimated. A scoping study for a future phase is under way; MVV heat offtake talks are ongoing.
resource reserve update
- 24 June
Vulcan signs a heat offtake agreement with EnergieSüdwest for at least 35 years, following heat supply starting in April 2025. Volumes step up from 25 GWh to a potential 595 GWh by 2042. D12 supply depends on land purchase, a building permit and an ESW investment decision.
material agreement
- 13 June
Building permits are approved for the 30MW geothermal power plant and electrical substation at Landau, part of Phase One. Vulcan already sells power from a smaller 4.8MW plant nearby (about 6,500 homes). This advances Phase One permitting; construction still waits on financing.
regulatory community update
- 12 June
The conditional debt commitment letter from the commercial bank group, signed in December 2024, is extended to September 2025 to match the H2 2025 financing timeline. It remains conditional on due diligence, credit approvals and final documentation, with terms otherwise unchanged.
debt financing
- 27 May
Vulcan's Vercana subsidiary starts drilling the first new Phase One well at Schleidberg near Landau, the fifth well in the project area. This begins sub-surface execution of the planned 24 new wells; full execution waits for financing to complete.
drilling spud
- 7 Apr
Vulcan completes the acquisition of 100% of Geox, with its Landau geothermal wells and licence, replacing the earlier joint venture and brine offtake. About €3.3m was paid on 7 April; a final €11.03m is due by 31 October 2025, plus 5% interest.
asset acquisition disposition
- 2 Apr
Germany's €1bn Raw Materials Fund has moved Vulcan's project to detailed due diligence. To allow its possible inclusion, Vulcan now targets H2 2025 to finalise Phase One financing and start full construction, later than the earlier first-half 2025 expectation for final documents.
debt financing
- 26 Mar
The European Commission designates the Phase One Lionheart Project an EU Strategic Project under the Critical Raw Materials Act, from 170 applications. It allows Vulcan to request a financing subgroup meeting and opens possible regional funding. No funding amount is stated.
regulatory community update
- 4 Feb
Vulcan starts moving its V20 drilling rig to the Schleidberg site near Landau, the first Phase One execution work. Well drilling is scheduled for Q2 2025, subject to rig commissioning. The V10 rig will go to Trappelberg only after Phase One financing closes.
drilling scheduled
- 13 Jan
Vulcan produces battery-quality lithium hydroxide at its Höchst demonstration plant, weeks after operations began in November 2024. It is described as Europe's first fully integrated product from brine to final chemical. It will feed qualification with Stellantis, Renault, LG and Umicore.
production update
2024
- 18 Dec
Vulcan signs a €879m (~A$1.45bn) conditional debt commitment letter with EFA and seven commercial banks, toward a €1.5-1.6bn target. It remains conditional on approvals from EDC, Bpifrance and SACE; final documents are expected in the first half of 2025.
debt financing
- 12 Dec
The €100m (A$164m) placement is completed at A$5.85 (€3.57) per share, about 28 million new shares, with trading resuming. €6m settles late, around 8 January 2025. A correction tells investors to disregard BES#1-3 economics in the presentation.
capital raising announcement
- 12 Dec
The EIB Board approves its participation in Phase One financing, potentially up to €500m (~A$819m), subject to final due diligence, legal documents and final internal approval. This advances the EIB thread open since the February 2024 appraisal stage.
debt financing
- 11 Dec
Vulcan launches a fully underwritten €100m (A$164m) placement at A$5.85 (€3.57), an 11.9% discount to the last price, plus a targeted €12.2m (A$20m) share purchase plan. Funds start Phase One execution, including rig mobilisation and EPC contracts. Total project funding is put at about €2.2bn.
capital raising announcement
- 9 Dec
Export Finance Australia conditionally approves a €120m (~A$196m) commitment to Vulcan's Phase One debt financing, following its October 2023 non-binding letter of support. It remains subject to final due diligence and legal documentation; more commitments are expected in coming weeks.
debt financing
- 21 Nov
Vulcan signs a staged agreement with BASF to develop geothermal heat for its Ludwigshafen site, targeting 2,000-2,500 GWh a year. Seismic costs are shared evenly, with BASF paying up to €5m. A lithium extraction plant is possible, with Vulcan keeping 100% of lithium.
material agreement
- 12 Nov
Vulcan is awarded €100m (A$162m) in German federal grant funding for the HEAT4LANDAU district heating project: €22m in 2026 and €78m in 2027. This is the first of the public grants awaited, and Vulcan says Phase One financing is timed to follow the grant process.
material agreement
- 8 Nov
First lithium hydroxide has been produced at the CLEOP plant in Höchst from Landau lithium chloride. This resolves the pending first-product milestone since commissioning began in August. Product will go to Stellantis, Renault, LG and Umicore for qualification. Registered address also changed.
production update
- 8 Oct
Debt talks with the EIB, four export credit agencies and four structuring banks have advanced, and the lending pool is now being widened to other commercial banks. Vulcan targets credit approvals and commitment letters by end 2024, and signing finance documents in Q1 2025.
debt financing
- 27 Sept
Vulcan agrees to buy 100% of Geox, owner of Landau geothermal wells and licence, for deferred cash of about €15m, replacing the IKAV joint venture. Payment is conditional on Phase One financing, due by 30 June 2025 at the earliest. A €10m BNP Paribas credit facility and updated ESIA were also announced.
asset acquisition disposition
- 13 Sept
Angus Barker joins the board as non-executive director on 13 September 2024. Annie Liu leaves that day; Gavin Rezos and Ranya Alkadamani retire 31 December 2024. The board is being streamlined, with room left for possible strategic-investor nominees.
director officer appointment
- 8 Aug
Commissioning has started at CLEOP 1, the 100%-owned lithium hydroxide optimisation plant at Höchst, with power fed through the main switchboard. First lithium hydroxide and battery-grade product are still to come, following the mid-2024 expectation noted earlier.
production update
- 3 June
Vulcan raises €40m (~A$65m) in private placements at €2.50 (A$4.08) per share, a 9% discount to the 30-day VWAP. CIMIC takes €25m (~6%), Hancock €12.5m (to ~7.5%), Smorgon €2.5m. Funds support early EPCM validation and long-lead items ahead of final financing.
capital raising announcement
- 17 May
Vulcan launches the second and final phase of its project-level debt and equity financing (target 65:35 debt:equity). ABN-AMRO, ING, Natixis and UniCredit plus four export credit agencies and the EIB (up to €500m, not committed) move to due diligence. Completion now targeted by end of 2024; earlier target was end Q2 2024.
debt financing
- 11 Apr
First lithium chloride produced at the Landau plant, meeting the Q1 2024 target. Extraction efficiency is consistently over 90% (up to 95%). The €40m+ plant is a pre-commercial optimisation facility; conversion to hydroxide at Höchst is expected mid-2024.
production update
- 23 Feb
European Investment Bank says Phase One has reached 'Under Appraisal' and proposes financing of up to €500m (~A$825m), subject to due diligence, credit approval, legal agreement and board approval. It is not yet committed, but would be a cornerstone for the BNP-led debt process.
debt financing
- 15 Jan
Felicity Gooding, formerly CFO of Fortescue Future Industries, is appointed Group CFO. Robert Ierace steps down as CFO-Australia from 15 January 2024 but stays until end of March to assist the transition. Phase One financing is already under way.
director officer appointment
2023
- 13 Dec
Landau City Council on 12 December approved an agreement letting Vulcan begin building the Phase One geothermal and lithium extraction plant, with land purchase to follow once agreed conditions are met. Vulcan targets first on-spec lithium in Q1 2024 and financing finalised by end of Q2.
regulatory community update
- 16 Nov
Bridging Study cuts Phase One capex about €100m to €1,399m (from €1,496m) and opex to €4,022/t. Post-tax NPV stays €2.6B, with 4.2-year payback. First Proved and Probable reserve of 0.57Mt LCE at 181mg/L, in the Lionheart area. Still 24ktpa lithium hydroxide.
resource reserve update
- 26 Oct
Export Finance Australia gave a conditional, non-binding letter of support for up to A$200m (about €120m) towards Phase One financing. It adds to Bpifrance, SACE and EDC support. Formal financing is due to start mid-November, after the bridging study.
debt financing
- 29 Sept
Resource rises to 27.7Mt LCE at 175 mg/L from 26.6Mt. The Phase One Lionheart area holds 4.16Mt in Measured and Indicated. The plan now centres on core Insheim-Landau wells, dropping the higher-risk step-out zone. Bridging study now due November, then financing starts.
resource reserve update
- 21 Sept
Vulcan was granted the Luftbrücke geothermal and lithium exploration licence, 207 km2 around Frankfurt including Höchst and the airport. Project area grows 13% to over 1,790 km2. A jointly funded research well is drilled, with brine analysis under way.
regulatory community update
- 6 Sept
Phase One bridging study is 80% complete, due October. It proposes one central extraction plant and one geothermal plant instead of two each, at unchanged 24 ktpa. Full project financing is targeted to start in November. A building permit was received for the Hoechst electrolysis pilot plant.
regulatory community update
- 17 Aug
Commissioning has started at the Landau lithium extraction optimisation plant, on the schedule set in June. It runs to October, when first brine goes in. The plant can make about 100 tonnes a year of lithium chloride, ahead of commercial operations targeted for end-2025.
production update
- 13 July
Landau City Council approved entering contract negotiations to sell land for the Phase One lithium extraction plant. The mining authority approved the first operating plan for new Insheim wells, and the Ortenau II permit was extended to end-2025. Advances Phase One permitting.
regulatory community update
- 30 June
From 1 July 2023, Deputy CEO Cris Moreno becomes Managing Director and CEO. Founder Francis Wedin moves to Executive Chair and Gavin Rezos to Non-Executive Deputy Chair. The company says this suits the shift from development to execution.
director officer appointment
- 27 June
Binding term sheet with SLB to drill at least 15 production and re-injection wells for Phase One, with US$3.6m of in-kind services and a right of first refusal on well scope. A Master Supply Agreement is to be negotiated within 60 days. Advances the drilling plans.
material agreement
- 31 May
Binding term sheet with Stellantis, its fourth agreement with Vulcan, for a pre-feasibility study of geothermal energy for the Mulhouse plant in France. If the study succeeds, the parties aim to develop it 50:50, with energy possibly from 2026. Builds on the Rüsselsheim term sheet.
material agreement
- 4 May
Launches a fully underwritten placement of 21.4m shares at A$5.10 (€3.08) to raise €66m (A$109m), a 17.2% discount to the last ASX price. Funds go to long lead items for Phase One, wells, land and Phase 2 seismic. Follows the earlier funding plans.
capital raising announcement
- 4 May
The placement completed: €66m (A$109m) raised from 21.4m new shares at A$5.10. Settlement is 11 May, with trading from 15 May. It resolves the launch announced the same day and funds Phase One long lead items.
capital raising announcement
- 27 Apr
Non-binding term sheet with Nobian for a 50/50 joint venture over the Central Lithium Plant: Nobian would contribute EUR161m cash against a EUR322m pre-money valuation, with EUR15m on signing definitive agreements. Definitive agreements are targeted within 10 weeks and are not guaranteed.
material agreement
- 19 Apr
Export credit agencies from France (Bpifrance) and Italy (SACE) confirmed in-principle support or eligibility, and Canada's EDC confirmed interest, for Phase One financing, subject to conditions. Target is a 65:35 debt-to-equity split on EUR1.496B capex, with financing completion aimed for Q1 2024; project-level equity talks are under way.
debt financing
- 13 Feb
Phase 1 DFS completed: 24ktpa lithium hydroxide, post-tax NPV8 €2.6B (pre-tax €3.9B), post-tax IRR 26%, capex €1,496m, targeted production end-2025. Resource rises to 26.6Mt LCE; Phase 1 reserves 0.54Mt LCE. Delivers the DFS promised for Q1 2023.
resource reserve update
- 17 Jan
Vulcan signed a binding term sheet with Stellantis, its largest lithium customer and a major shareholder, for a phased geothermal heat project at Stellantis' Rüsselsheim plant. Phase A is a Vulcan-run pre-feasibility study; Stellantis would repay 50% of Vulcan's costs if it does not proceed.
material agreement
2022
- 14 Nov
Vulcan developed its own lithium extraction sorbent, VULSORB, which it says outperformed commercial sorbents tested in the pilot plant with lower water use. It is the first-choice sorbent for Phase 1; first commercial lithium production is now targeted Q4 2025.
other
- 2 Nov
Vulcan is expanding into Alsace, France, setting up Vulcan Energie France and applying for its first 155km2 lithium exploration licence, Les Cigognes. Stellantis and Renault, both existing customers, endorse it. Licence is only applied for, not yet granted.
asset acquisition disposition
- 24 Oct
Pilot plant produced lithium hydroxide grading 57.1% LiOH, above the 56.5% battery-grade spec required by offtake customers, with low impurities. Pilot data is now sufficient to complete the Phase 1 DFS, still scheduled Q1 2023; first commercial production now targeted 2025.
well test result
- 26 Sept
Cris Moreno will join as Deputy CEO from 1 November 2022, based in Europe. He has over 20 years in major projects, including LNG roles at Santos, Woodside and Shell, and recent lithium work at Northvolt and Aurora Lithium.
director officer appointment
- 13 Sept
Onsite construction began on the Landau Sorption Demo Plant, and 3D seismic crews mobilised at Insheim. A second Taro preliminary environmental approval was granted. DFS completion is now likely Q1 2023, slipping from the H2 2022 target; rigs likely early Q2 2023.
regulatory community update
- 8 July
Vulcan signed a binding collaboration with Enel Green Power to scope the Cesano lithium licence in Italy, which will become co-owned 50:50. Separately, the Sorption (DLE) Demo Plant commissioning slipped to late Q4 due to supply chain issues; Taro wells need no full environmental assessment.
farm in farm out agreement
- 24 June
Stellantis agreed a A$76M (€50M) equity investment at A$6.622 per share (about 11.45m shares), becoming the second largest shareholder at 8%. Funds go to production expansion drilling, and its lithium hydroxide offtake was extended five years to 2035.
capital raising announcement
- 6 Apr
Vulcan signed a binding 20-year agreement to supply MVV Energie with renewable heat from 2025, 240,000 to 350,000 MWh per year, for Mannheim homes. Its first heat offtake, adding an energy revenue line beside lithium; supply depends on planned Mannheim wells in Phase 2.
material agreement
- 15 Feb
Vulcan's German regulator BaFin approved the listing prospectus, and trading on the Frankfurt Prime Standard is expected from 15 February 2022, making it the first ASX-listed company to dual list there. The ASX listing is unaffected. Confirms the February filing; no new shares offered.
other
- 31 Jan
Vulcan signed the binding LG Energy Solution offtake for 41,000-50,000t of lithium chemicals over five years from January 2025, market-priced. This resolves the open definitive-agreement thread. Conditions include project finance and commissioning; Vulcan says the first five years are now fully sold.
material agreement
- 24 Jan
Vulcan was granted the 11.5 km² Cesano research permit near Rome, where a 1976 well sample showed historical lithium of 350 and 380 mg/l. Grades are unverified; Vulcan will review data first. It is a possible future addition beyond the Rhine project.
regulatory community update
- 4 Jan
Vulcan was granted five new exploration licences covering 325km² in the Upper Rhine Valley, lifting granted area by nearly 50% to over 1,000km². DFS is now targeted for H2 2022, with first production by 2024.
regulatory community update
2021
- 15 Dec
Vulcan settled its Federal Court case against J Capital and Timothy Murray, with permanent restraints on them publishing about the company and an open apology. This resolves the October short-report dispute; settlement terms beyond the orders are not stated.
other
- 10 Dec
Vulcan agreed to buy 100% of the operating Insheim geothermal power plant from Pfalzwerke for about €31.5m, from the A$200m raise, taking over 1 Jan 2022. It reported 2020 sales of €5.8m and EBITDA of €2.9m. A 20-year Landau brine offtake was also signed.
asset acquisition disposition
- 8 Dec
Vulcan signed a binding offtake with Volkswagen Group for 34,000-42,000t of lithium hydroxide over five years from 2026, market-price take-or-pay, plus a first right of refusal on extra capacity. Conditions include commercial start and product qualification. Adds to the Stellantis, Renault and Umicore deals.
material agreement
- 29 Nov
Vulcan signed a binding offtake with Stellantis for 81,000-99,000t of lithium hydroxide over five years from 2026, market-price take-or-pay. Conditions include successful commercial start and product qualification. It adds to the Umicore and Renault agreements.
material agreement
- 22 Nov
Vulcan signed the definitive binding Renault offtake, converting the August term sheet: 26,000-32,000t lithium hydroxide over six years from 2026, about 12% of planned output, market-price take-or-pay. Conditions include successful commercial start and product qualification.
material agreement
- 19 Nov
Vulcan agreed to acquire two electric deep-drilling rigs, using part of the A$200m raise, and formed in-house drilling company VERCANA. One purchase is complete; the other awaits a final contract. Rigs are operation-ready in late 2022; drilling targeted late 2022. Price not stated.
asset acquisition disposition
- 18 Oct
Vulcan signed a binding offtake agreement with Umicore for 28,000 to 42,000 tonnes of lithium hydroxide over five years from 2025, about 20% of planned output. Pricing is market-based, take-or-pay. Conditions include DFS publication, project finance and product qualification. Adds to the LGES and Renault term sheets.
material agreement
- 29 Sept
Vulcan signed an agreement with Infraserv to secure a site at the Höchst Chemical Park near Frankfurt for its planned Central Lithium Plant. Permits for construction and operation are still to be obtained. It advances the project toward commercial plant development.
material agreement
- 27 Sept
Vulcan produced its first battery-quality lithium hydroxide monohydrate (above 56.5% LiOH.H2O, very low impurities) from its pilot plant, with electrolysis done offsite. This builds on the pilot running since April 2021; data feeds the DFS and samples will go to offtake partners.
other
- 16 Sept
Vulcan completed the A$200m placement at A$13.50 per share, with Hancock Prospecting and ESG-focused institutions participating. Settlement is expected 21 September. An SPP of up to A$20m opens 24 September, and directors may add up to A$1m, subject to shareholder approval.
capital raising announcement
- 14 Sept
Vulcan launched an underwritten A$200m placement of about 14.8m shares at A$13.50 (15.1% discount), plus up to A$20m share purchase plan at the same price and up to A$1m from directors. Funds target exploration equipment, brownfield energy and brine assets, and expanded development. Follows February's A$120m raise.
capital raising announcement
- 23 Aug
Vulcan appointed BNP Paribas as financial adviser, starting with a bankability review before the DFS and then structuring and executing project financing. BNP's energy fund was already a February placement investor. Addresses the open question of funding the roughly €700m initial capex.
material agreement
- 2 Aug
Renault Group signed a binding five-year offtake term sheet for 6,000 to 17,000t a year of lithium hydroxide from 2026, the second major offtaker after LGES. It is conditional on a definitive agreement by 20 November 2021 and product qualification. Pricing is market-based.
material agreement
- 19 July
Vulcan signed its first binding offtake term sheet, with LG Energy Solution: 5,000t of lithium hydroxide in year one, rising to 10,000t a year, for five years from 2025. Pricing is market-based. It is conditional on a definitive agreement by 30 November 2021, the DFS, project finance and commissioning.
material agreement
- 11 June
Kuniko lodged its IPO prospectus to raise $7,886,213 at $0.20 per share: $2.5m public offer plus a 1-for-4 priority offer to Vulcan holders (record date 16 June). Chairman Rezos will be Kuniko's Executive Chair. Continues the April spin-off plan.
asset acquisition disposition
- 27 May
The DLE pilot plant hit its target feed specification and achieved over 90% lithium chloride recovery from Upper Rhine brine. This follows the April start-up. Next steps are 24/7 operation and making samples for potential offtakers.
flow test result
- 27 Apr
Vulcan signed a binding deal to buy 100% of German geothermal engineering firm gec-co from COO Thorsten Weimann, subject to shareholder approval. Payment is 325,000 shares plus an earnout of up to €1,190,000 tied to permitting. It follows the GeoT acquisition.
asset acquisition disposition
- 21 Apr
Vulcan plans to spin off its Norwegian copper, nickel and cobalt assets into a new company, Kuniko (proposed code KNI), with an IPO. Shareholders get a 1-for-4 priority offer at 20c, and Vulcan keeps about 27%. This resolves the open Norwegian assets review and sharpens focus on German lithium.
asset acquisition disposition
- 17 Feb
Vulcan is collaborating with DuPont Water Solutions to test and scale up direct lithium extraction on its brine, as input to the DFS. No payment terms are shown. It is aimed at reducing technical risk in the extraction step.
material agreement
- 15 Feb
Vulcan agreed to buy 100% of Global Geothermal Holding, its partner on the Taro licence, where it has earned 51%. Payment is shares only: $90,000 on completion plus $720,000 in milestone-based performance shares. It needs shareholder approval.
asset acquisition disposition
- 10 Feb
Vulcan signed a binding agreement to buy 100% of geothermal consultancy GeoT for €1.00, to grow its development team. GeoT is owned by executive director Dr Horst Kreuter, who is owed about €140,000 by it; completion is subject to due diligence.
asset acquisition disposition
- 4 Feb
Vulcan raised A$120m through a placement of 18,461,538 shares at A$6.50, a 17.1% discount to the last close, with Hancock Prospecting as cornerstone. Cash will be about A$125m before costs, funding the project to final investment decision, with a DFS targeted for mid-2022.
capital raising announcement
- 1 Feb
Thorsten Weimann joins as Chief Operating Officer, with over 25 years in German geothermal development, to oversee the Zero Carbon Lithium Project. Separately, Vulcan's lithium product manager Dr Katharina Gerber was elected chair of the German ISO lithium standards committee.
director officer appointment
- 15 Jan
PFS completed: post-tax NPV €2.25B for the full project, about 40ktpa lithium hydroxide, 74MW of power, and OPEX of €2,640/t. Maiden Probable Ore Reserve of 1.12Mt LCE. Starting capital is €700m, and Phase 2 raises total capex to €1.74B. Resolves the open PFS thread; DFS next.
resource reserve update
2020
- 15 Dec
Ortenau upgraded: 2.06Mt LCE Indicated, with Inferred revised to 10.80Mt. Total Upper Rhine resource is now 15.85Mt LCE, with 23% Indicated. Continues the 12 November Taro upgrade; the Indicated portion feeds the PFS, with final review expected by January.
resource reserve update
- 12 Nov
Taro resource upgraded: 0.83Mt LCE Indicated plus Inferred raised to 1.44Mt. Total Upper Rhine resource rises to 16.19Mt LCE (90% Inferred), from 15.37Mt. Vulcan says it has met the €500,000 spend to earn 51% of Taro, with a further €500,000 to reach 80%.
resource reserve update
- 31 Aug
Taro licence granted; maiden Inferred resource of 1.42Mt LCE at 181mg/l Li. Total Upper Rhine resource rises to 15.37Mt LCE (95% Inferred), from 13.95Mt. Vulcan can earn 80% of Taro by spending €1M, with 51% after the first €500,000.
resource reserve update
- 3 Aug
Bench-scale (10L) direct lithium extraction tests on Upper Rhine geothermal brine recovered over 90% of lithium on first pass with two commercially used adsorbents. Delivers the test results promised earlier; feeds the PFS, with optimisation continuing.
other
- 8 July
EIT InnoEnergy signs a staged investment agreement with Vulcan: €150,000 first tranche (about A$245,534), then two €50,000 tranches, with warrants priced at the 15-day VWAP (A$0.512). Small sum; subject to shareholder approval. Follows the 26 May support agreement.
material agreement
- 24 June
Vulcan raises $4.8M (before costs) via a placement of 12,000,000 shares at 40 cents, described as significantly oversubscribed. Funds go to the PFS, a pilot plant and the seismic data purchase. Lead managers get 6% fees plus 1,125,250 options at 80c, subject to shareholder approval. Follows cash of about $2.5M in March.
capital raising announcement
- 26 May
Vulcan signs a binding agreement with EU-backed EIT InnoEnergy to help secure project funding, grants, offtakers and licences in Germany. Fees are entirely success-based with no upfront cost, and may be paid in shares at 30-day VWAP, subject to shareholder approval. Addresses the open funding and offtake threads.
material agreement
- 4 May
Vulcan signs an option to buy a seismic data package (about 50km2 3D survey, eight 2D lines totalling 80km) over several licence application areas in the Upper Rhine Valley. €30,000 option fee, then €570,000 purchase at Vulcan's election within nine months. Company says it could save over a year of exploration time and about 70% of survey cost.
asset acquisition disposition
- 21 Feb
Positive scoping study for a two-stage plan: Stage 1 lithium extraction and hydroxide plant at an operating geothermal plant (Insheim), Stage 2 ten new wells at the Ortenau licence. Offtake and financing talks begun; pre-feasibility study targeted for late 2020. Economic figures not visible in the text provided.
other
- 20 Jan
Maiden Indicated resource at the Insheim licence of 722,000t LCE at 181mg/l Li, higher confidence from producing-well data. Combined Vulcan resource is now 13.95Mt LCE across 2 of 6 licences. Scoping study still on track for Q1 2020.
resource reserve update
2019
- 4 Dec
Maiden JORC Inferred resource for the Ortenau licence of 13.2Mt contained lithium carbonate equivalent at 181mg/l Li, 100mg/l cutoff. Delivers the resource flagged as imminent; company calls it Europe's largest. Covers one of five licence areas; scoping study now due Q1 2020.
resource reserve update
- 2 Dec
Brine sampling of Upper Rhine geothermal wells returned 104-215mg/l lithium (average 181mg/l), above expectation. Insheim, covered by the Pfalzwerke MoU, had the highest average. Results feed a maiden resource estimate expected imminently. Wells sampled lie mostly outside Vulcan's licences.
drilling result
- 26 Nov
Vulcan signed an MoU with Pfalzwerke geofuture over the operating Insheim geothermal plant. Vulcan can earn up to 80% of the lithium rights by completing pre-feasibility and definitive feasibility studies, starting at 0% and funding a demonstration plant, without drilling its own geothermal well.
joint venture update
- 5 Sept
Koppar completed the Vulcan Lithium Project acquisition on the 10 July terms. Francis Wedin became Managing Director and Gavin Rezos Chairman; Rebecca Morgan resigned. Issued capital is 48,500,002 shares. Scoping study targets end-2019; Norwegian target ranking continues.
farm in farm out completion
- 20 Aug
First Vulcan update: a conceptual Exploration Target of 10.73 to 36.20Mt lithium carbonate equivalent across the five licences. It is not a Mineral Resource, and no exploration has yet been done at the project.
resource reserve update
- 19 July
Placement completed: 6,333,334 shares issued at $0.15 (about $950,000, calculated), with 6% fees. Dilution of 16.78% on 34,570,001 prior shares. Funds the new Vulcan lithium direction (inference).
capital raising announcement
- 10 July
Koppar signed a binding heads of agreement to acquire 100% of Vulcan Energy Resources, a lithium brine project in Germany's Upper Rhine Valley (78,600ha, brines averaging 161mg/l Li). Francis Wedin proposed as MD and Gavin Rezos as Chairman. A strategy shift away from Norwegian copper-zinc.
business combination
- 22 Jan
Koppar renewed key permits but chose not to renew Løkken, Killingdal, Storwartz and Fløttum, narrowing focus to Tverfjellet, Undal, Grimsdal and Vangrøfta. It is also reviewing acquisitions across commodities and jurisdictions. Grimsdal drilling still awaits National Park authority permission.
asset acquisition disposition
2018
- 16 Oct
Rock chip assays from Vangrøfta returned up to 16.75% copper, 3.33g/t gold and 0.216% cobalt, with 11 of 13 samples above 1% Cu. This resolves the pending assays; surface samples from old workings only, with historical data review underway.
drilling result
- 10 Sept
The Grimsdalen EM survey found five conductors, including three not previously drilled; two are chosen for drilling next quarter. The top target, GR1, is modelled at over 1000S conductance and about 500m x 500m. The Killingdal survey is complete, with results pending.
drilling result
- 29 Aug
Koppar pegged 507.5 km2 of new Norwegian ground, lifting its holding from about 58 km2 to 565.4 km2, with 18 more permits (174.6 km2) pending. New projects include Undal, Flottum and Rødalen-Lomsjodalen. The Grimsdal-Nygruva EM survey is complete.
asset acquisition disposition
- 28 May
Koppar confirmed it completed the acquisition of 100% of Koppar Resources Europe, issuing 1.25 million shares. Up to 8 million further shares are issuable on milestones; the cash consideration was removed, and the public offer is complete.
asset acquisition disposition
- 28 May
Koppar Resources (code KRX) was admitted to the ASX official list on 28 May 2018, with trading due 30 May. It raised $4.5 million by issuing 22.5 million shares at $0.20 each, giving 24.6 million quoted shares.
other