Each one in plain English, with the numbers worked through for a shareholder.
23 Feb 2024debt financing▲ GoodMajor
European Investment Bank says Phase One has reached 'Under Appraisal' and proposes financing of up to €500m (~A$825m), subject to due diligence, credit approval, legal agreement and board approval. It is not yet committed, but would be a cornerstone for the BNP-led debt process.
December 2023 quarter cash flow: cash fell to €78.6m from €112.7m. Operating outflow was €4.3m and investing outflow €30.3m. No debt drawn; stated funding is 7.8 quarters, down from 9.88 in the September quarter.
December quarter report: Landau plant brine introduced in November and plant opened 23 November; first on-spec lithium chloride still targeted Q1 2024, hydroxide plant readiness Q2. Financing is progressing. Largely repeats known events; Insheim produced 5,680 MWh at €0.252/kWh (about €1.4m).
Non-executive director Mark Skelton retires from the board from 1 February 2024, after joining in April 2022. Dr Günter Hilken will chair the Projects Oversight Committee. The company says construction of the Landau extraction plant is complete.
15 Jan 2024director officer appointment● NeutralMajor
Felicity Gooding, formerly CFO of Fortescue Future Industries, is appointed Group CFO. Robert Ierace steps down as CFO-Australia from 15 January 2024 but stays until end of March to assist the transition. Phase One financing is already under way.
Landau City Council on 12 December approved an agreement letting Vulcan begin building the Phase One geothermal and lithium extraction plant, with land purchase to follow once agreed conditions are met. Vulcan targets first on-spec lithium in Q1 2024 and financing finalised by end of Q2.
The environmental and social impact assessment by ERM is complete, with no impact rated above minor after mitigation. It is a prerequisite for green debt finance and feeds into Phase One financing, which the company says has been initiated. Closes the October ESIA item.
Presentation of the Bridging Study results, launching Phase One financing. Visible text is only the cover and disclaimers; it repeats the study released the same day and carries no new readable figures.
Bridging Study cuts Phase One capex about €100m to €1,399m (from €1,496m) and opex to €4,022/t. Post-tax NPV stays €2.6B, with 4.2-year payback. First Proved and Probable reserve of 0.57Mt LCE at 181mg/L, in the Lionheart area. Still 24ktpa lithium hydroxide.
September quarter report: project-level Phase One financing is on track to start in November. Brine into the Landau plant now due November (previously October); Bridging Study due early November. Final land package for the extraction plant is expected in Q4. Largely repeats known events.
September 2023 quarter cash flow: cash fell to €112.7m from €147.7m. Operating outflow was €7.6m and investing outflow €27.1m, mostly plant and equipment. No debt drawn; stated funding is 9.88 quarters, down from 13.6 in the June quarter.
Export Finance Australia gave a conditional, non-binding letter of support for up to A$200m (about €120m) towards Phase One financing. It adds to Bpifrance, SACE and EDC support. Formal financing is due to start mid-November, after the bridging study.
Resource rises to 27.7Mt LCE at 175 mg/L from 26.6Mt. The Phase One Lionheart area holds 4.16Mt in Measured and Indicated. The plan now centres on core Insheim-Landau wells, dropping the higher-risk step-out zone. Bridging study now due November, then financing starts.
21 Sept 2023regulatory community update▲ GoodMajor
Vulcan was granted the Luftbrücke geothermal and lithium exploration licence, 207 km2 around Frankfurt including Höchst and the airport. Project area grows 13% to over 1,790 km2. A jointly funded research well is drilled, with brine analysis under way.
Interim group management report for 1 January to 30 June 2023, prepared for Frankfurt listing requirements. Visible text is the contents and company profile; it carries no new figures in the extract.
Half-year report to 30 June 2023. Visible text is the contents and company background, citing the 26.6Mt LCE resource. Financial results are not readable in the extract; the cash position was already reported in the July quarterly.
Phase One bridging study is 80% complete, due October. It proposes one central extraction plant and one geothermal plant instead of two each, at unchanged 24 ktpa. Full project financing is targeted to start in November. A building permit was received for the Hoechst electrolysis pilot plant.
Commissioning has started at the Landau lithium extraction optimisation plant, on the schedule set in June. It runs to October, when first brine goes in. The plant can make about 100 tonnes a year of lithium chloride, ahead of commercial operations targeted for end-2025.
Educational presentation on adsorption-type direct lithium extraction, the method Vulcan uses with its VULSORB sorbent. It covers industry background and Vulcan's plants. No new company results are visible.
Third-quarter 2023 corporate presentation. Visible text is only the cover and disclaimers, referring to the 13 February 2023 DFS; no new results are readable.
June 2023 quarter cash flow: cash rose to €147.7m from €112.0m after €65.9m placement proceeds. Operating outflow was €9.1m and investing outflow €17.0m. No debt drawn; stated funding is 13.6 quarters.
June quarter report: Moreno became CEO, SLB term sheet signed, Stellantis Mulhouse agreement, land packages acquired and the €66m placement completed. Insheim produced 2,282 MWh. Updated Phase One capex and schedule from bridging engineering are due in Q4. Largely repeats known events.
13 July 2023regulatory community update▲ GoodMajor
Landau City Council approved entering contract negotiations to sell land for the Phase One lithium extraction plant. The mining authority approved the first operating plan for new Insheim wells, and the Ortenau II permit was extended to end-2025. Advances Phase One permitting.
30 June 2023director officer appointment● NeutralMajor
From 1 July 2023, Deputy CEO Cris Moreno becomes Managing Director and CEO. Founder Francis Wedin moves to Executive Chair and Gavin Rezos to Non-Executive Deputy Chair. The company says this suits the shift from development to execution.
Binding term sheet with SLB to drill at least 15 production and re-injection wells for Phase One, with US$3.6m of in-kind services and a right of first refusal on well scope. A Master Supply Agreement is to be negotiated within 60 days. Advances the drilling plans.
Director interest notice: Ranya Alkadamani received 25,234 performance rights as part remuneration, valued at $105,000. Her holding of 276,000 shares is unchanged. Administrative; follows the AGM approval of the issue.
Project update: the Landau optimisation plant targets mechanical completion in August and commissioning in September. Senior execution hires were made and Phase One EPCM contracts entered the request-for-proposal stage. Cash is about €164m. Continues the May update.
Binding term sheet with Stellantis, its fourth agreement with Vulcan, for a pre-feasibility study of geothermal energy for the Mulhouse plant in France. If the study succeeds, the parties aim to develop it 50:50, with energy possibly from 2026. Builds on the Rüsselsheim term sheet.
All five AGM resolutions passed on a poll. The placement share ratification had the lowest support at about 80% for. Also a change of company phone number. Issued capital is 164,835,301 shares.
Managing Director's AGM presentation. The visible text is only the cover and disclaimers, referring to the 13 February 2023 DFS and earlier disclosures; no new results are readable.