20 Mar 2026agm notice● Neutral
Vulcan expects to hold its AGM on 28 May 2026, with director nominations closing 15 April 2026. Administrative notice.
Each one in plain English, with the numbers worked through for a shareholder.
20 Mar 2026agm notice● Neutral
Vulcan expects to hold its AGM on 28 May 2026, with director nominations closing 15 April 2026. Administrative notice.
17 Mar 2026regulatory community update▲ GoodMajor
Vulcan is granted its first lithium production licence (LiThermEx), covering the Insheim area, for an initial six years, with extension to at least 30 years planned. It is the first such licence in the Upper Rhine Valley and Rhineland-Palatinate. More licences are planned for the rest of Lionheart.
6 Mar 2026other▲ Good
S&P Dow Jones Indices announces Vulcan will be added to the S&P/ASX 200 Index from 23 March 2026. Index inclusion is not a company announcement of operational change; the text does not state any effect on the company.
2 Feb 2026investor presentation● Neutral
February 2026 corporate presentation. Only the title and disclaimers are readable here, so no new figures can be drawn from it.
30 Jan 2026quarterly activities report▲ Good
Quarter covers FID on Phase One Lionheart backed by a €2.2bn financing package, construction starting December 2025, and a Glencore offtake of 36,000-44,000 tonnes of LHM. Landau building permit secured. The LSC-1b sidetrack flow test met expectations after quarter end.
30 Jan 2026quarterly activities report▲ Good
December quarter cash rose to €523.1m from €47.0m, driven by €545.3m of equity raised, against €7.2m operating outflow and €26.0m investing outflow. This reflects the completed Phase One equity raising. Debt facilities show nil drawn at quarter end.
22 Jan 2026remuneration report● Neutral
From 1 January 2026, CEO Cris Moreno's fixed pay rises to $804,000 and CFO Felicity Gooding's to $670,000, plus super. Short-term incentive opportunity rises from 25% to 50%. The board links this to the move from development into construction.
12 Jan 2026agm notice● Neutral
The 12 January 2026 EGM passed its sole resolution, ratifying the December institutional placement shares, by poll with about 83% of proxy votes in favour. The HOCHTIEF resolution had been withdrawn. Routine follow-up to the equity raising.
29 Dec 2025capital raising announcement▲ GoodMajor
The retail offer raises about €147m at A$4.00, with HOCHTIEF taking ~58m shortfall shares. Total equity raised is about €545m (A$973m). HOCHTIEF is expected to hold about 15.41%, so its conditional placement and EGM Resolution 2 are withdrawn.
12 Dec 2025other● Neutral
Executive Chair Francis Wedin and his associate Magni Associates (15,646,061 and 812,500 shares) cease to be substantial holders on 11 December 2025. The notice attributes this to dilution from the ~178m new shares issued, not to a sale.
10 Dec 2025security holder rights change● Neutral
Notice to shareholders outside Australia and New Zealand that they are ineligible for the retail entitlement offer at A$4.00 and will not receive the booklet, due to cost and complexity of foreign compliance. They need do nothing but will be diluted. Administrative notice.
10 Dec 2025agm notice● Neutral
Notice of an extraordinary general meeting on 12 January 2026 asking shareholders to ratify 61,327,226 placement shares and approve up to 38,592,026 conditional shares for HOCHTIEF. Procedural meeting tied to the December equity raising.
10 Dec 2025capital raising announcement● Neutral
The retail component of the 1-for-1.128 entitlement offer at A$4.00 opens, and is expected to close on 23 December 2025. The booklet and letters go to eligible Australian and New Zealand retail shareholders. Administrative step in the raising announced 3 December.
4 Dec 2025capital raising announcement● NeutralMajor
The institutional placement and institutional entitlement offer are completed, raising about €398m (A$710m) from ~178m shares at A$4.00, a 34.7% discount to the last ASX price of A$6.13. Settlement is due 10 December; a retail offer of up to about €205m follows, with HOCHTIEF backstopping up to €130m.
What it means for a shareholder
178m new shares at A$4.00 to raise about A$710m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Create a free account to see this worked out for your own holding.
3 Dec 2025investor presentation● Neutral
Presentation accompanying the 3 December financing and final investment decision announcement, and the equity raising. Only the title and disclaimers are readable here, so no new figures can be drawn from it.
3 Dec 2025contract award▲ GoodMajor
Sedgman and HOCHTIEF are awarded the EPCM contracts for the Landau and Frankfurt plants, estimated at about €72m and likely to rise after full scoping. Payment is on a fee and cost-reimbursable basis; scoping follows financing completion.
3 Dec 2025capital raising announcement▲ GoodMajor
Vulcan's board takes a final investment decision on Phase One Lionheart after securing a €2.2bn financing package: €1,185m senior debt, €204m grants, €150m KfW for 14% of GermanSubCo, €133m for 15% of the project entity, and €528m underwritten equity at A$4.00. Construction starts within days.
19 Nov 2025drilling result▲ GoodMajor
The first new Phase One well at Schleidberg (LSC-1) and its sidetrack LSC-1a met expectations. The main reservoir is about 440m thick versus ~380m expected, and brine lithium is ~183 mg/L, consistent with the resource grade. A further sidetrack and production test come next.
14 Nov 2025contract award▲ Good
ABB is appointed Main Electrical Contractor for Phase One in contracts worth about €46m, on a fixed-price basis. Signing is a condition precedent to financing, still targeted for Q4 2025.
3 Nov 2025regulatory community update▲ GoodMajor
Vulcan secures the permit to build the Landau Lithium Extraction Plant, meaning all major Phase One construction permits are now in hand. The permit is part of the financing requirements, which are targeted for completion in Q4 2025.
22 Oct 2025quarterly activities report● Neutral
Quarterly report recaps the €104m grants, €30m placement, Mannheim resource, permits and NESI and Turboden contracts. After quarter end: Glencore offtake, JordProxa contract and Schleidberg sidetrack to about 3,700m. No lost time injuries; financing targeted for the rest of 2025.
22 Oct 2025quarterly activities report● Neutral
September 2025 quarter cash flow: cash ended at €47.0m (from €48.8m), after €10.9m operating outflow, €17.8m investing outflow and €30m placement proceeds. The €10m BNP facility remains undrawn.
17 Oct 2025contract award▲ GoodMajor
JordProxa is awarded about €140m of contracts for lithium extraction, purification and conversion equipment for Phase One. Signing is a condition precedent to financing, targeted for Q4 2025; pricing can be renegotiated if financing is not notified by 31 December 2025.
13 Oct 2025material agreement▲ GoodMajor
Vulcan signs a binding offtake with Glencore for 36,000-44,000t of lithium hydroxide over eight years, about 20% of planned output. It is the final offtake needed for Phase One financing, which is targeted for Q4 2025; start of commercial production is during 2028.
10 Oct 2025security holder rights change● Neutral
Shareholders ratified the issue of the July 2025 placement shares (€30m, ~15.8m shares at A$3.40) at the 10 October 2025 meeting, with the sole resolution carried on a poll with about 96% of proxy votes in favour.
26 Sept 2025contract award▲ GoodMajor
Vulcan signs a fixed lump-sum turnkey contract of about €110m with Turboden and ROM Technik to build the Landau geothermal power plant. It is a condition precedent to financing, and material payments depend on financing being finalised, targeted for H2 2025.
19 Sept 2025investor presentation● Neutral
September 2025 corporate presentation. Only the title and disclaimers are readable here, so no new figures can be drawn from it.
11 Sept 2025regulatory community update▲ Good
Landau City Council approves Vulcan's purchase of the land for the G-LEP plant, following the November 2024 option agreement. The purchase is subject to Phase One financing completing, which Vulcan expects in H2 2025.
10 Sept 2025regulatory community update▲ GoodMajor
Vulcan receives the permit to build and operate the Central Lithium Plant at Höchst, Frankfurt (up to 24,000t LHM a year). The Li4BAT grant financing deadline moves to 31 December 2025, and offtakes with Umicore, LG and Stellantis are amended, with one last offtake still being negotiated.
10 Sept 2025half year report● Neutral
Interim management report for the half to June 2025, required for the Frankfurt listing. It restates the Lionheart project and the 29.1Mt LCE total resource; the visible text includes no new figures beyond that.