29 Dec 2025capital raising announcement▲ GoodMajor
The retail offer raises about €147m at A$4.00, with HOCHTIEF taking ~58m shortfall shares. Total equity raised is about €545m (A$973m). HOCHTIEF is expected to hold about 15.41%, so its conditional placement and EGM Resolution 2 are withdrawn.
Executive Chair Francis Wedin and his associate Magni Associates (15,646,061 and 812,500 shares) cease to be substantial holders on 11 December 2025. The notice attributes this to dilution from the ~178m new shares issued, not to a sale.
Notice to shareholders outside Australia and New Zealand that they are ineligible for the retail entitlement offer at A$4.00 and will not receive the booklet, due to cost and complexity of foreign compliance. They need do nothing but will be diluted. Administrative notice.
The retail component of the 1-for-1.128 entitlement offer at A$4.00 opens, and is expected to close on 23 December 2025. The booklet and letters go to eligible Australian and New Zealand retail shareholders. Administrative step in the raising announced 3 December.
4 Dec 2025capital raising announcement● NeutralMajor
The institutional placement and institutional entitlement offer are completed, raising about €398m (A$710m) from ~178m shares at A$4.00, a 34.7% discount to the last ASX price of A$6.13. Settlement is due 10 December; a retail offer of up to about €205m follows, with HOCHTIEF backstopping up to €130m.
What it means for a shareholder
178m new shares at A$4.00 to raise about A$710m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Presentation accompanying the 3 December financing and final investment decision announcement, and the equity raising. Only the title and disclaimers are readable here, so no new figures can be drawn from it.
Sedgman and HOCHTIEF are awarded the EPCM contracts for the Landau and Frankfurt plants, estimated at about €72m and likely to rise after full scoping. Payment is on a fee and cost-reimbursable basis; scoping follows financing completion.
Vulcan's board takes a final investment decision on Phase One Lionheart after securing a €2.2bn financing package: €1,185m senior debt, €204m grants, €150m KfW for 14% of GermanSubCo, €133m for 15% of the project entity, and €528m underwritten equity at A$4.00. Construction starts within days.
The first new Phase One well at Schleidberg (LSC-1) and its sidetrack LSC-1a met expectations. The main reservoir is about 440m thick versus ~380m expected, and brine lithium is ~183 mg/L, consistent with the resource grade. A further sidetrack and production test come next.
ABB is appointed Main Electrical Contractor for Phase One in contracts worth about €46m, on a fixed-price basis. Signing is a condition precedent to financing, still targeted for Q4 2025.
Vulcan secures the permit to build the Landau Lithium Extraction Plant, meaning all major Phase One construction permits are now in hand. The permit is part of the financing requirements, which are targeted for completion in Q4 2025.
JordProxa is awarded about €140m of contracts for lithium extraction, purification and conversion equipment for Phase One. Signing is a condition precedent to financing, targeted for Q4 2025; pricing can be renegotiated if financing is not notified by 31 December 2025.
Vulcan signs a binding offtake with Glencore for 36,000-44,000t of lithium hydroxide over eight years, about 20% of planned output. It is the final offtake needed for Phase One financing, which is targeted for Q4 2025; start of commercial production is during 2028.
Shareholders ratified the issue of the July 2025 placement shares (€30m, ~15.8m shares at A$3.40) at the 10 October 2025 meeting, with the sole resolution carried on a poll with about 96% of proxy votes in favour.
Vulcan signs a fixed lump-sum turnkey contract of about €110m with Turboden and ROM Technik to build the Landau geothermal power plant. It is a condition precedent to financing, and material payments depend on financing being finalised, targeted for H2 2025.
Landau City Council approves Vulcan's purchase of the land for the G-LEP plant, following the November 2024 option agreement. The purchase is subject to Phase One financing completing, which Vulcan expects in H2 2025.
10 Sept 2025regulatory community update▲ GoodMajor
Vulcan receives the permit to build and operate the Central Lithium Plant at Höchst, Frankfurt (up to 24,000t LHM a year). The Li4BAT grant financing deadline moves to 31 December 2025, and offtakes with Umicore, LG and Stellantis are amended, with one last offtake still being negotiated.
Interim management report for the half to June 2025, required for the Frankfurt listing. It restates the Lionheart project and the 29.1Mt LCE total resource; the visible text includes no new figures beyond that.
Half-year report to 30 June 2025. Visible text is mostly the corporate directory, project description and contents; no financial results can be drawn from the readable portion.
Vulcan signs a supply contract with NORAM (NESI) as exclusive electrolysis technology supplier for the Central Lithium Plant in Frankfurt, following NESI's work on the CLEOP pilot plant. Construction contracts are a prerequisite for financing; more contracts are expected in coming weeks.
Australian Shareholders' Association presentation, 29 July 2025. Only the title and disclaimers are readable here, so no new figures can be drawn from it.
Two German government grants totalling up to about €104m (~A$186m) are approved for Li4BAT, supporting the Landau and Frankfurt lithium plants. Payment depends on financing being finalised by 1 September 2025 (extension being sought), construction by January 2026, and a €150m Raw Materials Fund investment by 31 March 2026.
Cover note attaching a Frankfurt Stock Exchange notice that the board resolved to raise up to €30m through new shares. Final size is to be announced separately. This precedes the placement details released the same day.
10 July 2025capital raising announcement● NeutralMajor
Vulcan completes a €30m (~A$53.6m) placement of ~15.8m shares at A$3.40 (7.3% below the 15-day VWAP), with BNP Paribas' Clean Energy Solutions Fund taking €15m. Funds keep critical-path Phase One work going, including extending the EPCm contracts to October 2025. Financing is still targeted for H2 2025.
What it means for a shareholder
15.8m new shares at A$3.40 to raise about A$53.6m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Re-release of the 7 July Mannheim resource announcement, updated at ASX's request under Listing Rule 5.8.1 with revised page references and some JORC table information moved into the main text. The resource figures are unchanged.
After 3D seismic, the Mannheim lithium brine resource rises 76%, from 1,833kt to 3,225kt LCE (820kt Indicated, 2,405kt Inferred). A maiden geothermal resource is also estimated. A scoping study for a future phase is under way; MVV heat offtake talks are ongoing.
Vulcan signs a heat offtake agreement with EnergieSüdwest for at least 35 years, following heat supply starting in April 2025. Volumes step up from 25 GWh to a potential 595 GWh by 2042. D12 supply depends on land purchase, a building permit and an ESW investment decision.
13 June 2025regulatory community update▲ GoodMajor
Building permits are approved for the 30MW geothermal power plant and electrical substation at Landau, part of Phase One. Vulcan already sells power from a smaller 4.8MW plant nearby (about 6,500 homes). This advances Phase One permitting; construction still waits on financing.