Each one in plain English, with the numbers worked through for a shareholder.
28 Sept 2021capital raising announcement▲ Good
Following the SPP and the 27 September EGM, the company has A$1.73m in funds and commitments from 2Invest and existing shareholders, completing the package of just over A$10m. Share issues due that week. Underground make-safe work began at Frankfort ahead of trial mining.
Share purchase plan closed on 23 September 2021. Results are due early the following week. The company also received applications for any shortfall, separate from 2Invest's A$1m underwriting. Admin update.
Chairman confirms the A$6m bond was received (15 bonds, 20% coupon, due 31 January 2023, redeemable early without penalty). Also received: a first A$1m 2Invest tranche and A$1.626m from other investors. A further A$500k from 2Invest awaits EGM approval.
Prospectus for the share purchase plan announced in August: up to 7,142,858 shares at $0.21 to raise up to $1.5m, with one Series B and one Series C option for every two shares. Formalises a known raising; no new terms.
What it means for a shareholder
7.1m new shares at $0.210 to raise about $1.5m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Cover letter explaining that the 27 September 2021 extraordinary general meeting will be held virtually because of COVID-19 restrictions, with no physical venue. No new substance.
Director Robert Thomson resigned from the board on 13 August 2021, after serving since 2016. The chairman says he left on good terms. Board drops to five directors (inference from the prior list).
Company outlines its second-half 2021 program: trial mining at the Frankfort mine, underground drilling and sampling at Beta South, and DFS work now including Rietfontein. DFS completion slips to Q2 2022 from the Q1 2022 given earlier. Funded by the recent raising.
ASX lifted the trading suspension from the start of trading on 2 August 2021, after the company released its capital raising results. Administrative notice with no new substance.
2 Aug 2021capital raising announcement● NeutralMajor
A$10.6m funding package led by 2Invest AG: A$6m secured bond at 20% coupon due 31 January 2023, a A$3.126m placement at $0.21 with options, and a A$1.5m share purchase plan. The bond is secured on Transvaal Gold Mining Estates' proceeds, with an option over its shares.
ASX suspended trading at the company's request, pending an announcement on a funding transaction. This follows a trading halt request dated 26 July 2021.
Site work update on the underground project: gravity survey, Rietfontein tailings sampling, community forums, and engineers appointed for waste management. Definitive feasibility study for Beta, CDM and Frankfort now due Q1 2022. Metallurgical testwork continues.
CFO and Company Secretary Chin Haw Lim retired after four years. Heath Roberts becomes Company Secretary and Phillip Rankin Acting CFO from 1 July 2021.
380,000 performance rights lapsed after an employee resigned. Capital structure now 503,245,666 shares and 33,738,353 unlisted options and rights. Administrative.
Mines & Money presentation repeating known figures: 6Moz resource, 580koz reserve, AISC US$905/oz, 160kozpa target. Carried a slide comparing it with ASX peers, which was retracted the same day (see next entry).
Company retracted Slide 4 (resource comparison with ASX peers) of the same-day Mines & Money presentation, citing ASX Guidance Note 8, and lodged a revised presentation. The text gives no further reason.
April 2021 investor presentation. Visible text is disclaimers only, with a '6 Moz gold resource' headline; no new figures visible. Appears to repeat known information.
Maiden underground pre-feasibility study (Beta, Frankfort, CDM): 419koz mined over 7.67 years, NPV US$91.2m, IRR 82%, AISC US$905/oz at US$1,570/oz gold. Total capex US$79m, with US$36-37m peak in first three years; funding not yet secured.
Maiden underground Ore Reserve of 419koz at 5.49g/t (Beta, Frankfort, CDM), lifting global reserve to 580koz. Delivers the Q1 2021 promise, but the open-pit reserve fell from 205koz to 161koz, which the text attributes to combined open-pit and underground studies.
25 Mar 2021capital raising announcement● NeutralMajor
Theta signed a standby equity facility with Acuity Capital for up to $15m, expiring 31 July 2023. The company decides if, when and at what floor price to draw; 24m shares placed with Acuity as security at nil cash, which could be bought back.
15 Mar 2021capital raising announcement● NeutralMajor
Raising $3.13m via 11.39m shares at $0.275, plus 3.64m shares at $0.275 converting a $1.0m shareholder loan made Dec 2020-Jan 2021. Funds go to permitting, the underground PFS and working capital. A maiden underground reserve is promised shortly.
Half-year report to 31 December 2020. Visible text covers directors, the new Africa executives, the unchanged April 2020 optimisation economics (NPV5 US$85m at US$1,500/oz) and the BAM investment (2,087,682 shares at $0.33). Open-pit still awaits permit and finance; financials not visible.
Listing Rule 5.3.3 schedule of mining tenements held at 31 December 2020, with confirmation of no farm-in or farm-out agreements during the quarter. Administrative.
January 2021 Mines & Money online presentation. Visible text is disclaimers only and it notes TGM joined the MSCI World Micro Cap Index in November 2020. No new figures visible; appears to repeat known information.
Kamara Group appointed debt adviser for the Theta open-pit project financing, the funding still unsecured. Mechanised long hole stoping chosen as the preferred underground method; underground PFS and maiden reserve still on track for Q1 2021; MR83 open-pit amendment still under DMRE review.
20 Jan 2021asset acquisition disposition● NeutralMajor
Theta will take about 5% of Singapore-based Bullion Asset Management (gold tokenisation) for A$700,000 paid in Theta shares. Options allow up to about 15% in total and co-investment in up to 50% of BAM's future gold mine acquisitions to 2025. A step outside its South African gold project focus.
Holders of 53,333,334 escrowed shares agreed to extend escrow from 31 December 2020 to 30 September 2021. In return the company will issue them 5,000,000 unlisted options at $0.50 expiring 30 June 2022, a small dilution.
Board approved an underground pre-feasibility study on the Beta/Frankfort mines (575koz M&I resource), due Q1 2021, aiming for a first underground maiden reserve to add to the 205koz open-pit reserve. Advances the underground acceleration plan; no reserve declared yet.