20 Feb 2019admin correction● Neutral
Corrects the September 2018 resource tables, which wrongly said some resources were based on historical estimates; none are. The total resource is unchanged at 39.15Mt at 4.57g/t for 5.75Moz.
Each one in plain English, with the numbers worked through for a shareholder.
20 Feb 2019admin correction● Neutral
Corrects the September 2018 resource tables, which wrongly said some resources were based on historical estimates; none are. The total resource is unchanged at 39.15Mt at 4.57g/t for 5.75Moz.
18 Feb 2019investor presentation● Neutral
Chairman's presentation at the Proactive Investors Sydney session. Standard company and South Africa overview repeating known information. No new results.
5 Feb 2019investor presentation● Neutral
Chairman's presentation at the Indaba Investment Battlefield in Cape Town. Standard company overview and team slides repeating known project information. No new results.
31 Jan 2019other● Neutral
Registered and principal office moves to Level 32, 101 Miller Street, North Sydney from 1 February 2019. Administrative only.
31 Jan 2019quarterly activities report● Neutral
December quarter report. Of the A$6m placement, A$3.5m has been received so far. Name change and consolidation completed, Behnken appointed. Feasibility study, previously due late Q1, is now expected in early Q2 2019. Otherwise repeats scoping study and drill results.
29 Jan 2019security holder rights change● Neutral
954,546 shares will be released from voluntary escrow on 14 February 2019. About 91.7m shares remain escrowed, expiring September and November 2019. Housekeeping.
21 Jan 2019drilling result▲ Good
First-phase resource drilling at Theta Hill is nearly complete, with over 7,400m drilled in Q4 2018. Results include 11m at 2.1g/t and 1m at 27.5g/t at Theta Hill, plus more shallow gold at Columbia Hill and Scammells. Feasibility study and reserves still planned for early 2019.
21 Jan 2019investor presentation● Neutral
Chairman's London roadshow presentation. It shows about 334m shares, a A$301m undiluted market cap and A$4.9m cash and placement commitments, with Fineway the largest holder at 19.92%. Mostly repeats known project information.
4 Jan 2019security holder rights change● Neutral
1,000,000 unlisted options at $0.15 lapsed on 3 January 2019. Capital structure now 333.9m shares, 31.4m listed options and 35.7m unlisted options and performance rights. Housekeeping only.
19 Dec 2018director officer appointment▲ GoodMajor
Finn Behnken, a South Africa-based mining engineer, former CEO of Tshipi é Ntle Manganese and ex-banker, joins the board. The company says he will help finance and develop South African operations ahead of the planned 2019 development phase.
7 Dec 2018security holder rights change● Neutral
Formal ASX notice of the 10-for-1 consolidation approved at the 30 November AGM. Ordinary shares fall from 3,166,964,556 to 333,918,791 and listed options from 314.3m to 31.4m, with strike rising from $0.03 to $0.30. Confirms the earlier timetable.
30 Nov 2018agm notice▲ Good
All nine AGM resolutions passed, including the 10-for-1 consolidation, name change, new constitution, Ernst & Young as auditor, additional placement capacity, and election of Guy and Tang. Opposing votes were negligible. This resolves the AGM thread.
30 Nov 2018other● Neutral
New company constitution adopted at the AGM on 30 November 2018, replacing the 2011 one. Administrative document; no new commercial information.
30 Nov 2018investor presentation● Neutral
AGM presentation repeating known points: resource 5.75Moz up 57% in a year, scoping study figures, Columbia Hill drill results and a path to a feasibility study with about a 3-year mining reserve. No new results.
30 Nov 2018security holder rights change● Neutral
Confirms shareholders approved the 10-for-1 consolidation at the AGM. Shares fall from about 3.17bn to 316.7m; trading of consolidated shares begins 4 December, with normal settlement from 13 December.
29 Nov 2018drilling result▲ Good
New RC drilling at Theta Hill and Columbia Hill shows shallow high-grade gold, e.g. 3m at 19.4g/t at Theta Hill and 4m at 12.53g/t and 16m at 3.27g/t at Columbia Hill. Over 2,500m drilled since September; results feed the Q1 2019 feasibility resource update.
29 Nov 2018security holder rights change● Neutral
Three lots of unlisted options expiring July 2022 lapsed, 9m in total: 2m at $0.035, 2m at $0.040 and 5m at $0.025, because their vesting conditions were not met (inference). Housekeeping.
12 Nov 2018capital raising announcement▲ GoodMajor
Two private placements totalling $6m to fund the Theta Hill feasibility study: Fineway Creation $1.5m at $0.009 per pre-consolidation share (166.7m shares), and new investor Zenith (Mingliang Zhu) $4.5m in two tranches at $0.09 post-consolidation and a 20-day VWAP. Shares escrowed; this settles the funding question for the feasibility study.
31 Oct 2018quarterly activities report● Neutral
September quarter report restating the 5.75Moz resource, Theta Hill maiden resource and scoping study, with two RC rigs drilling for reserves. Rietfontein dewatering continues. Mostly repeats earlier announcements.
29 Oct 2018other● Neutral
Company proposes renaming to Theta Gold Mines (new code TGM), with a 10:1 consolidation and new constitution at the 30 November AGM. It cites A$4.9m of debt reduction and says funding talks have progressed, with the Board confident of funding the Theta Hill feasibility study. A 'Pipeline Strategy' to replicate Theta Hill across 620 km2 is flagged.
29 Oct 2018investor presentation● Neutral
Chairman's presentation for the IMARC Melbourne conference, repeating known figures: 5.75Moz resource, Theta Hill 600koz, peak capex US$16m, AISC US$569/oz. Feasibility study targeted for end of Q1 2019, with construction aimed to begin in 1H 2019. No new results.
29 Oct 2018security holder rights change● Neutral
Timetable for the 10-for-1 share consolidation, subject to the 30 November AGM vote: shares fall from about 3.17bn to 316.7m, and listed options from 314.3m to 31.4m with the strike rising from $0.03 to $0.30. Trading in new shares starts 4 December.
29 Oct 2018agm notice● NeutralMajor
AGM set for 30 November 2018. Resolutions include a 10-for-1 share consolidation, a change of name to Theta Gold Mines Limited, a new constitution, election of Guy and Tang, and Ernst & Young's appointment as auditor.
22 Oct 2018security holder rights change● Neutral
23,272,728 unlisted options at $0.011 expired on 21 October 2018. Housekeeping; no cash raised.
16 Oct 2018investor presentation● Neutral
Presentation on the Theta Hill scoping study and the 5.75Moz resource, repeating the figures already released: AISC US$569/oz and the resource growth of 2.0Moz over 12 months. No new results.
15 Oct 2018resource reserve update▲ GoodMajor
Theta Hill scoping study: about 67kozpa for 7.6 years (509koz recovered), AISC about US$569/oz, peak capital about US$16m, post-tax NPV7.5 about US$152m. Plant refurbishment is estimated at US$11.1m. About 83% of the mined resource is Inferred, and funding is not secured.
5 Oct 2018debt financing▲ GoodMajor
The Lind (ASOF) convertible security, a 27-month facility from January 2017, is fully repaid ahead of time, in line with a new board policy of debt reduction. This resolves the Lind thread, expected to clear by October. With the Tasman note converted, it further cuts debt.
1 Oct 2018annual report● Neutral
Corporate governance checklist lodged with the annual report; it points to the governance statement on pages 23-27 of the annual report. Administrative, no new substance.
1 Oct 2018annual report● Neutral
FY2018 annual report: Chairman Guy describes a shift from underground production to lower-capital open-cut mining, starting at Theta Hill. Group resources reached 5.75Moz, up 2.0Moz. Rietfontein underground decisions await full dewatering. Mostly repeats known news.
26 Sept 2018resource reserve update▲ GoodMajor
Maiden Theta Hill open-cut resource of 4.48Mt at 4.14g/t for 600koz (85% Inferred) lifts group JORC resources to 5.75Moz (23% Measured and Indicated), up 2.0Moz in 12 months. This is the second upgrade due in September. Reserves are targeted for early 2019 and a feasibility study for Q1 2019.