History
Tasman Metals advanced its Swedish Norra Karr rare earth project, then lost its mining lease in 2016 and cut spending sharply.
2013-2015: Building the case for Norra Karr
Vancouver-based Tasman Metals pursued rare earth elements, a group of specialist metals, in Sweden. Its Norra Karr project took a significant step in May 2013, when the Mining Inspectorate granted a mining lease. It gave full mineral rights for an initial 25 years, renewable in 10-year steps if a mine was operating. Stakeholders had five weeks to appeal.
The record is then quiet until early 2015, when Tasman filed a prefeasibility study, an intermediate assessment of a possible mine that moved beyond its earlier preliminary economic assessment.
A British Columbia Securities Commission review followed. In July 2015, Tasman filed an amended study and retracted its claim of an unconstrained mine life exceeding 60 years. The revised version targeted 20 years. It reported an indicated resource (an estimate of mineral in the ground) of 31.11 million tonnes grading 0.61% total rare earth oxides, using a 0.4% minimum grade. It also reported a probable reserve (a portion assessed as economically mineable) of over 23.5 million tonnes at 0.59%.
2016: A lost lease and a retreat
In January, Tasman announced it would leave the NYSE MKT exchange to reduce costs, also citing the exchange's minimum price rules and its low share price. On 5 February, the shares moved to the US OTCQB market, while remaining on Canada's TSX Venture Exchange. Tasman began cost cuts and a review of strategic options.
On 23 February, it announced that Sweden's Supreme Administrative Court had cancelled the Norra Karr mining lease. The court found that environmental studies into a future mine did not adequately support the grant. The decision could not be appealed.
As of 1 March 2016, Tasman still owned all of Norra Karr under an exploration licence. Its requested two-year extension was subject to appeals. The company could reapply for a mining lease and believed its 2015 study data could meet requirements, but awaited new official guidance before deciding when. It planned to sharply reduce project spending and let its Olserum rare earth licences in southern Sweden lapse progressively over 12 months. Tasman linked its strategic review mainly to low rare earth prices. It was considering corporate and project opportunities, but had named no transaction.
Written from the 8 story beats below (2013 to 1 Mar 2016), which come from the company's own announcements and filings.