History
A small shell emerged from administration in 2006, became a South African coal developer, spent years chasing Boikarabelo mine funding, then collapsed into administration and delisting in 2022.
2006-2008: From administration to coal
Resource Generation, then trading as Comdek, came out of administration in November 2006, when the Deed Administrator retired and an entirely new board took over. In July 2007 it raised $1.249m through a placement of 49.96 million shares at 2.5 cents. It then moved into resources. It agreed to buy 80% of Uranex, which held three uranium licences in Cameroon, and in November 2007 signed to buy Isicebi Carbon Mining, which had the right to earn 70% of three Waterberg coal projects in South Africa.
In 2008 it added two Tasmanian coal ventures, Energy Investments and Tiger Coal, and settled the Isicebi purchase in July after South African Reserve Bank approval, issuing 85.6 million shares. The Waterberg inferred coal resource was lifted from 415 million tonnes to 738.8 million. In August it raised $12 million at 18 cents. The year's loss was $10.99m, including a $7.57m write-down of the Uranex investment. Paul Jury became Managing Director, and the head office moved from Perth to Sydney.
2009-2011: Waterberg becomes Boikarabelo
Shares were consolidated one for ten in January 2009. In mid-2009 the company launched a fully underwritten one-for-one entitlement issue at 40 cents to raise $30.75m. Holders took up only about 40% of the shares offered, so the underwriter had to place the rest. Drilling kept enlarging the project, renamed Boikarabelo. A first reserve of 302.4 million tonnes in August 2009 doubled to 603 million in January 2010 and reached 744.8 million by December 2010. A pre-feasibility study put the capital cost at A$700m.
The company lifted its stake in the Ledjadja Coal venture to 74%, secured a JSE secondary listing in July 2010, and raised $30m at 50 cents in November 2010. It signed long-term coal offtake deals (agreements to sell coal) with Integrated Coal Mining and Bhushan Steel. A 30-year mining right was granted in March 2011, though three landholders appealed. The Tasmanian tenements were sold for $1.5m.
2011-2013: Permits, rail and the turn to Noble
The project's cost and timetable moved repeatedly. Stage 1 capex rose to $750m in September 2011, then fell to US$630m in August 2012 once Eskom agreed to supply power. Environmental approval came in March 2012. The appeal was dismissed and the water licence received in May 2012, and a ten-year rail haulage contract was signed with Transnet in June 2012. Six banks were mandated for about US$400m of debt, but approvals dragged on and the offered terms proved unacceptable.
Noble Group stepped in with a $20m debenture in January 2013, then bought shares at 40 cents and provided a US$123m loan facility. In mid-2013 the company launched a one-for-one offer at 22 cents to raise A$62.6m. Holders took up only about 16.7%, and a shortfall placement raised $52.2m. A 15% placement to Blumont for about $22.6m was never paid, and the company kept a $2.5m deposit. Shares on issue stood at 237,161,400 at the end of 2013.
2014-2017: Funding delays and a fight for control
Construction began in 2013, but the record shows the main debt was still unsettled. A contractor went into liquidation in 2014, pushing first coal back. A US$113m equipment loan from Komatsu Financial was signed. In 2015 a lender club including RMB, HSBC, IDC, PIC and Noble sought a cheaper contract-mining model, delaying funding.
Noble and Altius then pressed for board seats, and Altius's subsidiary Shinto Torii requisitioned a meeting to remove all four directors. The company went to ASIC and the Takeovers Panel, and Altius-backed nominees took control in November 2015, with Robert Lowe as interim CEO. A EUR480m Swiss funding memorandum was abandoned. In August 2016 terms were agreed for R5.52bn, but timetables kept slipping. Noble kept lending small amounts of working capital and gained board seats.
2018-2020: Close, but never closed
In April 2018 the IDC signed a binding R540m senior loan, but a second lender's approval stalled over credit concerns and an internal ESG review. Noble's facility grew to US$44.4m by May 2019. In June 2019 the third lender confirmed approval, confirming a R4.2b mine package. Binding funding agreements with PIC, IDC and Noble followed in December 2019, and a Transnet rail contract was signed in November 2019. Shareholders approved the package with 99.6% in April 2020.
Financial close then slipped from April to June to August 2020, with COVID-19 blamed for part of it. On 26 October 2020 the company sought a trading suspension, with management taking 30% pay cuts. Two days later the IDC cancelled all its approved facilities, citing materially worse market conditions.
2021-2022: Administration and delisting
Noble agreed a little more funding in November 2020 but refused further advances in April 2021, and the CFO and COO resigned. Administrators from McGrathNicol were appointed on 2 July 2021. Creditors backed a holding deed in August. Exclusive talks with one party ended without a proposal in November. In February 2022 creditors approved a varied deed with Alt Finance Pty Ltd, and four directors, including CEO Molotsane, resigned.
A 72-for-1 consolidation was approved in May 2022, cutting shares from 581,380,338 to about 8.07 million. By August the company had exited the deed as a shell with cash of $8,419, and was discussing a backdoor listing (buying a business to gain a listing). It was not completed, and ASX removed the company from its official list on 27 October 2022 after two years of suspension.
Written from the 142 story beats below (2006 to 27 Oct 2022), which come from the company's own announcements and filings.