History
Randgold built the Kibali mine in the DRC into a major gold producer, rebuilt its cash pile, then merged into Barrick Gold on 1 January 2019.
2013-2014: Kibali comes to life
In mid-2013 Randgold was preparing to pour the first gold at Kibali in the Democratic Republic of Congo, owned 45% each by Randgold and AngloGold Ashanti, with the state miner SOKIMO holding 10%. The initial investment was put at US$1.7 billion. Gold was poured on 24 September 2013, ahead of the original year-end target. Bristow, the chief executive, said Randgold's business was planned to stay profitable even as the gold price fell. At Tongon in Côte d'Ivoire, operations were improving after setbacks the year before.
The DRC formally opened Kibali on 2 May 2014. By then the investment was quoted at more than US$2.5 billion. In its first production quarter to December the mine made 88,200 oz. Shareholders approved a final 2013 dividend of US$0.50 per share and a scrip scheme, which lets them take new shares instead of cash.
2015-2017: Cash, dividends and a new pit
For 2014, group production rose 26% to 1,147,414 oz and the cost per ounce fell to $698. Profit fell 17% to $271.2m on a lower gold price. Kibali produced 526,627 oz in its first full year. The year ended with no borrowings, and the revolving credit facility, a standing bank line, was doubled to $400m. Randgold said it wanted dividends that rose or stayed flat, and aimed to build net cash to about $500m. At the May 2015 AGM, about 30.77% of shares available took the scrip option, creating 250,635 new shares. Issued shares stood at 92,941,521 at 30 April 2015.
The record then goes quiet for 2016. Results for that year showed record production of 1,252,957 oz, profit up 38% to $294.2m and cash of $516.3m with no debt, passing the $500m target. The dividend was proposed at $1.00 per share. The board approved the Gounkoto super pit in Mali in place of the earlier underground-only plan, and Morila was heading for closure in 2019. Kibali's reserves fell to 9.2 million oz after depletion and a remodel of the underground geology.
2018: Pressure in the DRC and a bid
In February 2018 Randgold reported record 2017 production of 1.315 million oz, profit up 14% to $335m, cash up 39% to $720m and a proposed $2.00 dividend. Kibali's underground mine was commissioned, ending an eight-year build. But a new DRC mining code threatened the 10-year stability clause in the 2002 code. Randgold said it would seek to enforce its rights, including through international arbitration, if talks failed. An industry team went to Kinshasa in March, and Kibali left the Congolese Chamber of Commerce.
First-quarter profit fell to $66.5m, with Tongon hit by work stoppages, though guidance was kept. Bristow said Randgold was hunting for its next big project.
2018-2019: Merger with Barrick
In October 2018 Randgold sent shareholders the circular for an all-share merger with Barrick Gold. Directors unanimously recommended it, as did proxy advisers ISS and Glass Lewis. Kibali also agreed with the DRC Finance Ministry to recover $218 million of VAT, $40 million upfront and the rest by offset. The Jersey court sanctioned the scheme on 17 December. It took effect on 1 January 2019. Randgold's London and Nasdaq listings were cancelled on 2 January 2019, and its holders received new Barrick shares. A $2.69 interim dividend was expected on 11 January, though payment is not confirmed in the record.
Written from the 16 story beats below (2013 to 2 Jan 2019), which come from the company's own announcements and filings.