Quest Rare Minerals spent 2012 to 2014 turning its Strange Lake rare earth deposit into a costed mining and processing plan, still unfunded and without a binding sale agreement.
2012-2013: Sizing the deposit and seeking partners
Quest Rare Minerals set out to develop the Strange Lake B-Zone in Québec, a deposit of rare earth metals. In October 2012 it reported a revised estimate by Micon International: 278.1 million tonnes Indicated at 0.93% total rare earth oxides plus yttrium, and 214.4 million tonnes Inferred at 0.85%. Quest said this was more than double its April 2011 estimate to a depth of 150 m. It also hired Gunter Thase as Manager, Metals & Marketing, to find off-take (buyers) and strategic partners.
That search produced a first result in July 2013: a non-binding letter of intent with TAM Ceramics Group of NY, LLC to buy up to 24,000 tonnes a year of zirconia, all of Quest's expected zirconia output. A definitive agreement, including price, was still to be negotiated by December 31, 2014.
The same month Quest closed a private placement raising $2,741,948 gross, its first new equity since October 2010. It sold flow-through shares (money for Québec exploration) and units with half-warrants (money for working capital). Shares outstanding rose to 67,237,044.
2013-2014: Studies, a plant site and a redesign
In October 2013 Quest released a pre-feasibility study, which it called positive. Initial capital was $2.565 billion, with a post-tax return of 21.2%, a post-tax net present value of $1.8 billion, a 30-year mine life and a 3.5-year payback. The filings did not say how the build would be financed, and the project was not yet funded or committed.
In November 2013 Quest chose Bécancour Industrial Park for its $1.3 billion processing plant, with construction planned for 2016 and first product in 2018. It said it would voluntarily submit the project to Québec's environmental review and set up a community monitoring committee.
On April 9, 2014, Quest released a revised preliminary economic assessment it called substantially improved. The excerpt did not show the new figures, but its contents listed a flotation step and a separation plant, suggesting a changed process design. The resource estimate behind it was still the August 2012 one. At that date, the TAM agreement remained non-binding and the large capital cost remained unaddressed.