27 Feb 2025resource reserve update● NeutralMajor
Kore restated its 2017 Kola Mineral Resource: over 500 Mt (508 Mt) Measured and Indicated sylvinite at 35.4% KCl, plus 340 Mt Inferred. The text says no figures changed; it adds ASX-required detail and underpins the Optimised DFS released the same day.
Updated Dougou Extension (DX) study: Ore Reserve 9.31 Mt at 35.7% KCl, Mineral Resource 129 Mt, 12-year life at 400,000 tpa. NPV10 US$275M (down from US$412M in the 2020 study), IRR 27%, funding about US$316M (previously about US$286M) and unsecured.
Kore's review of the Kola optimisation study puts build cost at US$1.83B (EPC basis), down US$520M from the 2019 DFS's US$2.35B, with a 40-month build. NPV10 rises to US$1.623B, IRR 20%. EPC proposal now due August 2022, later than earlier guidance.
Seven DX drill holes finished within budget, with assays received after lab quality delays. Sylvinite in the Hanging Wall Seam is more complex than modelled in the earlier study; carnallite areas will be excluded, and more drilling or seismic work may be needed. A new geological model is due by end-2021.
DX feasibility study phase one remains on track for May 2021 and within budget. Holes DX 10 and DX 11 are drilled to the anhydrite layer, and core drilling has begun on DX 11. Dissolution tests suggest brine of 170-200 g/l KCl may be possible, versus 165 g/l in the PFS.
Updated DX pre-feasibility study extends mine life from 18.4 to 30 years at 400,000 tonnes a year by adding Indicated and some Inferred resources. NPV10 is US$412m and IRR 23.4%. Ore Reserves are unchanged at 17.7 Mt. About US$286m funding is still unsecured.
Drilling of the up-to-5-hole DX definitive feasibility study programme has started, using Kore's own rigs. Two rotary holes go first to the anhydrite layer, with core drilling to follow. Target seams are about 400 metres deep; phase one is still due May 2021.
The Dougou Extension PFS shows a 400,000 tpa potash operation over 18 years. Initial capex is about US$286M, post-tax NPV10 about US$319M and IRR 22.9%. Maiden sylvinite Ore Reserves are 17.7 Mt at 41.7% KCl. The company cautions that funding is not secured. DFS planning is next.
Two of three Dougou Extension infill holes hit sylvinite: DX_07 had 4.2 m at 56.4% KCl and DX_09B 4.9 m at 32% KCl. DX_08 was stopped short after equipment failure. Results feed into the PFS due in May.
The French consortium sent a new Kola proposal identifying US$415M of capital cost savings. Seven other engineering groups will price the Kola bill of quantities, results expected Q4 2019. Dougou Extension pre-feasibility work started: advisers appointed, drill rigs mobilising, seismic gear arriving in August.
Scoping study for solution mining 400 ktpa of potash at Dougou Extension: capex about US$327M, 17-year life, NPV10 about US$221M, IRR 19.3%. It is preliminary and funding is uncertain. It offers a possible faster route than Kola, which remains separate.
Kore reported exploration targets (not resources) next to existing deposits: Kola South 95-175 Mt at 34-42% KCl and DX North 320-600 Mt at 30-38% KCl. These could lift total sylvinite to 1.5-1.9 billion tonnes. Quantity and grade are conceptual.
First sylvinite resource at Dougou Extension: 232 Mt at 38.1% KCl (111 Mt Indicated, 121 Mt Inferred), including 67 Mt at 60.1% KCl. This lifts Kore's sylvinite resources 27% to 1.08 billion tonnes, completing the planned update after 2017 drilling.
Lab assays at Kola confirm holes EK_53 and EK_54 at 61.9% and 60.0% KCl over 2.22 m and 3.26 m, up from earlier gamma-ray estimates of 52.0% and 54.1%. Both sit southeast of the 508 Mt resource. The Dougou Extension drilling is ended, as two holes could not be completed, to focus on the Kola feasibility study.