19 Jan 2023quarterly activities report● Neutral
Quarter to 31 December 2022: Kola EPC terms still being negotiated with SEPCO, and the Consortium financing proposal still awaits them. Minister of Mines assured support on 17 December. Cash US$5.0M, down from US$6.2M.
December 2022 CDI notice: ASX CDIs fell by 9,789,439 to 667,957,820 through transfers to AIM/JSE. Options and performance rights unchanged. Administrative only.
COO Gavin Chamberlain, in the role since September 2017, leaves at end of January 2023 to take a role closer to home. Project Director Ryan Leland now reports directly to the CEO. Construction-phase recruitment is planned for the first half of 2023.
Non-executive director Sameer Oundhakar, the Oman Investment Authority nominee since April 2021, resigned immediately after leaving his OIA job. OIA has put forward a replacement, which the board is considering subject to due diligence.
Kore met the Minister of Mines on 17 December; he thanked it for its response and assured it of the government's ongoing support for Kola. Kore's internal review found no material administrative deficiencies; two independent reviews are due January 2023. Eases the October tension.
November 2022 CDI notice: ASX CDIs fell by 5,523,291 to 677,747,259 through transfers to AIM/JSE. Options and performance rights unchanged. Administrative only.
Kore replied in writing to the Minister of Mines' letter within his 30-day window and is seeking his continued support to complete Kola financing. It now awaits further feedback. No government action is reported.
October 2022 CDI notice: ASX CDIs fell by 492,047 to 683,270,550 through transfers to AIM/JSE. Options and performance rights unchanged. Administrative only.
Quarter to 30 September 2022: EPC proposal received but terms still under discussion, financing proposal awaits them, and the Minister's letter is noted. DX PFS update is under way. Cash US$6.2M, down from US$7.6M; US$999,000 spent on studies.
Congo's Minister of Mines wrote expressing discontent with subsidiary administration and slow Kola financing progress, after two senior employees were arrested and released without charge. The government reserves its rights under the Mining Code if no reply within 30 days. Kore says it is compliant.
SEPCO delivered the Kola EPC proposal, after delays from COVID lockdowns in China, reflecting the US$1.83B cost and HoA terms. Kore wants several contract terms discussed before accepting, and SEPCO may need further board approvals. Consortium's financing proposal still awaits agreed EPC terms.
September 2022 CDI notice: ASX CDIs fell by 5,524,647 to 683,762,597 through transfers to AIM/JSE. Options and performance rights unchanged. Administrative only.
Half-year report to 30 June 2022. The text provided is only the cover, contents, corporate directory and glossary, so no financial results can be drawn from it.
August 2022 CDI notice: ASX CDIs fell by 6,343,301 to 689,287,244 through transfers to AIM/JSE. Options and performance rights unchanged. Administrative only.
July 2022 CDI notice: ASX CDIs fell by 7,606,461 to 695,630,545 through transfers to AIM/JSE. Options and performance rights unchanged. Administrative only.
Quarter to 30 June 2022 restates the Kola study results, the HoA with SEPCO and the August EPC proposal expectation. Financing proposal is expected 'later this year'. Cash fell to US$7.6M from US$9.4M.
June 2022 CDI notice: ASX CDIs fell by 18,526,532 to 703,237,006 through transfers to AIM/JSE. The 44,132,674 SQM shares issued after AGM approval are noted. Options and performance rights unchanged. Administrative only.
Kore signed a Heads of Agreement with SEPCO to build Kola for US$1.83B over 40 months, on FIDIC Silver Book terms. Underground works (about US$164M) may be adjusted, as may costs if exchange rates move. Binding EPC proposal due August 2022; financing proposal follows.
Kore's review of the Kola optimisation study puts build cost at US$1.83B (EPC basis), down US$520M from the 2019 DFS's US$2.35B, with a 40-month build. NPV10 rises to US$1.623B, IRR 20%. EPC proposal now due August 2022, later than earlier guidance.
14 June 2022security holder rights change● Neutral
44,132,674 new shares issued to SQM in lieu of fees under its Technical Services Agreement, lifting total shares to 3,420,177,120. SQM's holding rises from 14.64% to 15.74%. This appears to settle part of the deferred SQM shares.
Remote listen-in access via dial-in is provided for the AGM on 9 June 2022 in London. Shareholders may attend in person, but no directors will be at the venue.
May 2022 CDI notice: ASX CDIs fell by 17,146,092 to 721,763,538 through transfers to AIM/JSE. 550,000 performance rights converted to shares; 1,760,000 rights remain. Administrative only.
550,000 new shares issued to employees and ex-employees on vesting of performance rights, including 283,333 to COO Gavin Chamberlain. Total shares become 3,376,044,446. Minor, non-cash issue.
April 2022 CDI notice: ASX CDIs fell by 20,198,835 to 738,909,630 through transfers to AIM/JSE. Options and performance rights unchanged. Administrative only.
Quarter to 31 March 2022: study received 1 April and under Kore's review; Consortium expects to deliver the EPC proposal within two months, then financing proposal. Management now speaks of financing proposal 'later this year'. Cash US$9.4M, down from US$11.1M.
March 2022 CDI notice: ASX CDIs rose by 52,689,068 to 759,108,465 through transfers from AIM/JSE. Options and performance rights unchanged. Administrative only.
Kore received the completed Kola Optimisation Study from SEPCO, finishing the Consortium's optimisation work. Kore's review will take several weeks; the EPC proposal is expected within two months, with the financing proposal to follow. No new capex figure is given. Slightly later than the Q1 EPC guidance.
Annual report for the year to 31 December 2021. The text provided is only the cover, contents, corporate directory and glossary, so no financial results can be drawn from it.
Appendix 4G corporate governance key lodged with the annual report, with the governance statement at pages 36-71 of the report. Administrative compliance form with no new information.
February 2022 CDI notice: ASX CDIs fell by 10,574,511 to 706,419,397 through transfers to AIM/JSE. Options and performance rights unchanged. Administrative only.