Each one in plain English, with the numbers worked through for a shareholder.
29 July 2022director officer appointment▲ Good
Stephen Gardiner, a former Oil Search CFO with over forty years of corporate finance experience, joins the board from 25 August 2022. He takes over the Audit and Risk Committee chair left by Julian Babarczy, as ioneer works on finalising debt agreements.
June quarter cash flow report: cash fell from A$144.2M to A$136.7M. Operations used A$4.4M and capitalised project spending was A$8.1M; exchange movements added A$4.9M. No debt; about 10.9 quarters of funding at the current rate.
June quarter report: the revised Plan of Operations was resubmitted to BLM in early July, with the Notice of Intent expected shortly. Nasdaq trading began; DOE due diligence continues. The remaining lithium offtake talks are now expected to conclude in 3Q 2022, slipping from 2Q.
Executive Chairman James Calaway's employment agreement was renewed for another 12 months from 1 July 2022, as flagged in 2021. He receives US$300,000 executive pay on top of US$150,000 director fees, with a focus on offtake, financing and US investor relations.
ioneer signed a binding 5-year offtake with Ford for 7,000 tpa of lithium carbonate, about 34% of output in the first five years, starting in 2025. It is conditional on final investment decision (expected by June 2023) and Ford approving product specification by September 2022.
Non-executive director Julian Babarczy retired with immediate effect, citing workload from his other business interests. He chaired the Audit and Risk Committee and sat on the Nomination and Remuneration Committee. The board is down one director.
ioneer's ADRs began trading on Nasdaq on 30 June 2022 as IONR, completing the secondary listing flagged since 2021. No capital raise was involved. Cash was A$144.2M at 31 March. The release now says production is expected in 2025, versus 2024 earlier.
The US SEC declared ioneer's Form 20-F effective on 28 June 2022, a step toward the planned Nasdaq secondary listing. It would use a Level II ADR program with BNY Mellon as depositary, with no new share issue. ASX shares continue trading.
RIU Sydney Resources Round-up presentation of 3 May 2022, with the same disclaimers and lithium market background as earlier decks. No new information visible.
March quarter report: a revised Plan of Operations is to be submitted to BLM soon, with the Notice of Intent expected shortly after, and the timetable has been updated. Further lithium offtake announcements are anticipated in the June quarter. DOE due diligence and the NASDAQ listing continue.
March quarter cash flow report: cash fell from A$149.0M to A$144.2M. Operations used A$2.5M and capitalised project spending A$7.6M, offset by A$7.8M from option exercises. No debt; about 14 quarters of funding at the current rate.
Ord Minnett East Coast Mining Conference presentation covering lithium markets, corporate overview and Rhyolite Ridge. Visible text is mostly disclaimers and market background; no new information seen.
ioneer's US subsidiary signed a non-binding MOU with Nevada lithium-sulphur battery maker NexTech Batteries on possible lithium carbonate or hydroxide supply. Long-term supply would only be discussed once production begins. No volumes or prices are stated.
Half-year accounts to 31 December 2021: net loss A$6.5M (A$5.8M a year earlier). Cash rose to A$149.0M from A$83.1M and net assets to A$283.4M, mainly from the Sibanye placement. Resource unchanged at 146.5Mt; no significant changes reported.
EcoPro Innovation exercised the extra 5,000 tpa option, lifting its lithium carbonate offtake from 2,000 to 7,000 tpa, about 34% of output in the first three years. The June 2021 binding deal stays conditional on ioneer's final investment decision.
ioneer awarded ABB Inc. an engineering and equipment contract covering power generation, electrical distribution and plant automation at Rhyolite Ridge. It is on a limited notice to proceed basis, with equipment supply conditional on a final investment decision. Adds to the earlier LNTP awards.
ioneer says the US Fish and Wildlife Service proposed 910 acres of critical habitat for Tiehm's buckwheat (plant occupies 10 acres), alongside the proposed endangered listing. ioneer says this has no material impact on planned mining; final listing decision expected by September 2022.
February 2022 investor presentation. Snapshot: about 2.05B shares, A$0.685 share price, A$1.405B market value, A$149.0M cash at 31 December 2021. Reaffirms the 2020 reserve and production figures. No new information visible.
Correction to the December quarter cash flow report: the form was updated to the newest version and the year-to-date header changed from 12 months to 6 months. Underlying numbers unchanged.
December quarter report recaps the completed Sibanye US$70M investment and the DOE loan due diligence invitation. A US secondary listing (NASDAQ) is now expected in the first half of 2022. Federal Plan of Operation approval remains awaited; offtake talks and engineering continue.
December quarter cash flow report: cash rose from A$69.9M to A$149.0M after A$95.6M equity proceeds (the Sibanye placement). Operations used A$4.3M and project spending A$9.0M. No debt; about 11 quarters of funding at the current rate.
The US Department of Energy loan office invited ioneer into due diligence on its loan application, which it judged substantially complete, to support the Sibanye investment. No loan amount is stated, and the invitation is not an assurance of a loan.
Macquarie WA Forum presentation (dated 30 September in the text, lodged 30 November) with a snapshot of about 2.05B shares, A$0.64 share price and A$1.323B market value. Cash shown is A$69.9M excluding the Sibanye US$70M. Repeats known milestones.
Managing Director's AGM presentation recaps the year: EcoPro offtake, state air and water permits, Sibanye partnership for 50% of the project, engineering design about 50% complete, and debt funding progressing. No new information visible.
Chairman Calaway's AGM address reviews the year and calls lithium a firm sellers' market. He expects final lithium offtake contracts by end of Q1 2022 and says debt work is well advanced. Largely recaps known developments.
28 Oct 2021capital raising announcement▲ GoodMajor
Sibanye-Stillwater's US$70M placement completed, with 145,862,742 shares issued at A$0.6553 after shareholders approved it at the 21 October EGM. Funds go to advancing the project to construction start, long-lead items and working capital. Completes the placement part of the September deal.
What it means for a shareholder
146m new shares at A$0.6553 to raise about A$70.0m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Presentation for the 21 October EGM on the Sibanye-Stillwater US$70M placement. Text shown is mostly disclaimers and instructions on asking questions; no new information visible.
September quarter report recaps the Sibanye-Stillwater deal, with the placement priced at A$0.6553 per share. Notes the Water Pollution Control Permit and FLSmidth, Veolia and DuPont contracts. Federal Notice of Intent is still awaited, with debt funders being engaged. Routine recap.
September quarter cash flow report: cash fell from A$83.1M to A$69.9M, with A$4.0M used in operations and A$11.6M on capitalised project spending. The A$69.9M excludes the US$70M Sibanye placement received after quarter end. No debt; about 4.5 quarters of funding at this rate.
Sibanye-Stillwater received South African Reserve Bank approval for both the US$490M joint venture investment and US$70M placement, satisfying one condition. Remaining JV conditions, including permits and binding debt commitments, are expected in 2H 2022. Placement still needs the 21 October shareholder vote.