The events that changed the company's story, in plain English, each written against everything known about the company at the time. The dot shows whether it was good, bad or neutral for shareholders.

2026

  1. 8 July

    Non-binding MOUs signed with KIND and Hyundai Engineering, as foreshadowed in June. KIND is considering an equity investment and Hyundai Engineering procurement work. Neither is legally bound, so the partnering and funding gap remains open.

    material agreement

  2. 26 June

    The US Army gave ioneer a conditional award for a long-term land lease at Tooele Army Depot to build a boron processing facility; ioneer is one of four companies selected. Formal lease terms are still being negotiated, so it is not yet a binding lease.

    contract award

  3. 23 June

    Ioneer signed non-binding letters of intent with Korea's KIND and Hyundai Engineering to advance Rhyolite Ridge toward a final investment decision targeted for the second half of 2026. Memorandums of Understanding were expected in July 2026; the LOIs create no legally enforceable obligations.

    material agreement

  4. 31 Mar

    The US District Court for Nevada upheld the federal approval of Rhyolite Ridge, rejecting all challenges in the Center for Biological Diversity lawsuit filed October 2024. This resolves the main permitting legal risk at first instance; ioneer says it looks to complete partnering and start construction.

    regulatory community update

  5. 30 Jan

    Firm commitments for a placement of about 400 million shares at A$0.18 to raise about US$50M (A$72M), a 14.3% discount to the 28 January close. It funds long lead items, early works and the strategic partnering process through FID. This is well above the A$0.10 June 2025 raise.

    capital raising announcement

2025

  1. 29 Oct

    Cutting leach time further from two days to 1.5 days lifts throughput from 3.0 to 3.4Mtpa. Unlevered NPV rises 19% to US$2,237M, IRR 18.0%, AISC US$4,628/t LCE. Capex rises only US$15M; about 9,500tpa of lithium is uncommitted.

    resource reserve update

  2. 22 Sept

    CFO and Company Secretary Ian Bucknell, with Ioneer seven years, will leave effective mid-December. The CFO role will move to the US as the company heads towards partnering, FID and construction; the Company Secretary role stays in Australia.

    director officer appointment

  3. 3 Sept

    Shortening the vat leach time from three days to two lifts processing from 2.4 to 3.0Mtpa. Unlevered NPV rises 38% to US$1,888M, IRR 16.8%, AISC US$5,626/t LCE, with no capex change. This builds on the June testwork on shorter leach cycles.

    resource reserve update

  4. 26 June

    Ioneer formally launched its strategic partnering process, with Goldman Sachs advising, to find an equity partner for Rhyolite Ridge. It is expected to take at least 4 months. This continues the search that began after Sibanye's exit.

    other

  5. 13 June

    Ioneer raised about US$16M (A$25M) in a placement of roughly 253M shares at A$0.10, a 13.0% discount to the 10 June close. A share purchase plan targeting up to A$5.0M follows. Funds are meant to carry the project through the partnering process to a final investment decision.

    capital raising announcement

  6. 2 June

    Ore Reserve rose more than fourfold from 60Mt (2020) to 247Mt, a 95-year mine life, containing 1.92Mt lithium carbonate equivalent. Updated economics: after-tax NPV8 US$1.367B (2020: US$1.265B), IRR 14.5% (2020: 20.8%), capex US$1,667.9M (2020: US$785M).

    resource reserve update

  7. 5 Mar

    South Basin Mineral Resource rose 45% to 510Mt, containing 3.97Mt lithium carbonate equivalent and 14.66Mt boric acid equivalent, with 81% Measured and Indicated. It includes the 12 Shelf Zone holes, up from 351Mt in April 2024. The Ore Reserve is now due April 2025.

    resource reserve update

  8. 26 Feb

    Sibanye-Stillwater's board decided not to proceed with the Rhyolite Ridge joint venture, and the agreement was terminated. This ends the planned US$490M for 50%. ioneer keeps 100% and says the DOE loan is unaffected, and it will seek a new equity partner.

    material agreement termination

  9. 20 Jan

    Closed a US$996M US Department of Energy loan (US$968M principal plus US$28M capitalised interest), US$268M more principal than the January 2023 conditional commitment. It has a 20-year tenor. First funding needs the Sibanye JV closing, additional funding and a model bring-down.

    debt financing

2024

  1. 25 Oct

    The BLM issued the Record of Decision, the final federal permit for Rhyolite Ridge, resolving the permitting thread. Construction is planned for 2025 and first production in 2028. FID has slipped to 1Q 2025, with updated reserves and costs due by December 2024.

    regulatory community update

  2. 20 Sept

    The Bureau of Land Management published the Final EIS, and US Fish and Wildlife concluded the project will not jeopardise Tiehm's buckwheat, ending ESA consultation. A Record of Decision can follow after a waiting period to 21 October. First production is now targeted for 2028, versus 2027 earlier.

    regulatory community update

  3. 18 July

    The final 12 Shelf Zone holes, left out of the April resource, all average over 2000ppm lithium in the main B5 unit, more than 20% above the Stream 1 average. It lies under less than 30m of gravel, outside critical habitat. Reserve update due in weeks.

    drilling result

  4. 30 Apr

    South Basin resource restated at 351Mt with 3.25Mt LCE (3.4Mt LCE in 2023), now split in three streams. Measured resource rose 71% to 75Mt, and a high-grade shallow Shelf Zone sits outside critical habitat. Further update due within three months.

    resource reserve update

  5. 30 Apr

    Raising US$25.1M (A$38.4M) via placement at A$0.18 a share, about 213.6M new shares, led by Goldman Sachs. Price equals the 26 April close. Funds engineering and permitting through FID, now expected December 2024. Follows cash falling to US$28M at December.

    capital raising announcement

  6. 15 Apr

    Draft EIS to open for 45-day public comment from 19 April. The timeline moves later: Record of Decision now expected October 2024 (previously 1H 2024), with production in 2027 (previously 2026). Revised plan avoids direct impact on Tiehm's buckwheat.

    regulatory community update

  7. 3 Apr

    53 new holes south of the current resource hit mineralised strata in 49, extending the deposit about 1km south and southeast. BLM review of the draft EIS is complete. Updated resource and reserve due within two months; engineering about 70% complete; FID expected later in 2024.

    drilling result

2023

  1. 1 Nov

    ioneer announced an R&D agreement with EcoPro Innovation to develop its ~1Mt LCE lithium clay resource, with EcoPro to fund a refining plant if the process works. Profits would be shared equally. Initially described as binding; corrected two days later (see next).

    material agreement

  2. 21 Sept

    Leach tests on low-boron 'Type 3' mineralisation recovered 89-94% of lithium, with free-draining behaviour, making it a candidate for heap or vat leaching like Type 1. Type 3 is excluded from the 2020 DFS economics; this supports growth within the 360Mt resource's footprint, though no new economics are given.

    drilling result

  3. 10 May

    ioneer signed a lithium carbonate offtake with Nevada's Dragonfly Energy: 3 years, variable surplus volume after existing commitments, market-based price. Conditional on ioneer's Final Investment Decision. Adds to the Ford, PPES and EcoPro contracts; replaces the earlier non-binding Dragonfly MOU.

    material agreement

  4. 26 Apr

    South Basin Mineral Resource rises to 360Mt containing 3.4Mt lithium carbonate equivalent, up 168% from the 2020 estimate of 1.2Mt, because low-boron lithium is now included. Boric acid equivalent rises 18% to 14.1Mt. Resource sits within the permitting boundary.

    resource reserve update

  5. 16 Jan

    The US Department of Energy offered a conditional commitment for a loan of up to US$700M, about 10 years, at fixed US Treasury-based rates. Financial close needs a positive Record of Decision and FID; amount may change. Follows the Sibanye US$490M equity.

    debt financing

2022

  1. 20 Dec

    The BLM will publish a Notice of Intent, starting the NEPA review of Rhyolite Ridge's Plan of Operations. Record of Decision is now expected 1Q 2024, with first production pushed to 2026 (previously 2025). Extra southern drilling and updated costs come before FID.

    regulatory community update

  2. 15 Dec

    ioneer welcomes the US Fish and Wildlife Service's decision to list Tiehm's buckwheat as endangered and designate critical habitat. This resolves the overdue listing decision; the company says it matches expectations and its July 2022 plan avoids all direct impacts to the plant.

    regulatory community update

  3. 8 Dec

    ioneer signed a non-binding MOU with Shell Canada to buy up to 500,000 tonnes of sulphur a year for Rhyolite Ridge, building on the December 2019 letter of intent. It includes binding exclusive negotiation toward a definitive agreement; not yet a binding supply contract.

    material agreement

  4. 16 Sept

    ioneer completed a definitive Technology System Supply Agreement with Caterpillar for autonomous haul trucks at Rhyolite Ridge, converting the February 2021 MOU. Equipment for the first five years is valued at about US$100M and may be financed by Caterpillar, subject to documentation.

    material agreement

  5. 1 Aug

    ioneer signed a binding 5-year offtake for 4,000 tpa of lithium carbonate with Prime Planet Energy & Solutions (Toyota-Panasonic joint venture), about 19% of output. With Ford and EcoPro, it completes the pre-production lithium commitments ioneer intends to make; conditional on final investment decision.

    material agreement

  6. 22 July

    ioneer signed a binding 5-year offtake with Ford for 7,000 tpa of lithium carbonate, about 34% of output in the first five years, starting in 2025. It is conditional on final investment decision (expected by June 2023) and Ford approving product specification by September 2022.

    material agreement

  7. 1 July

    ioneer's ADRs began trading on Nasdaq on 30 June 2022 as IONR, completing the secondary listing flagged since 2021. No capital raise was involved. Cash was A$144.2M at 31 March. The release now says production is expected in 2025, versus 2024 earlier.

    other

  8. 16 Feb

    EcoPro Innovation exercised the extra 5,000 tpa option, lifting its lithium carbonate offtake from 2,000 to 7,000 tpa, about 34% of output in the first three years. The June 2021 binding deal stays conditional on ioneer's final investment decision.

    material agreement

  9. 10 Feb

    ioneer awarded ABB Inc. an engineering and equipment contract covering power generation, electrical distribution and plant automation at Rhyolite Ridge. It is on a limited notice to proceed basis, with equipment supply conditional on a final investment decision. Adds to the earlier LNTP awards.

    contract award

2021

  1. 20 Dec

    The US Department of Energy loan office invited ioneer into due diligence on its loan application, which it judged substantially complete, to support the Sibanye investment. No loan amount is stated, and the invitation is not an assurance of a loan.

    debt financing

  2. 28 Oct

    Sibanye-Stillwater's US$70M placement completed, with 145,862,742 shares issued at A$0.6553 after shareholders approved it at the 21 October EGM. Funds go to advancing the project to construction start, long-lead items and working capital. Completes the placement part of the September deal.

    capital raising announcement

  3. 4 Oct

    US Fish and Wildlife Service proposed listing Tiehm's buckwheat as endangered, following its June finding. Final decision is expected by September 2022. ioneer says it anticipated this and that co-existence with the project is achievable. Raises permitting risk for Rhyolite Ridge.

    regulatory community update

  4. 16 Sept

    Sibanye-Stillwater will contribute US$490M for 50% of a Rhyolite Ridge joint venture; ioneer keeps 50% and operatorship. It also gets a US$70M share placement, subject to a 21 October EGM vote. JV conditions are expected to be met in 2H 2022. Delivers the long-awaited strategic partner.

    farm in farm out agreement

  5. 7 Sept

    DuPont Clean Technologies was awarded the licence, engineering and equipment contract for Rhyolite Ridge's 3,500 tonne-per-day sulphuric acid plant, working with SNC-Lavalin. Conditional on FID. The plant would generate an initial 35MW of power for the site. Production is now expected in 2H 2024.

    contract award

  6. 24 Aug

    Veolia Water Technologies awarded the largest single supply package at Rhyolite Ridge, covering evaporation, crystallisation and dewatering equipment. Detailed design has started; equipment supply is conditional on FID. Veolia has worked with ioneer since 2018.

    contract award

  7. 26 July

    Update: a strategic partner funding agreement is expected in Q3 2021, and the secondary US listing evaluation is complete, with listing likely H2 2021. The federal Notice of Intent is still delayed; FID is about 12 months after it is published.

    investor presentation

  8. 19 July

    Nevada issued the Water Pollution Control Permit; with the June air permit these are the two key state permits needed before construction. Resolves the pending state water permit. Project uses a 3.8 sq km footprint, with no evaporation ponds or tailings dams.

    regulatory community update

  9. 13 July

    FLSmidth awarded a major engineering and equipment contract for crushing, material handling and dryers, on limited notice to proceed; equipment supply depends on FID. FLSmidth introduced ioneer to Denmark's export credit agency about possible financing.

    contract award

  10. 30 June

    ioneer signed its first lithium offtake: a binding three-year deal with Korea's EcoPro Innovation for up to 7,000tpa lithium carbonate (firm 2,000tpa, 5,000tpa optional by Q1 2022), up to 34% of early output. Conditional on FID. Meets the June-quarter expectation.

    material agreement

  11. 24 June

    Nevada issued a Class II Air Quality Permit for Rhyolite Ridge, a requirement before construction can start. It is the first such permit in Nevada for a project with sulphuric acid production. Resolves one of the pending state permits.

    regulatory community update

  12. 4 June

    US Fish and Wildlife Service found an Endangered Species Act listing investigation for Tiehm's buckwheat is 'warranted', citing drought and herbivory. A decision on proposing a listing is due September 2021. ioneer says it expected this and is developing a conservation agreement.

    regulatory community update

  13. 28 Apr

    ioneer starts formally evaluating a secondary US stock exchange listing, likely in the second half of 2021. No guarantee it proceeds. Says strategic and financial partner talks are at an advanced stage and construction is expected to begin late 2021.

    other

  14. 5 Mar

    Placement completed and upsized from A$60M to A$80M at A$0.38, issuing 210,526,316 shares, with BNP Paribas Energy Transition Fund as cornerstone. Settlement 9 March. Funds Rhyolite Ridge engineering ahead of expected Q4 2021 permits; adds about 12% to the share count.

    capital raising announcement

  15. 4 Mar

    ioneer launches a fully underwritten A$60M placement at A$0.38 a share, a 13.6% discount to the last close. Funds mainly go to detailed engineering. Addresses the ~2.6 quarters of cash left; Record of Decision expected Q4 2021, FID late 2021.

    capital raising announcement

  16. 10 Feb

    ioneer says the new US administration's transition will delay BLM permitting; it now expects the final Record of Decision in Q4 2021, later than the earlier Q2 2021 construction-ready target. It also began working with The Conservation Fund on Tiehm's buckwheat protection.

    regulatory community update

2020

  1. 28 Oct

    Caterpillar (via Nevada dealer Cashman Equipment) chosen as exclusive heavy equipment partner for Rhyolite Ridge, about US$100M of equipment and services over the first five years. Caterpillar Financial may offer financing. Subject to FID and definitive documents; a joint autonomous haul truck study is planned.

    contract award

  2. 31 Aug

    BLM deemed the Plan of Operations complete and accepted it, so environmental review and the Stantec-prepared EIS can proceed. This resolves the earlier wait for BLM's completeness review. Company still targets being construction ready in Q2 2021; final approval needs a Record of Decision.

    regulatory community update

  3. 2 July

    Chairman James Calaway becomes an executive for 12 months from 1 July 2020, on US$300,000 a year on top of his US$150,000 director fee. He is to lead the search for project partners and funding; follows the FY2020 'special exertion fee'.

    director officer appointment

  4. 1 June

    Julian Babarczy joins the board as non-executive director from 1 June, a former Regal Funds Management portfolio manager (Regal is a long-term shareholder). He is focused on funding construction. The board says it is still reviewing board and management composition.

    director officer appointment

  5. 21 May

    Signed three-year boric acid distribution agreements with Kintamani and Boron Bazar for South and Southeast Asia, conditional on a positive FID expected early 2021. With Jinma, 100% of year-one boric acid is covered; the new deals are about 13% of forecast output.

    material agreement

  6. 12 May

    ioneer lodged its Plan of Operations with the BLM, as previously flagged, including 14 baseline studies. BLM must review it and publish a Notice of Intent before the Environmental Impact Statement process starts. Approval is not yet granted.

    regulatory community update

  7. 30 Apr

    Ore Reserve up 280% to 60.0Mt at 1,800ppm lithium and 15,400ppm boron (0.6Mt lithium carbonate, 5.3Mt boric acid), about half Proved. Resource revised to 146.5Mt from 154.0Mt. Delivers the update promised with the DFS.

    resource reserve update

  8. 30 Apr

    DFS completed: after-tax NPV US$1.265B (down from PFS US$1.8B) and IRR 20.8% (PFS 27.7%). Capex US$785M, up US$186M on the PFS. All-in sustaining cost US$2,510/t lithium carbonate equivalent. 26-year life; partner and funding talks continue.

    investor presentation

  9. 24 Mar

    COVID-19 delays the DFS again, now to late April 2020, and the company says it could slip further. It moves to a slower post-DFS pace, with cash of A$54.2M at 29 February said to fund all capital needs until at least end 2021. Engineering is close to 30% complete.

    investor presentation

2019

  1. 18 Dec

    First binding offtake: Dalian Jinma Boron will buy 105,000 tonnes a year of boric acid for five years from Q1 2023, over 50% of expected output. Conditional on a positive final investment decision, expected early 2021. Jinma also becomes exclusive China/Taiwan distributor.

    material agreement

  2. 21 Nov

    Fully underwritten A$40M placement of 200M shares at A$0.20, an 11.1% discount to the last close, including A$20M from Centaurus Capital (7.8% holding after). Funds the company to FID, including DFS completion and engineering to about 50%.

    capital raising announcement

  3. 1 Oct

    Pilot plant processed 30t of ore and met its objectives, but process tweaks push the Rhyolite Ridge DFS from late Q3 2019 to Q1 2020. Samples went to 30 potential offtake customers; 20 potential partners toured the plant.

    drilling result

  4. 4 July

    Pilot plant in Vancouver is operating and the main ore run has begun, producing boric acid above 99.9% purity that meets industry specifications. Samples have gone to potential offtake partners; about 28t of ore will be processed, with lithium carbonate to follow.

    drilling result

  5. 26 June

    Rhyolite Ridge resource upgraded 27% to 154Mt, containing 1.3Mt lithium carbonate and 12.4Mt boric acid, from the 2018-19 drilling. Includes a maiden Measured Resource of 41.0Mt; starter pit to mine the high-grade Upper Zone. Remains open to the south.

    resource reserve update

  6. 11 June

    Veolia bench-scale testwork produced battery-grade lithium hydroxide from Rhyolite Ridge ore, validating the flowsheet and key parameters for the DFS. It adds lithium hydroxide to the carbonate and boric acid product range; DFS still due Q3 2019.

    drilling result

  7. 3 Apr

    SNC-Lavalin, using DuPont MECS technology, awarded acid plant engineering for the DFS. Its estimate is about US$111M versus US$170M in the PFS, a saving of about US$60M, from a change in contracting approach. Further savings are possible but not yet confirmed.

    contract award

  8. 13 Mar

    Kemetco Research appointed to build and run the Vancouver pilot plant for the DFS, with the main bulk sample run in May 2019. It will make products for offtake marketing and support partner talks. DFS still due Q3 2019; company says it is funded to FID.

    contract award

  9. 20 Feb

    Assays for the first 17 of 45 holes show higher grades than the 2018 reserve. The 10 southernmost holes average 2,162ppm lithium and 1.44% boron, about 15% and 20% above PFS reserve grades. Mineralisation stays open to the south; results feed the DFS.

    drilling result

2018

  1. 21 Dec

    Maiden Ore Reserve for the starter pit: 15.8Mt at 1,900ppm lithium and 12,200ppm boron, containing 160,000t lithium carbonate equivalent and 1.1Mt boric acid. Early drilling shows higher boron grades and shallow southern extensions, which the company expects to help early cash flow. Three rigs continue into 2019.

    resource reserve update

  2. 21 Nov

    Fluor Corporation appointed engineering and design firm to complete the Definitive Feasibility Study for Rhyolite Ridge, and to provide engineering, procurement and construction management as the project advances. Fills the open DFS engineer thread; first production still expected in 2021.

    contract award

  3. 23 Oct

    South Basin resource updated to 475Mt at 1,610ppm Li and 4,100ppm B (4.1Mt lithium carbonate, 10.9Mt boric acid). High-grade portion is now 121Mt at 1,740ppm Li, 1.26% B, down from 137Mt at 1,800ppm in October 2017, after a revised geological interpretation.

    resource reserve update

  4. 23 Oct

    PFS completed: 20,200tpa lithium carbonate and 173,000tpa boric acid, US$1,796/t lithium carbonate cost net of boric acid credit, 2021 production target. After-tax NPV (7%) US$1.8B, IRR 27.7%; initial capex US$426M plus US$173M acid plant. Resolves the open PFS thread; DFS engineer to be named.

    resource reserve update

  5. 28 Sept

    Company plans to change its name from Global Geoscience to ioneer Ltd, subject to shareholder approval at the 31 October 2018 AGM. ASX code INR has been reserved for when trading as ioneer begins.

    other

  6. 28 Aug

    Premium-quality boric acid was produced from Rhyolite Ridge material using the PFS flowsheet, with low impurities and 550 micron crystals. Lithium carbonate production is in progress, and the PFS is still said to be on track for the current quarter.

    drilling result

  7. 3 Aug

    Mining study shows a 92Mt mineable quantity (1,735ppm Li, 1.23% B) from the Indicated resource only, supporting about 30 years at 3Mtpa. A southern start-up pit of 15Mt at 1,957ppm Li is favoured. Two drill rigs have started; PFS still due Q3 2018.

    resource reserve update

  8. 14 June

    A$53M placement completed, described as heavily oversubscribed: 130M shares at A$0.41, taking shares on issue from 1,339M to 1,469M (9.73% dilution). Underwriter fee 4.75% of proceeds; settlement 20 June 2018.

    capital raising announcement

  9. 13 June

    Company launched a fully underwritten A$53M placement of 130M shares at A$0.41, a 7.9% discount to the last close. Citigroup underwrites. Funds PFS, pilot plant, DFS and A$20M of resource drilling, through to a mine development decision by late 2019.

    capital raising announcement

  10. 6 June

    Proposed flowsheet and site layout released for Rhyolite Ridge, producing lithium carbonate and boric acid on site. Footprint under one square mile (640 acres) may allow the faster BLM Environmental Assessment permitting path; baseline studies due end Q3 2018. PFS still due Q3 2018.

    regulatory community update

  11. 23 May

    Phase 1 of the Rhyolite Ridge PFS is complete. Vat leaching, an on-site acid plant (acid cost estimated US$20-30/t after steam and power credits), mechanical evaporators and dry stacking were selected. This resolves the open flowsheet question; PFS release is now due Q3 2018.

    other

  12. 3 May

    Vat leach tests at Rhyolite Ridge recovered over 90% of lithium and boron in under 7 days, with acid use under 400kg/t, versus 15 days for the best heap test. Company expects lower costs; Amec has completed PFS Phase 1, results due later in May.

    drilling result

  13. 21 Feb

    Finer crushing (minus 38mm) cut column leach time at Rhyolite Ridge from 41 to 15 days, with 97% lithium and 98% boron recovery. Builds on December's heap leach result; Amec is now weighing tank, vat and heap routes for the PFS.

    drilling result

2017

  1. 19 Dec

    Initial mining study indicates low-cost open pit mining at 2-4Mtpa from the high-grade resource alone. Options are a 26Mt starter pit (13-year life, strip ratio 3.9) possibly eligible for fast-track permitting, and an 87Mt pit (21 years). Mining costs only; processing excluded.

    resource reserve update

  2. 12 Dec

    Column testwork shows Rhyolite Ridge ore can be heap leached, with 89-92% lithium and 88-89% boron recovery in 30-41 days. Company says this is an industry first and likely cuts capital and operating costs versus tank leaching. Builds on the earlier 98% tank-leach recoveries; PFS continues.

    drilling result

  3. 31 Oct

    Updated South Basin resource at Rhyolite Ridge: 460Mt at 1,700ppm Li and 0.46% B (4.1Mt lithium carbonate, 11.9Mt boric acid), up from 393Mt. High-grade portion doubled from 65Mt to 137Mt, 75% Indicated. Resource still open north, south and east.

    resource reserve update

  4. 5 Oct

    Final assays from the completed drilling program confirm thick near-surface high-grade mineralisation within and south of the resource, e.g. 26m at 1580ppm Li and 1.93% B in SBH-25. Company expects a higher high-grade tonnage; updated resource due later in October.

    drilling result

  5. 28 Sept

    Raised A$30M via a fully underwritten placement of 150M shares at A$0.20, a 9.1% discount to the last close. Citigroup underwrote. Funds the PFS, pilot plant and, if the PFS is positive, the DFS; cash rises to about A$35M. Larger than the April Calaway raise.

    capital raising announcement

  6. 25 Sept

    Secured an exclusive 20-year lease (renewable for 79 years) over water rights of 1.2 gigalitres a year for Rhyolite Ridge, with an option to buy. Drilling is complete and the resource update has slipped from September to October.

    material agreement

  7. 31 Aug

    Further assays extend near-surface high-grade lithium-boron south of and within the resource, e.g. 21m at 2147ppm Li and 1.25% B in SBH-28 and 29m at 1695ppm Li and 1.85% B in SBH-33. Company says the high-grade tonnage is likely to rise; resource update due September.

    drilling result

  8. 16 Aug

    First eight holes of the 5,000m program hit high-grade lithium-boron within and south of the 393Mt resource, e.g. 17m at 2153ppm Li and 1.18% B in SBH-19. Mineralisation is open to the south; updated resource due September 2017.

    drilling result

  9. 30 June

    A 5,000m drill program has started at Rhyolite Ridge, now 100% owned. It aims to upgrade the resource to Indicated for the pre-feasibility study and test for shallow high-grade extensions outside the current resource. Results will be released as received.

    drilling spud

  10. 23 May

    Former Rio Tinto energy and industrial minerals CEO Alan Davies and former Shell Oil president John Hofmeister join as non-executive directors. Gabriel Chiappini and Barnaby Egerton-Warburton stepped down to make way, continuing the board renewal under new Chairman Calaway.

    director officer appointment

  11. 2 May

    Acid-leach tests recovered 98% of lithium and 99% of boron, using 296kg of acid per tonne of ore, below the 350-450kg target. This completes the stage 3 testwork. The company also exercised its option for 100% of Rhyolite Ridge, with no royalties; a PFS is due late 2017.

    drilling result

  12. 28 Apr

    March quarter report gives the maiden drill assays: South Basin extended mineralisation 200m east of the resource, e.g. 22.9m at 1354ppm Li and 1.68% B in SLB-2; North Basin confirmed thick mineralisation (67m at 1212ppm Li). One South Basin hole was abandoned. Acid leach results are imminent.

    quarterly activities report

  13. 5 Apr

    James Calaway, former Orocobre chairman, becomes non-executive Chairman. He and related parties will invest US$4M (about A$5M) in about 40M shares at roughly A$0.125, a 15% discount to the ten-day average. He also receives 40M options at $0.15, $0.20 and $0.25.

    director officer appointment

2016

  1. 16 Nov

    Site visit identified a 20m-thick Searlesite Zone, which makes up 97% of the 65Mt high-grade part of the South Basin resource. The company says its coarse grain and low clay content point to simpler, lower-cost processing. Test results are due in six to eight weeks.

    drilling result

  2. 10 Oct

    Maiden South Basin resource, as flagged for October: 393Mt at 1.2% lithium carbonate equivalent (Indicated and Inferred), containing 3.4Mt lithium carbonate. Includes a 65Mt high-grade zone at 2.0% LCE. Open to north, south and east; drilling starts late October.

    resource reserve update

  3. 30 Sept

    Historic US Borax drilling at North Basin, which backs the 5 September Exploration Target, shows 100-260m thick shallow lithium-boron zones over 5 sq km in 9 holes. Best: 201m at 1364ppm Li. A drill program starts late October; South Basin resource due early October.

    drilling result

  4. 5 Sept

    Historic data shows a high-grade upper zone at South Basin (10-20m thick, about 1.4% LCE). Also announced a North Basin Exploration Target of 1-1.5 billion tonnes at 1000-2000ppm Li, conceptual only. Maiden resource due October; drilling planned for the December quarter.

    resource reserve update

  5. 16 Aug

    Review of five undisclosed 2011 diamond holes at South Basin, drilled by a previous explorer, shows wide mineralisation, e.g. 163m in SBHC-1, including 41m at 1892ppm Li (1.01% LCE). Maiden JORC resource is expected within two months.

    drilling result

  6. 9 Aug

    Raised A$6M through a heavily oversubscribed placement of 80M shares at A$0.075, an 8.5% discount to the last close. Hartleys and Cygnet were joint lead managers. The company says this fully funds Rhyolite Ridge through pre-feasibility, resolving the earlier funding need.

    capital raising announcement

  7. 21 July

    Announced a new 2.5km outcropping zone of lithium-boron-strontium mineralisation at South Basin. 84 rock chips average 2016ppm Li for samples over 1000ppm, up to 3740ppm Li (2.0% LCE). It is undrilled and outside the 8 June Exploration Target, which may be enlarged.

    drilling result

  8. 4 July

    Completed due diligence and proceeds with the Rhyolite Ridge option from Boundary Peak Minerals. Payable at completion of due diligence: US$300,000 cash plus US$1.5M in shares; a further US$200,000 plus US$1.5M in shares on exercise within a year, plus US$4M deferred. Share issues need shareholder approval.

    farm in farm out agreement

  9. 8 June

    Announced an Exploration Target at Rhyolite Ridge of 200 to 300 million tonnes at 1200-2000ppm lithium (0.64-1.06% LCE) and 0.6-1.2% boron. It is conceptual only, based on 15 historic RC holes, and not a Mineral Resource.

    resource reserve update

  10. 3 June

    Secured an exclusive option to acquire 100% of the Rhyolite Ridge lithium-boron project in Nevada from Boundary Peak Minerals, covering over 22 sq km with over 100 past drill holes. Due diligence runs to 3 July 2016, with US$100,000 payment. A new lithium direction after the GetSwift deal was dropped.

    asset acquisition disposition

  11. 26 May

    Company chose not to exercise its option to acquire GetSwift, ending the deal signed 12 April 2016. It says it will refocus on its 100%-owned Nevada and Arizona projects and look for further opportunities. The proposed consolidation and $5M raising fall away (inference).

    business combination

  12. 12 Apr

    Company signed a binding term sheet to acquire GetSwift, a logistics software platform, via an option over Distributed Logistics Group, subject to due diligence. Cygnet Capital would lead a raising of up to $5M. This is a move away from mineral exploration.

    business combination

  13. 29 Jan

    The $1M placement completed in two tranches, and shareholders approved tranche 2 on 4 December. Excelsior option was terminated with no retained interest, as final spending was not met. No field work; review to divest early-stage projects continues.

    quarterly activities report

2015

  1. 3 Nov

    Chairman Rob Reynolds and director Peter Nicholson resigned; Barnaby Egerton-Warburton and Gabriel Chiappini were appointed directors. Nicholson stays as technical consultant. This carries out the board restructure announced on 28 October.

    director officer appointment

  2. 28 Oct

    Cygnet Capital is mandated to run a $1M placement of 500M shares at $0.002, in two tranches; tranche two needs shareholder approval. Completion also depends on restructuring existing debt. The board is reviewing divesting early-stage projects and plans to replace Reynolds and Nicholson with two new directors.

    capital raising announcement

  3. 22 July

    Reprocessed geophysics defines a large copper-gold porphyry target at Quillcata, within the 100%-owned Mancha Pampa project in Peru. Rock chips reach 2.5% Cu and 4g/t Au; up to eight holes (2,000m) are proposed, with permitting underway. Never drilled.

    drilling scheduled

2014

  1. 7 Nov

    The rights issue closed under-subscribed: applications for 34.2M shares raised $342,413 against up to $1.08M sought. Directors plan to take 20M shares from the shortfall, lifting the total to about $542,412. Well short of the target amount.

    capital raising announcement

  2. 29 Sept

    Global launched a non-renounceable rights issue of 1 new share for every 2 held at $0.01, raising up to $1.08M, with a free 3c option per two new shares expiring Sept 2016. Funds go to Excelsior drilling and Peru work. Not underwritten.

    capital raising announcement

  3. 31 July

    Antofagasta has elected to stop funding Towers Mountain and keeps no rights, so Global holds 100% and can seek others; drill permitting is underway. Tokop leach tests show lower recoveries on coarse material, so focus shifts to higher-grade zones above 1g/t Au.

    quarterly activities report

  4. 26 May

    Preliminary cyanide leach tests on Tokop drill chip samples show average recoveries of 81% gold and 71% silver (46 samples above 0.1g/t Au). Company says this indicates amenability to heap leach and justifies more testing. Later reporting qualifies this result.

    well test result

  5. 7 May

    Tokop second program (13 holes, 2,774m) hit shallow oxide gold-silver, best 13.8m at 0.94g/t Au from 193.5m. Company states an Exploration Target of 50-100Mt at 0.4-0.8g/t Au (conceptual, not a resource). Heap leach testing is the next step.

    drilling result

  6. 31 Mar

    Drilling has begun at Tokop: up to twenty reverse-circulation holes, about 4,000m total, targeting shallow oxide gold. It follows the 2013 maiden program. Results from the first ten holes are expected in three to four weeks.

    drilling spud

  7. 27 Mar

    Global raised $926,574 (before fees) through a placement to new sophisticated investors: 30,885,800 shares at $0.03 plus 15,442,901 free options at $0.05 expiring September 2015. Funds go to a Tokop drilling program starting within days.

    capital raising announcement

  8. 20 Feb

    Global named Towers Mountain, a copper-molybdenum porphyry system in Arizona (178 claims, 14.5 sq km, 100% Global), as the first Designated Property under the Antofagasta alliance. Antofagasta can earn 51% for US$1M over two years, then 70% with US$5M total over six years.

    farm in farm out agreement

2013

  1. 23 Oct

    Osisko terminated its earn-in on Global's five Nevada gold projects, ending the 2012 deal; Global keeps 100% of its rights and Osisko has no retained interest. Osisko had funded about US$3.7M. Global says third parties are showing interest in Tokop, with site visits planned.

    material agreement termination

  2. 2 Oct

    The Antofagasta copper alliance in Arizona is now formal, resolving the earlier non-binding letter of intent. Antofagasta can earn 51% per project by spending US$1M over two years, then 70% with a further US$4M. Initial focus is 15 targets; fieldwork starts this month.

    farm in farm out completion

  3. 16 Sept

    Tokop's maiden seven-hole program hit gold in every hole, including 12.2m at 2.5g/t Au from 59.4m and 18.8m at 1.3g/t. Company calls it a greenfield discovery and plans systematic follow-up drilling; only part of the 2x1.1km intrusion was tested.

    drilling result

  4. 19 Aug

    The $1.1M rights issue is now complete. The shortfall of $514,239 was filled: 10,474,641 shares and options issued to investors, and directors applied for $200,000 subject to approval at a 3 September EGM. This resolves the Veritas shortfall thread.

    capital raising announcement

  5. 1 Aug

    Global and Osisko plan to start maiden drilling at Tokop on or around 4 August 2013: at least five holes of 200-300m over about 1km. It tests beneath trench results such as 18m at 1.9g/t gold. Global calls Tokop its top priority project.

    drilling scheduled

  6. 17 June

    The rights issue closed with applications for 19.9M shares and options, about 55% of the offer, raising $597,650 against the up to $1.11M sought. Veritas Securities will try to place the balance with new investors; an update is promised.

    capital raising announcement

  7. 5 June

    Global signed a non-binding letter of intent with Antofagasta for a fully funded copper exploration alliance in Arizona, covering 13 Global-selected targets. Antofagasta can earn 51% per project by spending US$1M over two years, rising to 70% with a further US$4M. Contingent on a formal agreement.

    farm in farm out agreement

  8. 13 May

    Global launches a non-renounceable rights issue: 1 new share for every 4 held at $0.03, with a free attaching 5c option expiring 30 June 2014. It aims to raise up to $1.11M, not underwritten. Funds go to Nevada, Peru and working capital; directors (about 12%) intend to take up in full.

    capital raising announcement

  9. 21 Mar

    Osisko committed to keep funding gold exploration at Lone Mountain, Excelsior and Tokop, under the US$8M for 45% deal. Global will pursue the Lone Mountain silver-lead-zinc target itself. Field work restarts in April; South Jasperoid drilling is set for late June quarter.

    joint venture update

  10. 28 Feb

    Two new Lone Mountain drill targets: a silver-lead-zinc target of over 100 million tonnes (Global's own estimate target, not a resource) and a South Jasperoid gold target. Osisko is not interested in the base metals, so Global can pursue them itself. Drilling planned for the coming field season.

    drilling scheduled

  11. 14 Feb

    Global now sees Excelsior as an intrusion-related gold system, which it says significantly upgrades size potential. Eight wide-spaced holes (1,976m) hit broad low-grade gold, no ore grade. Past intercepts include 47.3m at 1.5g/t. Target is a multi-million ounce deposit.

    drilling result

2012

  1. 19 Sept

    Lone Mountain first-pass drilling (seven holes) confirmed Carlin-type gold at South Jasperoid, best 44m at 0.3g/t gold, and base-metal breccia at Rip Van Winkle. A second phase is planned. Bartlett assays pending; Orovada drilling started and Excelsior due. Osisko funds all.

    drilling result

  2. 9 Aug

    First Lone Mountain results: Rip Van Winkle hole 1 hit 72m at 0.5% lead, 1.3% zinc and 34g/t silver, including 17m at 1.23% Pb, 3.5% Zn and 78g/t Ag. The breccia is open and could host gold. Base metals, not gold, so far. Osisko funds it.

    drilling result

  3. 26 June

    A 4,000m reverse circulation drill program began at Lone Mountain, testing Carlin-style gold targets at the Rip Van Winkle and South Jasperoid prospects, funded by Osisko. It is the first of four planned Nevada drill programs for 2012. This follows the gravity survey.

    drilling spud

  4. 14 May

    A 2,000m reverse circulation drill program began at Sara Sara, Peru, the first follow-up to the 2010 silver hit of 16.4m at 410g/t. Mineralisation is open in all directions. This is Global's first Sara Sara drilling since that 2010 discovery.

    drilling spud

  5. 12 Apr

    Field programs have started in Nevada and Peru, with 5,000m+ of drilling scheduled for the June quarter, including 2,000m at Sara Sara from May and 3,000m at Lone Mountain. Global describes the 2012 exploration budget as fully funded at $2.5M.

    drilling scheduled

  6. 27 Feb

    A detailed gravity survey (547 stations) at Lone Mountain identified untested drill targets at 100-300m depth that could host Carlin-style gold. Drilling is planned and will be funded by Osisko under its US$8M earn-in. Follows the December gravity work; no drill results yet.

    drilling result

  7. 14 Feb

    Osisko Mining can earn 45% of Global's five Nevada gold projects by funding US$8M over up to four years (minimum US$2M in year one), and has subscribed A$852,000 for 14.2M shares at $0.06. Global stays operator. Osisko can lift to 70% by funding a feasibility study.

    farm in farm out agreement

2011

  1. 30 Nov

    Global took an exclusive lease and option to buy 100% of the 35 sq km Lone Mountain gold project in northern Nevada, a Carlin-style target between the Carlin and Independence trends. Only four holes drilled in 13 years; gravity survey then RC drilling planned.

    asset acquisition disposition

  2. 28 Sept

    Global's first Excelsior drilling, 23 RC holes (3,657m), hit shallow oxidised gold across 2.2km, e.g. 7.6m at 5.1g/t from 93m. Mineralisation is open along strike and at depth. Infill drilling is planned. This follows the July drilling start.

    drilling result

  3. 27 Apr

    The Sara Sara diamond program ended after seven holes (3,600m). Best result was KPD-03 at 36m at 0.27% Cu; the other six hit only sporadic low-grade copper and molybdenum. No porphyry copper has been found yet. Future RC silver drilling and a deeper hole to 1,500m are planned, subject to a rig.

    drilling result

  4. 28 Mar

    Global can earn 70% of the Excelsior Springs gold project in Nevada from Canada's Nubian Resources by spending $3M over four years plus $100,000 cash; minimum $150,000 by end 2011. Includes the historic Buster mine, with past drill hits such as 33m at 2.9g/t Au. This adds a new gold project.

    farm in farm out agreement

2010

  1. 23 Dec

    Sara Sara hole KPD3 hit 33m at 0.28% copper from 183m, mainly chalcocite in a supergene (enriched, often leachable) blanket. Management says all three holes in the Target Zone show it, and sees it as evidence of nearby primary copper. This is a new discovery-style result.

    drilling result

  2. 20 Oct

    Global is raising up to $4M at $0.07 a share. A $2.1M placement of 30M shares is split in two tranches, the second needing shareholder approval. A 1-for-3 entitlement offer raises $1.9M and is underwritten. Funds go to Sara Sara and gold projects.

    capital raising announcement

  3. 15 Oct

    The Guyra sale to White Rock is complete: Global's subsidiary received 2 million White Rock shares after both conditions were met. The shares are escrowed for 12 months. This resolves the pending conditional sale.

    asset acquisition disposition

  4. 29 Sept

    Sara Sara's Kapish prospect returned a high-grade silver discovery: 16.35m at 410g/t Ag, 0.14% Cu from 238.7m in hole KP-14, with some poor core recovery. Other holes show copper and molybdenum, open to the north, west and southwest. This follows the KP10 diamond and RC program.

    drilling result

  5. 23 Aug

    Diamond drilling has started at New Morenci in Arizona, one hole testing for a buried secondary copper blanket like that at the Morenci mine 1km south. No previous drilling is known in the area. This follows the early-August start planned earlier.

    drilling spud

  6. 4 Aug

    Global agreed to sell its Guyra copper-gold project in NSW (193 sq km) to White Rock Minerals for 2 million White Rock shares. It is conditional on White Rock's ASX listing in 2010 and NSW transfer approval. This continues the clear-out of Australian ground.

    asset acquisition disposition

  7. 3 Aug

    Global sold its subsidiary holding the Northern Territory uranium tenements to Crossland Uranium for $30,000 of past costs. It can buy back 20% after two years, or take a 2% royalty. This is the farm-out of NT ground Global had been seeking.

    asset acquisition disposition

  8. 5 July

    Diamond drilling has started at Sara Sara to test the centre of the 2.5km IP high, about 800m of core. A 2,000m RC program follows in August to chase the KP6 molybdenum result. This is the first deep test of the porphyry idea.

    drilling spud

  9. 24 June

    IP surveys at Sara Sara found a roughly 2.5km-wide deep chargeability high, interpreted at 400-500m depth, plus shallower highs. Global added at least one 800m diamond hole to the 2,000m RC program; the diamond hole starts late June, RC in August.

    drilling scheduled

  10. 27 Apr

    Global signed a lease and option over the adjoining 5 sq km Karico1 concession at Sara Sara, which may extend the KP6 molybdenum zone. Payments are US$30,000 on signing; purchase option is US$2.15M less payments, and Global can withdraw any time.

    asset acquisition disposition

  11. 4 Feb

    First Sara Sara drilling hit 24m at 877ppm molybdenum from 126m in hole KP6, including 6m at 1,530ppm. The nearest hole is 550m away. An induced polarisation survey is planned for April-May, with follow-up drilling in May-June.

    drilling result

2009

  1. 11 Dec

    First drilling at Sara Sara is set to start next week. Approvals are in hand and the drilling contract is signed. Up to ten 200m holes, about 2,000m in total, will test for copper enrichment beneath the leached surface rocks.

    drilling scheduled

  2. 20 Nov

    Placement of 8,929,000 shares at $0.10 to sophisticated investors raises $892,900, mostly for drilling at Sara Sara and other Peru and North America projects. Total shares rise to 71,789,000. The price is nearly triple the $0.035 rights issue price from September.

    capital raising announcement

  3. 11 Nov

    First three Sara Sara tenements (18 sq km) are granted, and Global plans wide-spaced drilling of the porphyry copper-molybdenum target. New sampling shows molybdenum up to 449ppm in rock, in concentric zones. This moves the project from surface work toward drilling.

    drilling scheduled

  4. 1 Sept

    The rights issue closed with shareholders applying for 22,257,817 of 31,430,000 new shares, about 70% take-up. The underwriter and sub-underwriters will take the 9,172,183 shortfall, so the full $1,100,050 is still raised.

    capital raising announcement

  5. 4 Aug

    Underwritten 1-for-1 non-renounceable rights issue at $0.035 to raise $1,100,050 via 31,430,000 shares, a near 50% discount to the prior close. Directors (19.9%) will take up their entitlements; funds go to accelerate drilling. Cash was about $1.1M at 30 June, so this roughly doubles it.

    capital raising announcement

  6. 30 Apr

    March 2009 quarter: Buenaventura found the Quillcata central zone barren and will withdraw from Mancha Pampa, paying US$33,680; Global keeps 100% and is seeking a new partner. Inmet's 63 line km IP survey at Los Graceros showed no strong anomalies. Winchester Range tenements granted.

    quarterly activities report

2008

  1. 10 Oct

    Peru's Buenaventura signs a Heads of Agreement to earn 61% of Mancha Pampa by spending US$3M over five years, including 1,000m of drilling before 31 December 2009. This delivers the farm-out to fund drilling that was being considered; Global can keep 39% afterwards.

    farm in farm out agreement

  2. 19 Sept

    Canada's Inmet Mining gets a three-year option to acquire 51% of the Mexican company holding Los Graceros by spending US$2M, at least US$350,000 in year one. This is the company's first farm-out since listing; Global can then keep 49% or convert to a 20% free-carried interest.

    farm in farm out agreement

  3. 18 Aug

    Trenching and sampling at Quillcata, Mancha Pampa, identified porphyry copper-gold mineralisation, with up to 2.6% copper in a grab sample and 4.0 g/t gold over 5m. The company will seek drilling approvals and may farm out to fund drilling.

    drilling result

  4. 24 July

    Drilling began at Brown Mountain in southern NSW, the company's first Australian drilling since listing. A 300m diamond hole tests whether the massive sulphide gossan dips west, unlike earlier holes drilled assuming an easterly dip. Company holds 100%.

    drilling spud

  5. 16 July

    Company identified a copper target, New Morenci, in Arizona, 5km north of the giant Morenci mine, on 7.6 km2 of claims it holds 100%. It plans to drill as soon as possible, though permits could take up to 12 months. No drilling results yet.

    asset acquisition disposition

  6. 29 Jan

    First post-listing exploration found a gold-in-soil zone 250m long at Mancha Pampa, Peru, with all samples above 0.5 g/t gold and a peak of 2.27 g/t. Drilling and trenching are planned for April/May. Soil results only; no drilling yet.

    drilling result

2007

  1. 19 Dec

    Global Geoscience completed its A$3.3M IPO and listed on the ASX, issuing 16.5 million shares at 20 cents for a A$6.3M market value at that price. Drilling is planned at gold and copper-gold targets in Peru, Nevada and Queensland.

    capital raising announcement

  2. 1 Nov

    Global Geoscience, the company that later became ioneer, lodged its IPO prospectus dated 23 October 2007. It describes early-stage exploration tenements with no history of profitable operations, and is flagged as speculative. Offer size and price are not visible in the readable text.

    capital raising announcement