Each one in plain English, with the numbers worked through for a shareholder.
14 Apr 2025material agreement▲ Good
Binding development agreement with Esmeralda County, Nevada, covering Rhyolite Ridge: an estimated US$5-7M in county benefits plus over US$10M in road upgrades through construction. The county approved it 2 April 2025; it takes full effect after routine statutory steps.
Ord Minnett conference presentation restating Rhyolite Ridge as permitted, with the US$996M DOE loan, 70% detailed design and the March 2025 resource of about 4Mt lithium carbonate and 15Mt boric acid. No new announcements in the excerpt.
South Basin Mineral Resource rose 45% to 510Mt, containing 3.97Mt lithium carbonate equivalent and 14.66Mt boric acid equivalent, with 81% Measured and Indicated. It includes the 12 Shelf Zone holes, up from 351Mt in April 2024. The Ore Reserve is now due April 2025.
26 Feb 2025material agreement termination▼ BadMajor
Sibanye-Stillwater's board decided not to proceed with the Rhyolite Ridge joint venture, and the agreement was terminated. This ends the planned US$490M for 50%. ioneer keeps 100% and says the DOE loan is unaffected, and it will seek a new equity partner.
Half-year to 31 December 2024: loss of US$5.6M comprehensive (US$2.6M a year earlier), cash US$21.6M, net assets US$216.4M. Reports the October Record of Decision and the January US$996M DOE loan as a subsequent event. No new project information in the excerpt.
Timetable update: Mineral Resource due February 2025, Ore Reserve and revised economics in March 2025, slipping from the earlier December 2024 target. The 12 Shelf Zone holes are expected to materially increase resource and reserves. Construction still depends on an FID with Sibanye.
December quarter report recaps the January US$996M DOE loan close, the October Record of Decision and a Nevada reclamation permit. A Center for Biological Diversity lawsuit against the BLM decision was filed in October; ioneer was allowed to intervene in January. FID is still targeted for 1Q 2025.
December quarter cash fell to US$21.6M from US$27.2M, with US$2.0M operating and US$2.5M investing outflow and no financing inflow. The US$1.2M unsecured Stillwater loan remains drawn.
Closed a US$996M US Department of Energy loan (US$968M principal plus US$28M capitalised interest), US$268M more principal than the January 2023 conditional commitment. It has a 20-year tenor. First funding needs the Sibanye JV closing, additional funding and a model bring-down.
Chair's AGM address says the October 2024 Record of Decision de-risks Rhyolite Ridge, engineering is 70% complete, and the focus is the DOE loan, Sibanye equity agreement and any extra funding. Construction notice to proceed is targeted for Q1 2025 and first production for 2028, assuming FID.
All 15 resolutions at the 1 November 2024 AGM were carried, including the remuneration report (about 96% for) and the refresh of the 15% placement capacity. Administrative result only.
IMARC conference presentation describing Rhyolite Ridge as permitted after the October 2024 ROD. It restates known points: US$700M DOE conditional loan, US$490M Sibanye equity, over 70% design complete and a 3.2Mt LCE resource. No new announcements in the excerpt.
The BLM issued the Record of Decision, the final federal permit for Rhyolite Ridge, resolving the permitting thread. Construction is planned for 2025 and first production in 2028. FID has slipped to 1Q 2025, with updated reserves and costs due by December 2024.
September quarter cash fell to US$27.2M from US$35.7M, with US$1.6M operating and US$7.3M investing outflow and no financing inflow. The US$1.2M unsecured Stillwater loan remains drawn.
September quarter report recapping the Final EIS publication, the Shelf Zone drilling results and the 2024 Sustainability Report. The ROD was expected in October. No new project figures in the excerpt.
20 Sept 2024regulatory community update▲ GoodMajor
The Bureau of Land Management published the Final EIS, and US Fish and Wildlife concluded the project will not jeopardise Tiehm's buckwheat, ending ESA consultation. A Record of Decision can follow after a waiting period to 21 October. First production is now targeted for 2028, versus 2027 earlier.
2024 Sustainability Report for the year to 30 June 2024, not externally assured. It reports zero injuries over 57,642 hours worked. No financial or project-timing information in the excerpt.
Appendix 4G checklist cross-referencing the governance statement to ASX recommendations, signed by the CFO/Company Secretary. Administrative filing with no new information.
FY2024 annual report. The Executive Chair says the US$25M placement strengthened the balance sheet and a positive October 2024 Record of Decision is expected. It stresses Rhyolite Ridge's multi-stage growth potential. The excerpt is truncated and has no new figures.
Corporate Governance Statement for the year to 30 June 2024, describing board and management arrangements under ASX principles. Compliance document with no new business information in the excerpt.
The 2024 AGM will be held at 10:00am Sydney time on 1 November 2024, in North Sydney and online. Director nominations from outside the Board close 12 September. Administrative notice only.
June quarter: placement of US$25.1M completed, draft EIS comment period closed, with final EIS expected September and Record of Decision October 2024. Cash was US$35.7M at 30 June. Resource figures repeat the April update: 351Mt and 3.25Mt LCE.
June quarter cash rose to US$35.7M from US$19.0M after US$25.1M of placement proceeds (US$24.3M financing inflow net of costs). Operating outflow was US$1.6M and investing US$6.7M. The US$1.2M Sibanye-affiliate loan remains drawn.
The final 12 Shelf Zone holes, left out of the April resource, all average over 2000ppm lithium in the main B5 unit, more than 20% above the Stream 1 average. It lies under less than 30m of gravel, outside critical habitat. Reserve update due in weeks.
ioneer joined Caterpillar's four-year Pathways to Sustainability education program, building on the 2022 autonomous haul system agreement. It is a relationship and learning program with no stated financial terms; the release cites 2027 for operations.
June investor presentation restating known points: expected full permitting in late 2024, US$490M Sibanye and US$700M DOE conditional funding, binding offtakes, engineering over 70% complete and 3.4Mt LCE resource. No new announcements in the excerpt.
The draft EIS public comment period closed, and management says this supports its expectation of a final EIS in September and a Record of Decision in October 2024. No new dates or figures.
Cleansing notice confirming 213,602,562 new shares were issued on 6 May 2024 under the April placement. Administrative notice completing the raising; no new information.