20 Oct 2025quarterly activities report● Neutral
Cash fell to US$21.8M from US$25.1M. Operating outflow was US$2.0M, investing US$3.5M, offset by US$2.2M equity from the SPP. No facilities drawn; the report shows about 4.0 quarters of funding.
Each one in plain English, with the numbers worked through for a shareholder.
20 Oct 2025quarterly activities report● Neutral
Cash fell to US$21.8M from US$25.1M. Operating outflow was US$2.0M, investing US$3.5M, offset by US$2.2M equity from the SPP. No facilities drawn; the report shows about 4.0 quarters of funding.
20 Oct 2025quarterly activities report▲ Good
September quarter report recaps the 3 September upgrade: NPV up 38% to US$1,888M, 25% more ore processed with two-day leach and no extra capex. Resource is 539Mt and Ore Reserve 260Mt. SPP raised US$2.2M.
25 Sept 2025admin correction● Neutral
The board is changing the financial year end from 30 June to 31 December. A six-month transitional year ends 31 December 2025, requiring an additional annual report by March 2026 and an extra AGM in May 2026.
22 Sept 2025director officer appointment● NeutralMajor
CFO and Company Secretary Ian Bucknell, with Ioneer seven years, will leave effective mid-December. The CFO role will move to the US as the company heads towards partnering, FID and construction; the Company Secretary role stays in Australia.
17 Sept 2025other● Neutral
Corporate governance statement for the year to 30 June 2025, stating the company's policies comply with the ASX governance principles except where otherwise indicated. Administrative; no new information.
17 Sept 2025other● Neutral
Appendix 4G checklist cross-referencing the governance statement to ASX recommendations, dated 17 September 2025 and signed by Ian Bucknell. Administrative; no new information.
17 Sept 2025annual report● Neutral
FY2025 annual report: Executive Chair says Rhyolite Ridge is 100% owned and focus is on a strategic equity partner and FID. Partnering began 3 July 2025 for at least four months. Reports AISC of US$5,745 per tonne LCE, which predates the later US$5,626 update.
17 Sept 2025other● Neutral
Fourth annual sustainability report for the year to 30 June 2025. Recaps the October 2024 BLM Record of Decision, Tiehm's buckwheat conservation and the county development agreement. Commercial operations have not started. No new project figures.
5 Sept 2025other▼ Bad
S&P Dow Jones Indices' September rebalance lists Ioneer among removals from the S&P/ASX 300, effective before the open on 22 September 2025. Ioneer had been in the index since March 2018. Index-fund selling may follow (inference).
4 Sept 2025investor presentation● Neutral
Notice of an investor conference call on 4 September with Bernard Rowe about the improved project economics. Administrative; no new information.
4 Sept 2025investor presentation● Neutral
September investor presentation repeating the 3 September economics upgrade: NPV up 38% to US$1.89B, AISC US$5,626, and a 260Mt Ore Reserve with an 82-year mine life. It says construction starts after the partnering process and final investment decision.
4 Sept 2025agm notice● Neutral
Annual general meeting set for 31 October 2025, online. Director nominations close 11 September. Administrative notice.
3 Sept 2025resource reserve update▲ GoodMajor
Shortening the vat leach time from three days to two lifts processing from 2.4 to 3.0Mtpa. Unlevered NPV rises 38% to US$1,888M, IRR 16.8%, AISC US$5,626/t LCE, with no capex change. This builds on the June testwork on shorter leach cycles.
28 July 2025quarterly activities report● Neutral
Cash flow report shows cash up to US$25.1M from US$14.1M, as US$16.4M of equity proceeds outweighed operating outflow of US$1.7M and investing outflow of US$3.2M. No financing facilities are shown as drawn.
28 July 2025quarterly activities report● Neutral
June quarter report recaps the Ore Reserve upgrade to 247Mt, US$1.367B NPV, the US$16M placement and the start of partnering. Cash rose to US$25.1M from US$14.1M, helped by the raise.
17 July 2025capital raising announcement● Neutral
The share purchase plan raised about US$2.2M (A$3.4M) from applications for 33.55M shares at A$0.10, below the A$5.0M target. This completes the placement-plus-SPP raise, which together brought in roughly A$28M.
What it means for a shareholder
33.5m new shares at A$0.100 to raise about A$3.4m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Create a free account to see this worked out for your own holding.
26 June 2025other● NeutralMajor
Ioneer formally launched its strategic partnering process, with Goldman Sachs advising, to find an equity partner for Rhyolite Ridge. It is expected to take at least 4 months. This continues the search that began after Sibanye's exit.
25 June 2025capital raising announcement● Neutral
The share purchase plan opened to eligible Australian and New Zealand shareholders at A$0.10, the same price as the placement, up to A$30,000 each, targeting about A$5.0M. It closes 10 July 2025. Administrative follow-up to the 13 June raise.
19 June 2025other● Neutral
Cleansing notice confirming issue of 252,500,000 placement shares from the 13 June raise. Administrative; no new information.
13 June 2025capital raising announcement● NeutralMajor
Ioneer raised about US$16M (A$25M) in a placement of roughly 253M shares at A$0.10, a 13.0% discount to the 10 June close. A share purchase plan targeting up to A$5.0M follows. Funds are meant to carry the project through the partnering process to a final investment decision.
What it means for a shareholder
253m new shares at A$0.100 to raise about A$25.0m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Create a free account to see this worked out for your own holding.
13 June 2025investor presentation● Neutral
Presentation supporting the June placement, referring back to the 2 June Ore Reserve and economics update. The excerpt shows only disclaimers and a competent persons statement, so no new information is evident.
13 June 2025admin correction● Neutral
Corrects two minor inconsistencies in the 2 June announcement: a boron grade table was deleted and a 2025 versus 2020 reserve comparison table was corrected. Ioneer says the Mineral Resource and Ore Reserve estimates are unchanged.
2 June 2025investor presentation● Neutral
Notice of an investor conference call on 2 June 2025 with Managing Director Bernard Rowe to discuss the Ore Reserve and economics update. Administrative; no new information.
2 June 2025resource reserve update▲ GoodMajor
Ore Reserve rose more than fourfold from 60Mt (2020) to 247Mt, a 95-year mine life, containing 1.92Mt lithium carbonate equivalent. Updated economics: after-tax NPV8 US$1.367B (2020: US$1.265B), IRR 14.5% (2020: 20.8%), capex US$1,667.9M (2020: US$785M).
2 June 2025investor presentation● Neutral
Presentation of the 2 June Ore Reserve and economics update, restating a 247Mt reserve, 95-year mine life and US$996M DOE loan. It notes a partnering process has begun. No new information beyond the release.
29 May 2025other▲ Good
Testwork shows a shorter vat leach cycle (7 to about 6 days) could raise lithium and boric acid output 7-14% per tonne of acid and allow 8-16% more ore throughput. Benefits are not yet in the updated economics, due within days.
6 May 2025other▲ Good
Preliminary testwork on low-boron Streams 2 and 3 showed gravity concentration lifting lithium grade 1.4-2 times and cutting mass 39-72%. A new Stream 1-focused mine plan and updated economics are due this month. Ioneer will take results to investors seeking a new equity partner.
5 May 2025director officer appointment● Neutral
Non-executive director Stephen Gardiner retired for personal reasons; Tim Woodall, with over 30 years in energy M&A and finance, joins as independent non-executive director. He takes over as Audit and Risk Committee chair.
15 Apr 2025quarterly activities report● Neutral
March quarter report recaps the US$996M DOE loan, the 45% resource increase and Sibanye's withdrawal. Goldman Sachs is engaged for a strategic partnering process to find a new equity partner. Cash fell to US$14.1M; the US$1.2M Stillwater loan was repaid.
15 Apr 2025quarterly activities report▼ Bad
Cash fell to US$14.1M from US$21.6M. Operating outflow US$1.1M, investing US$1.9M, financing US$4.5M, including the US$1.2M Stillwater loan repayment (resolving that thread) and US$3.3M of loan transaction costs. No financing facilities drawn.