Each one in plain English, with the numbers worked through for a shareholder.
25 Oct 2012asset acquisition disposition▲ GoodMajor
Ikwezi's 60%-owned subsidiary Bokamoso is granted a 3,998 ha prospecting right for the Assegai project in the Ermelo coalfield, with a conceptual 150Mt exploration target. Exploration is planned for Q3 2013; Ntendeka production is now aimed at early to mid-2013.
2012 annual report largely repeats known facts: A$30M IPO, Newcastle (Ntendeka) mining right granted February 2012, 221Mt resource. It describes about 1.25 Mtpa saleable coal, a 30-plus year mine life and the Phase 2 project now being called Dundee.
Statutory accounts for the year to 30 June 2012. Visible text covers only the contents, directors' biographies and the principal activity of coal exploration and development; no financial figures are readable in the truncated text.
June quarter: cash is A$12.131M (from A$24.5M at September 2011). Citing low thermal coal prices, production start is likely deferred from October 2012 to early 2013. A bank loan facility and the water licence remain unfinished.
Newcastle project renamed Ntendeka Colliery. Wash plant commissioning slips to mid-July 2012, and the company says licence approvals are taking longer than expected, with the water licence still pending. The 170,000t/month plant is now being bought directly rather than outsourced.
Stefanutti Stocks Mining Services is appointed opencast mining contractor for Newcastle, resolving the contract negotiations noted earlier. Mining is now expected to start mid-2012, with the wash plant still due for commissioning in Q2 2012.
Half-year to December 2011: net loss $580,977, operating outflow $1.93 million, plus $4.7 million on plant and equipment and $1.5 million on exploration. Q2 2012 production still targeted, but the company warns any delay in water licence approvals would delay production.
Newcastle JORC resource rises to 221 million tons from 209 million, with a first reserve of 14 million tons. Opencast mining is expected from Q2 2012, with a 2 Mtpa ROM wash plant and a ramp-up to 4 Mtpa ROM in Q4 2013.
The Department of Mineral Resources grants the Newcastle mining right, resolving the long-awaited approval. Q2 2012 production is still targeted; the water use licence is still pending, expected early Q2 2012.
February 2012 investor presentation covering the Newcastle, Newcastle Phase 2, Waterberg and Acorn projects. Visible text is only disclaimers, describing the projects as pre-feasibility stage; the rest is truncated.
Ikwezi signs a Transport Agreement with Transnet Freight Rail for 1.5 mtpa of Newcastle rail capacity, renewable annually. The mining right has slipped to expected January 2012 (it was earlier due 'shortly'), though Q2 2012 production is still targeted.
First annual report repeats known facts: $30 million IPO, Newcastle (70%) targeted for production in 2012, Waterberg exploration from Q1 2012. Adds that Transnet and port discussions are advanced, and BEE holdings are 30% in Newcastle and 40% in Phase 2 and Acorn.
Ikwezi agrees to acquire 70% of two Waterberg coalfield prospecting rights (5,714 ha, Limpopo). It sets a conceptual, unverified exploration target of 2–4 billion tonnes, with exploration planned for early 2012. Newcastle production is still targeted for early/mid 2012.
Statutory accounts for the period to 30 June 2011 show a net loss of $366,826 and operating cash outflow of $527,323, before the $30 million IPO closed in July 2011. Newcastle mining right application was lodged in December 2010.
Initial director interest notices. Hewetson and Pile each have an indirect interest in Belvedere's 170,000,000 shares, and Pile and Anthony hold 2,000,000 options each at $0.30 expiring December 2012. Fourth notice truncated.
Roger Rees will join the board as an independent non-executive director from 22 July 2011. He was Finance Director of Murray & Roberts for over 10 years. This starts the board independence the listing governance statement promised.
Post-listing investor presentation on the Newcastle, Newcastle Phase 2 and Acorn coal projects. The visible text is mostly disclaimers and describes the projects as pre-feasibility stage; the remainder is truncated.
Administrative notice listing the documents released before quotation (shareholder distribution, top 20 holders, escrow, governance, trading policy, option plan). No new substance.
Confirms the IPO closed: all shares allotted 12 July 2011, cleared funds received and applications accepted in full. The offer was 150,000,000 shares at $0.20 for $30 million, with $1.93 million of costs. Options were issued to directors and Euroz.
What it means for a shareholder
150m new shares at A$0.200 to raise about A$30.0m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Corporate governance statement. The board has one non-executive and two executive directors, none independent, so it departs from several ASX recommendations. It plans to add two independent non-executive directors after listing.
ASX circular confirming quotation from 19 July 2011. It describes the company as a South African coal explorer and developer, and notes 169,950,000 shares and 5,000,000 options are escrowed for 24 months.
Securities trading policy restricting insider trading by directors, employees and contractors. Standard administrative document with no new business information.
30 June 2011capital raising announcement● NeutralMajor
Prospectus for Ikwezi Mining's IPO, underwritten by Euroz Securities, to list the Bermuda-incorporated South African coal explorer on ASX. Per later disclosure, the offer is 150,000,000 shares at 20 cents to raise $30 million. The prospectus calls the investment speculative.
What it means for a shareholder
150m new shares at A$0.200 to raise about A$30.0m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.