Stockle - the stock oracle

Ikwezi Mining Ltd

ASX:IKW
A$0.460Latest close held · delayed

Past year: ▼ 30%(44.5c – 1.70 AUD)

Market cap
A$1.87bn
Shares on issue
4.07bn
Story beats
44 since 2011
Last event
30 Dec 2022

History

Ikwezi raised A$30M to build a South African coal mine, waited seven years to mine its first coal, and delisted from the ASX in 2022 after a profitable year.

2011-2012: Listing and a slow start at Newcastle

Ikwezi Mining, a Bermuda-incorporated company exploring for coal in South Africa, listed on the ASX on 15 July 2011 after an IPO underwritten by Euroz Securities. The offer was 150,000,000 shares at 20 cents to raise $30 million. In September 2011 it agreed to acquire 70% of two Waterberg prospecting rights, setting an unverified exploration target of 2-4 billion tonnes.

The main project was Newcastle, where production was first targeted for early to mid 2012. The mining right slipped, then was granted in February 2012. A rail agreement with Transnet covered 1.5 million tonnes a year, and Stefanutti Stocks Mining Services became the mining contractor in April. The resource rose to 221 million tons with a first reserve of 14 million tons. But the water licence stayed pending, and the project, renamed Ntendeka Colliery, slipped again. By June 2012 cash was A$12.131M, down from A$24.5M nine months earlier, and the company deferred production to early 2013, citing low thermal coal prices.

2013-2014: Approvals arrive, money runs short

In January 2013 the Waterberg agreement lapsed because a required approval never came. The same month Ikwezi signed a three-year deal with Vitol to sell 3.96 million tonnes of coal, conditional on arranging funding within three months. The water licence was finally granted in March 2013, and resources rose to 294 million tonnes with reserves of 16 million.

Funding, however, never closed. By September 2013 cash was A$1.979M and production was pushed to 2014. In January 2014 the company agreed to sell part of its Alleen No. 2 mining right for ZAR8M (A$0.84M). By March 2014 cash was A$1.149M and the company was reviewing strategic options. Chairman Simon Hewetson resigned in June 2014, and David Pile became Executive Chairman.

2014-2016: A small rights issue and a redesign

In December 2014 came the first raising since the IPO: a 2-for-1 rights issue at A$0.006 a share, fully underwritten by Azure Projects, to raise up to A$4.065M. Shareholders took up only about half, A$2.015M, and Azure took the remaining shortfall shares. Shares on issue rose from 338,750,000 at the end of 2013 to 1,016,250,000 a year later.

In 2015 two directors joined the board. The company decided not to renew its Dundee prospecting right and began redesigning Ntendeka for a phased, lower-cost start. By mid-2016 it was targeting run-of-mine coal (coal sent on without washing) from the Central opencast, with mining aimed at early 2017. The Acorn prospecting right lapsed. A December 2016 presentation said the mine plan was being remodelled for lower prices and that no reserves were currently recorded, contradicting the earlier 16 million tonnes. The record for 2017 is quiet.

2018-2019: First coal

By December 2017 cash was A$0.599M. Ikwezi said it would not renew the Assegai right, leaving Ntendeka as its focus. Legal steps against three resisting families were well advanced, and by April 2018 house relocation in the Central Mini Pit was complete. CML Melger Mining was selected and signed as mining contractor. Short-term funding came from related party Osho SA Coal, in loans that reached ZAR30M (about A$3M) by September 2018.

The project was now called the Newcastle Project, with mining at Kliprand Colliery. A box cut was completed and first coal was mined in September 2018. A 3-for-1 entitlement issue at A$0.002 a share, underwritten by Finevest Investments, sought up to A$6,097,500. Acceptances raised A$2.083M, with Finevest taking the rest. Shares on issue rose to 4,065,000,000. The Osho loans, A$4.352M, were repaid from the proceeds, and coal sales began in the March 2019 quarter. In July 2019 CML Melger terminated its contract, and Stefanutti Stocks took over mining.

2020-2021: Crisis and consolidation

In the March 2020 quarter receipts collapsed to A$0.568M from A$4.36M, cash fell to A$0.091M and about 180,000 tons of coal sat unsold. Related party Zarbon Coal (formerly Osho) advanced about US$1.66M under a US$4.3M facility. In late May 2020 the chairman, two directors and the company secretary resigned, and ASX suspended the shares until enough directors were appointed. Mining restarted in June with a new contractor. Nitin Agrawal became Chairman in September.

Ikwezi was also in arbitration with Stefanutti Stocks, claiming about A$10.6M for under-delivery against a counterclaim of about A$3.3M. In December 2020 it proposed a 100-for-1 share consolidation, cutting about 4.065 billion shares to about 40.65 million. The record is then quiet until 2022, and the arbitration outcome is not captured.

2022: Profit and delisting

For the year to 30 June 2022 Ikwezi reported a net profit of A$15.86M, against a prior-year loss of A$1.51M, with operating cash inflow of A$10.7M, helped by selling more washed coal. The Zarbon Coal loan was fully repaid, leaving no long-term external debt.

In October 2022 the company applied to leave the ASX, citing very low liquidity, no Australian operations, savings of about A$250,000 a year and negative perceptions of thermal coal. A buy-back was planned, though its terms were not reported. Shares were suspended on 28 December, and on 30 December 2022 ASX removed Ikwezi from the official list after shareholders resolved to delist. It then held 70% of the Newcastle Project, with 40,649,974 shares and cash of A$10.111M at September 2022, including A$8.534M of deferred payments.

Written from the 44 story beats below (2011 to 30 Dec 2022), which come from the company's own announcements and filings.

Beat by beat

The events that changed the company's story, in plain English, each written against everything known about the company at the time. The dot shows whether it was good, bad or neutral for shareholders.

shares on issue market cap (log scale)

20224.07bn shares · A$1.87bn market cap

  1. 30 Dec

    ASX removed Ikwezi from the official list at close of trading on 30 December 2022, at the company's request, after shareholders resolved to delist. This completes the delisting applied for on 25 October 2022.

    registration revoked

    4.07bn shA$1.87bn
  2. 28 Dec

    ASX suspended Ikwezi shares at the close of trading on 28 December 2022, at the company's request, pending removal from the official list. Delisting follows.

    registration revoked

    4.07bn shA$1.87bn
  3. 25 Oct

    Ikwezi applied to be removed from the ASX, citing very low liquidity, no Australian operations, costs (about A$250,000 a year saved) and negative thermal coal perception. A buy-back for shareholders is planned. Shareholders exit a listing they have found practically illiquid.

    asset acquisition disposition

    4.07bn shA$6.00bn
  4. 30 Sept

    Full-year accounts to 30 June 2022: net profit A$15.86M (prior-year loss A$1.51M), operating cash inflow A$10.7M, helped by selling more washed coal rather than discounted run-of-mine coal. The Zarbon Coal loan was fully repaid, leaving no long-term external debt.

    annual report

    4.07bn shA$6.00bn

20204.07bn shares · A$1.63bn market cap

  1. 30 Dec

    Ikwezi plans a 100-for-1 share consolidation, cutting about 4.065bn shares to about 40.65M, subject to shareholder approval on 7 January 2021. Post-consolidation trading begins 11 January on a deferred settlement basis.

    security holder rights change

    4.07bn shA$1.63bn
  2. 30 Sept

    Arbitration with former contractor Stefanutti Stocks is under way, with a hearing expected in Q1 2021. Ikwezi claims about A$10.6M for under-delivery; Stefanutti counterclaims about A$3.3M over the performance guarantee call. This follows the earlier claim lodged.

    regulatory community update

    4.07bn shA$1.63bn
  3. 7 Sept

    Nitin Agrawal appointed Chairman. Auditor Charter Financial Services resigned and Eyesure Financial Services was appointed for the year ended 30 June 2020, to be confirmed at the AGM.

    director officer appointment

    4.07bn shA$2.03bn
  4. 15 June

    Mining restarted at the Central Mini Pit after a pause, using a new mining contractor. Stefanutti Stocks is still in contractual process over missing the planned production schedule. This continues the contractor problems flagged in earlier quarterlies.

    production update

    4.07bn shA$407m
  5. 29 May

    ASX suspended Ikwezi's shares on 29 May 2020 until it appoints enough directors to meet the Corporations Act minimum. This follows the board resignations the day before.

    listing compliance notice

    4.07bn shA$407m
  6. 28 May

    Chairman David Pile and directors Ranaldo Anthony and Alok Joshi resigned on 28 May 2020 to focus on other business interests, and company secretary Alexander Neuling also resigned. Tushar Agrawal is the only remaining named director; replacements are to be announced.

    director officer appointment

    4.07bn shA$407m
  7. 1 May

    March 2020 quarter: receipts collapsed to A$0.568M (from A$4.36M) and cash fell to A$0.091M, with about 180,000 tons of unsold coal. Related party Zarbon Coal (formerly Osho) advanced about US$1.66M under a US$4.3M facility at 5%, repayable by 31 Dec 2020. API4 fell to about US$50.

    quarterly activities report

    4.07bn shA$407m

20194.07bn shares · A$407m market cap

  1. 31 July

    Mining contractor CML Melger, engaged in April 2018, terminated its contract at its own request effective 31 July 2019. Stefanutti Stocks Mining Services takes over mining at the Central Mini Pit from 1 August 2019.

    contract award

    4.07bn shA$407m
  2. 1 May

    March 2019 quarter: coal sales began, with receipts of A$1.688M. Osho loans were repaid in full (A$4.352M) from the raising proceeds, resolving that thread. Cash fell to A$0.46M and API4 slid to about US$71. Freddie Strydom appointed COO of the South African subsidiary.

    quarterly activities report

    4.07bn shA$407m

20184.07bn shares · A$407m market cap

  1. 12 Dec

    Entitlement issue closed with acceptances for 1.04bn shares raising A$2.083M. The remaining 2.007bn shares (about A$4.01M) fall to underwriter Finevest to take up, so the full A$6.1M is expected.

    capital raising announcement

    4.07bn shA$407m
  2. 21 Nov

    Prospectus for a 3-for-1 renounceable entitlement issue at A$0.002 per share, raising up to A$6,097,500. Fully underwritten by Finevest Investments. This is the long-planned ~A$6M raising, now launched at a very low price.

    capital raising announcement

    4.07bn shA$915m
  3. 28 Sept

    Box cut completed at Kliprand and first coal mined, the first production after years of delays. Initial sales are crushed run-of-mine coal on a free-on-truck basis. A third Osho loan (ZAR10.5M) brings Osho borrowings to ZAR30M (about A$3M); the ~A$6M entitlement issue is still pending.

    production update

    1.02bn shA$305m
  4. 31 July

    Project now called Newcastle Project; mining starts at Kliprand Colliery, with coal extraction expected late in the September 2018 quarter. Plans a roughly A$6M renounceable entitlement issue, with a shareholder in principle willing to underwrite it. A second ZAR10M Osho loan bridges until then.

    capital raising announcement

    1.02bn shA$229m
  5. 30 Apr

    Mining contract with CML concluded, resolving the contractor thread. Also a ZAR9.5M (about A$1M) unsecured loan from related party Osho SA Coal at 10% a year, repayable by 31 August 2019, as short-term funding ahead of the larger raising.

    debt financing

    1.02bn shA$305m
  6. 17 Apr

    CML Melger Mining selected as mining contractor for Ntendeka opencast; terms still being finalised. House relocation in the Central Mini Pit is complete, resolving the long-running resistance thread. About US$5M (A$6.5M) funding needed, with in-principle support from the principal shareholder.

    contract award

    1.02bn shA$305m
  7. 31 Jan

    December 2017 quarter: cash A$0.599M, and fund raising options have been identified, to be aligned with the mining start. Legal steps on the 3 resisting families are well advanced, and the Assegai prospecting right will not be renewed, leaving Ntendeka as the focus.

    quarterly activities report

    1.02bn shA$305m

20161.02bn shares · A$457m market cap

  1. 22 Dec

    Re-release of the AGM presentation to add a resource breakdown for Ntendeka's 294Mt: 50Mt Measured, 36Mt Indicated, 208Mt Inferred. It also states the mine plan is being remodelled for lower coal prices and that no Reserves are currently recorded, contradicting the earlier 16Mt reserve.

    resource reserve update

    1.02bn shA$457m
  2. 29 July

    June 2016 quarter: cash A$2.091M. With API4 near US$63, Ikwezi now targets run-of-mine coal from Ntendeka's Central opencast, with mining targeted for early 2017 once a contractor is chosen. The Acorn prospecting right was allowed to lapse.

    quarterly activities report

    1.02bn shA$229m

20151.02bn shares · A$229m market cap

  1. 2 Nov

    September 2015 quarter: cash A$2.923M. Ikwezi will not renew its Dundee prospecting right (previously 60% held), focusing on Ntendeka, which is being redesigned for a phased, lower-cost start. Northern drilling results are analysed; start remains delayed by weak margins.

    quarterly activities report

    1.02bn shA$229m
  2. 29 May

    Tushar Agrawal and Alok Joshi join the board; Alex Neuling resigns as director but stays company secretary. Belvedere (382.97M shares) agreed with Azure's shareholders (Azure holds 341.7M) to influence Azure's votes, giving a deemed 724.7M-share interest.

    director officer appointment

    1.02bn shA$305m
  3. 21 Jan

    Rights issue closed with acceptances for 335.8M shares raising A$2.015M, about half the maximum. The remaining 341.7M shortfall shares go to underwriter Azure Projects, which is how the full A$4.065M is expected to be met.

    capital raising announcement

    1.02bn shA$534m

20141.02bn shares · A$690m market cap

  1. 22 Dec

    First capital raising since the A$30M IPO: a 2-for-1 renounceable rights issue at A$0.006 per share, up to 667.5M shares to raise up to A$4.065M, fully underwritten by Azure Projects. Funds go to working capital and an initial box cut at Ntendeka to start mining run-of-mine coal.

    capital raising announcement

    1.02bn shA$690m
  2. 30 June

    Chairman Simon Hewetson resigns effective 27 June 2014 to focus on other business interests; MD David Pile becomes Executive Chairman, and company secretary Alex Neuling joins the board. A new non-executive director is planned. Follows the death of Roger Rees.

    director officer appointment

    339m shA$299m
  3. 30 Apr

    March quarter: cash is A$1.149M. The finance facility is progressing, but the company is now reviewing strategic options, including asset or corporate-level transactions, though bringing Ntendeka into production remains the preferred path. Production target is now 'during 2014'.

    quarterly activities report

    339m shA$230m
  4. 21 Jan

    Ikwezi agrees to sell part of its Alleen No. 2 mining right, near Dundee, to Forbes Coal's subsidiary for ZAR8M (A$0.84M), plus ZAR10/t above a production threshold. Needs ministerial consent by 30 April 2014; Ntendeka reserves and resources are unaffected.

    asset acquisition disposition

    339m shA$460m

2013339m shares · A$575m market cap

  1. 31 Oct

    September quarter: cash is A$1.979M. Production is now targeted for early to mid-2014, subject to financing with banks or off-take partners and stable coal markets, pushing back the earlier Q3 2013 target. Coal prices have recovered to about US$85/t from lows near US$70.

    quarterly activities report

    339m shA$575m
  2. 17 May

    Ntendeka resources rise from 221Mt to 294Mt and reserves from 14Mt to 16Mt, after drilling of 470 boreholes in total. Reserves were optimised for current low export prices, with a significant portion removed that could be reinstated if prices improve.

    resource reserve update

  3. 25 Mar

    Ntendeka Colliery is granted its Integrated Water Use Licence, resolving the long-pending approval that blocked construction and mining. Remaining construction and mining start now depend on finalising the finance facility, which the company says is progressing well.

    regulatory community update

  4. 23 Jan

    Ikwezi signs a three-year off-take deal with Vitol to sell 3.96Mt of coal, the full scheduled first-stage Ntendeka output, at fixed and API4-linked prices. It is conditional on Ikwezi arranging a funding facility within three months.

    material agreement

  5. 22 Jan

    The Waterberg acquisition agreement (70% of 5,714 ha, agreed September 2011) has lapsed because the Section 11 approval was never received. The company may revive it or look elsewhere, and says its focus is KwaZulu-Natal, Gauteng and Mpumalanga projects.

    asset acquisition disposition

2012

  1. 25 Oct

    Ikwezi's 60%-owned subsidiary Bokamoso is granted a 3,998 ha prospecting right for the Assegai project in the Ermelo coalfield, with a conceptual 150Mt exploration target. Exploration is planned for Q3 2013; Ntendeka production is now aimed at early to mid-2013.

    asset acquisition disposition

  2. 31 July

    June quarter: cash is A$12.131M (from A$24.5M at September 2011). Citing low thermal coal prices, production start is likely deferred from October 2012 to early 2013. A bank loan facility and the water licence remain unfinished.

    quarterly activities report

  3. 19 June

    Newcastle project renamed Ntendeka Colliery. Wash plant commissioning slips to mid-July 2012, and the company says licence approvals are taking longer than expected, with the water licence still pending. The 170,000t/month plant is now being bought directly rather than outsourced.

    production update

  4. 4 Apr

    Stefanutti Stocks Mining Services is appointed opencast mining contractor for Newcastle, resolving the contract negotiations noted earlier. Mining is now expected to start mid-2012, with the wash plant still due for commissioning in Q2 2012.

    contract award

  5. 7 Mar

    Newcastle JORC resource rises to 221 million tons from 209 million, with a first reserve of 14 million tons. Opencast mining is expected from Q2 2012, with a 2 Mtpa ROM wash plant and a ramp-up to 4 Mtpa ROM in Q4 2013.

    resource reserve update

  6. 27 Feb

    The Department of Mineral Resources grants the Newcastle mining right, resolving the long-awaited approval. Q2 2012 production is still targeted; the water use licence is still pending, expected early Q2 2012.

    regulatory community update

2011

  1. 19 Dec

    Ikwezi signs a Transport Agreement with Transnet Freight Rail for 1.5 mtpa of Newcastle rail capacity, renewable annually. The mining right has slipped to expected January 2012 (it was earlier due 'shortly'), though Q2 2012 production is still targeted.

    contract award

  2. 30 Sept

    Ikwezi agrees to acquire 70% of two Waterberg coalfield prospecting rights (5,714 ha, Limpopo). It sets a conceptual, unverified exploration target of 2–4 billion tonnes, with exploration planned for early 2012. Newcastle production is still targeted for early/mid 2012.

    asset acquisition disposition

  3. 15 July

    Ikwezi is admitted to the ASX Official List on 15 July 2011, with 168,800,000 shares at 20 cents to begin quotation on 19 July 2011 under code IKW.

    other

  4. 30 June

    Prospectus for Ikwezi Mining's IPO, underwritten by Euroz Securities, to list the Bermuda-incorporated South African coal explorer on ASX. Per later disclosure, the offer is 150,000,000 shares at 20 cents to raise $30 million. The prospectus calls the investment speculative.

    capital raising announcement