31 Oct 2016annual report● Neutral
Appendix 4G corporate governance checklist lodged with the annual report, pointing to the governance statement on page 32. Administrative compliance filing with no new business information.
Each one in plain English, with the numbers worked through for a shareholder.
31 Oct 2016annual report● Neutral
Appendix 4G corporate governance checklist lodged with the annual report, pointing to the governance statement on page 32. Administrative compliance filing with no new business information.
5 Oct 2016production update▲ GoodMajor
Portia passed 10,000oz of gold produced (5,000oz attributable to Havilah), about half the 10,000oz hedge book at A$1,618/oz. Records of 34kg daily concentrate and a 49kg pour were set despite rain halting mining; drilling to resume and PACE-funded exploration ($200,000 grant) is being prepared.
27 Sept 2016investor presentation▲ Good
Roadshow presentation repeating Portia progress: about 10,000oz produced on a 100% basis, debt reduced to $2 million after 31 July, and market cap $128m on 22 September (versus $70m in July). Mostly known facts.
29 Aug 2016capital raising announcement▲ GoodMajor
A Melbourne institution bought 2.2 million listed options from Managing Director Chris Giles and exercised them, paying Havilah $0.7 million. Shares on issue rise to about 171 million. Giles says the sale is not a lack of confidence.
26 Aug 2016drilling result▲ GoodMajor
Further Portia southern-extension drilling returned 30.5m at 39.3 g/t Au (washed samples; conventional assay gave 10.4 g/t). Havilah is seeking approval for a 120m south wall cutback to add about six months of mine life, and will drill the eastern down-dip extensions.
2 Aug 2016drilling result▲ GoodMajor
Southern-extension drilling at Portia hit 6m at 53.6 g/t Au and 13m at 8.4 g/t in bedrock, and pit-floor veining suggests a larger system. Management says this could extend mine life beyond the current six months, but it needs new approvals and a redesigned mine plan.
1 Aug 2016debt financing▲ Good
Havilah made its first $0.5 million repayment on the Investec loan, five months before it was due, leaving $3.5 million owing of the $4 million drawn from the $6 million facility. More repayments are planned in August from bullion being refined.
27 July 2016investor presentation● Neutral
Re-release of the 22 July Noosa presentation as an updated version, adding a note that the assumptions behind earlier forecasts continue to apply. Administrative re-issue with no new information.
22 July 2016investor presentation● Neutral
Noosa conference presentation repeating Portia progress, now stating more than $5 million of gold produced to date. Capital structure figures (cash $0.3m, debt $2.8m at 30 Apr) are unchanged; no new results.
21 July 2016production update▲ GoodMajor
Portia poured its largest single batch yet: four bars of about 40kg, over 90% pure, worth more than about $2 million at current prices. Mining has reached the high-grade zone, and 14,000t of high-grade ore is stockpiled, so rates are expected to hold.
7 July 2016investor presentation● Neutral
Sydney Mining Club presentation largely repeating Portia progress: $1 million gold revenue received, mining now in the main ore zone in the pit floor, and the target of 34,000t copper and 100,000oz gold a year. No new results.
23 June 2016investor presentation▲ Good
Updated presentation for the Exchange SA conference. Headlines the first $1 million of gold sales attributable to Havilah, reported two months ahead of schedule, building on the first ~$266,000 sale in early June. Cash $0.3m, debt $2.8m at 30 Apr 2016.
15 June 2016security holder rights change● Neutral
The unmarketable parcels sale completed, selling 339,046 shares at $0.4115 each, excluding costs. Shareholder numbers fell from 3,035 to 2,495; shares on issue are unchanged. Aims to reduce administration costs.
7 June 2016production update▲ GoodMajor
First Portia gold sales were finalised, with Havilah receiving about $266,000 for roughly 165oz, its 50% share under the CMC revenue-share deal. Described as the company's first mining income; further shipments are with the refiner.
12 May 2016investor presentation● Neutral
Presentation on a 'different approach' to the Maldorky iron project, restating 147Mt at 30.1% Fe and a three-stage pit. Highlights a magnetite/gravity concentrate at 65.2% Fe, and says a port and rail link remain the major challenges. Mining lease application is with DSD.
10 May 2016production update▲ GoodMajor
Havilah poured its first gold bar at Portia, just over 13 months after mining started. It was a trial pour from commissioning concentrate of variable grade, to test the furnace and fluxing. First production in the company's history.
9 May 2016production update▲ Good
Portia mining is to resume after the geotechnical review found it can safely proceed to about 35m below surface with minimal design change. Resolves the pit wall slip suspension. First gold pour planned this week.
2 May 2016production update● NeutralMajor
The Portia plant is now processing high-grade ore, with several weeks of stockpile available. A pit wall slip where ore was previously mined led contractor CMC to temporarily suspend mining for geotechnical review; Havilah says gold production is not affected.
21 Apr 2016production update▲ GoodMajor
The Portia gravity plant was completed two and a half months early and on budget, and began commissioning on low-grade ore on 20 April. Bedrock drilling beneath the interim sub-pit also showed significant gold, though grade and tonnage are unknown.
20 Apr 2016investor presentation● Neutral
Presentation at a South Australian investment conference stating gold plant construction is complete, commissioning on low-grade ore, with first ore through the plant on 20 April 2016. Largely recaps Portia milestones already announced.
14 Apr 2016half year report● Neutral
Interim financial report for the half-year to 31 January 2016. Text provided is only the cover, contents and directors' report opening, noting the accelerated Portia mining plan; no financial figures are visible in the excerpt.
31 Mar 2016production update▲ Good
The high-grade north pod at Portia has been fully mined from the interim sub-pit, giving roughly 10,000t of high-grade ore stockpiled plus more lower-grade ore. Water inflows were modest. Plant start-up still expected mid-April; ore across the rest of the pit within about two months.
18 Mar 2016production update▲ GoodMajor
Systematic mining of Portia gold ore has begun, 3.5 months ahead of the original schedule, following the revised mine plan. Several thousand tonnes of high-grade ore are expected to be stockpiled this week; the processing plant is expected to be commissioned by mid-April.
15 Mar 2016security holder rights change● Neutral
Havilah set up a share sale facility for holders of parcels under $500 (1,370 shares at $0.365). 841 of 3,035 holders qualify and the company pays sale costs to cut administration. Holders can opt out by 28 April 2016.
15 Mar 2016investor presentation● Neutral
Melbourne Mining Club presentation by the Managing Director, reporting first Portia gold ore mined and stockpiled. Shows cash $0.8m and debt $1.0m at 31 Jan 2016, market cap $64m, and prospect of >$40m gross cash flow to Havilah in 2016. Otherwise repeats known facts.
11 Mar 2016capital raising announcement● NeutralMajor
Havilah received about $0.5m for 300oz of Portia gold sold forward at A$1,691/oz to a long-time shareholder, on top of the 10,000oz hedged at A$1,618. The prepayment is secured by a contingent obligation to issue about 1.6 million shares at 32.25 cents.
What it means for a shareholder
1.6m new shares at $0.3225 to raise about $500,000. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Create a free account to see this worked out for your own holding.
3 Mar 2016drilling result▲ Good
Five more North Portia holes included 32m at 3.95% copper and 1.45 g/t gold, Havilah's best combined intercept there, though inside the existing resource so it does not extend it. Initial flotation tests recovered up to 90% of gold, while simple gravity recoveries were sub-optimal.
3 Feb 2016drilling result▲ Good
First three North Portia infill holes returned a best 30m at 1.53% copper and 0.56 g/t gold, supporting continuity of the existing 11.3Mt resource. They are the start of a 15-hole program to lift confidence in the oxidised ore. Metallurgical testing is under way.
27 Jan 2016production update▲ GoodMajor
A revised mine plan using an interim sub-pit on the high-grade northern zone targets first Portia gold ore in early April 2016, three months ahead of the July target, with about 600,000 m3 of overburden left to remove. The Investec $6m loan is still undrawn. The plant build must now be compressed.
23 Dec 2015production update● Neutral
Portia moved 403,000 m3 of overburden in November, lower than prior months mainly due to heavy rain, with the pit 17m above the gold zone. Plant parts will be assembled on site in January-February 2016, and North Portia drilling has started. Pit redesign to reach ore earlier is being considered.