16 Aug 2017capital raising announcement● Neutral
109,241,756 shares allotted under the rights issue and holding statements sent. Administrative confirmation of the result announced on 14 August.
Each one in plain English, with the numbers worked through for a shareholder.
16 Aug 2017capital raising announcement● Neutral
109,241,756 shares allotted under the rights issue and holding statements sent. Administrative confirmation of the result announced on 14 August.
16 Aug 2017security holder rights change● Neutral
Exercise price of the 35m unlisted options expiring 31 October 2019 adjusted from $0.04 to $0.0398 following the rights issue. Routine formula adjustment.
14 Aug 2017capital raising announcement● NeutralMajor
Rights issue closed raising $2,184,835 at $0.02 (applications for 109.2m shares), about half the $4.0m maximum. Chairman, CEO and Southern Cross took up full entitlements. A shortfall of 91.0m shares may be placed to investors within 3 months.
2 Aug 2017investor presentation● Neutral
Updated July 2017 corporate presentation, changing slides 8 and 9. The Gold Links notice says these remove targeted tonnages and grades and revise cashflow timing. Production start is still shown as July 2017 on the program slide.
2 Aug 2017drilling progress report● Neutral
Portal (the 'Reynolds Adit') at Upper Gold Links completed and about 10m of ramp developed; the 2150 vein is expected 30-35m from the portal. CEO says work is within budget. Slides are being revised to remove targeted tonnages and grades.
31 July 2017capital raising announcement● Neutral
Offer document and forms for the 1-for-2 rights issue sent to shareholders: up to 200.2m shares at $0.02 to raise up to about $4.0m, closing 9 August 2017. Not underwritten, so the full amount may not be raised. Repeats known terms.
What it means for a shareholder
200m new shares at $0.020 to raise about $4.0m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Create a free account to see this worked out for your own holding.
31 July 2017capital raising announcement● Neutral
Letter to shareholders with registered addresses outside Australia and New Zealand, telling them they cannot take part in the rights issue and get no payment for their entitlements. Administrative notice with no new information.
24 July 2017capital raising announcement● Neutral
Shareholder letter for the rights issue: 1 share for every 2 held at $0.02, up to about $4.0m. Record date 26 July, closing 9 August 2017. Not underwritten, so the full amount may not be raised. Repeats the 21 July announcement.
24 July 2017capital raising announcement● Neutral
Notice to option holders on the rights issue: options carry no entitlement unless exercised before the 26 July record date. Otherwise the exercise price may be adjusted after closing. Administrative notice repeating known terms.
21 July 2017capital raising announcement● NeutralMajor
1-for-2 non-renounceable rights issue of up to 200.2m shares at $0.02 to raise up to about $4.0m, not underwritten. Funds are for working capital including the Colorado gold project. Chairman Johnson (11.85%) and Southern Cross (39.95%) are expected to take up their full entitlements.
What it means for a shareholder
200m new shares at $0.020 to raise about $4.0m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Create a free account to see this worked out for your own holding.
20 July 2017asset acquisition disposition▼ BadMajor
Dateline relinquishes all five Mt Augustus copper exploration licences in Western Australia. The $910,639 carrying value will be fully expensed in the year to 30 June 2017. Ends the company's last Australian project.
20 July 2017quarterly activities report● NeutralMajor
June 2017 quarter: mining contractor mobilised and development started at Upper Gold Links; Hazen outlined a plan to lift Lucky Strike Mill capacity to 180tpd. Dateline is seeking a party to develop Udu, using PCF Capital, and has relinquished Mt Augustus.
27 June 2017investor presentation● Neutral
Updated version of the June 2017 corporate presentation, released a day after the original. Content is essentially the same, with minor wording changes to the targets and slide text. No new business information.
26 June 2017investor presentation● Neutral
June 2017 corporate presentation repeating the Gold Links plan: production from July 2017, modern exploration from September 2017, and a JORC resource targeted. Payment terms restated, including Lucky Strike US$4m instalments from April 2018. No new information apparent.
26 June 2017drilling result▲ GoodMajor
Four-hole, 440m diamond drilling at Gold Links intersected the 2150 vein in all holes, consistent with the earlier non-JORC interpretation. Best intercept was 0.5m at 10.02 g/t Au equivalent. Resolves the drilling thread; mining is still said to be on track for next month.
15 June 2017contract award▲ GoodMajor
Small Mine Development LLC appointed underground mining contractor at Gold Links after competitive bidding. Dateline targets small-scale production in early July 2017, with ore trucked about 50km to the Lucky Strike Mill. Follows the March sampling and tender process.
30 Mar 2017drilling result▲ GoodMajor
Channel sampling at Gold Links returned an average 22.75 g/t Au over 30m, with a best sample of 151 g/t Au. Dateline says this gives confidence to begin small-scale mining and has started tendering to contractors. Rock sampling, not a resource.
15 Mar 2017half year report● Neutral
Half-year to 31 Dec 2016: net loss $140,229, cash $687,461 and net assets $6.32m (up from $3.80m at June), reflecting the Gunnison Gold deal and $0.01 share issues. Notes the $1.0m Gleneagles placement after balance date. Mostly confirms known events.
14 Feb 2017regulatory community update▲ GoodMajor
MSHA approval lets Gold Links site works and drilling begin; an eight-hole, 1,000m program is due from March 2017. Colorado DRMS approved two new mining permits with no objections. Cash is about $1.4m; Sooner Lucky Strike completion expected in about 60 days.
6 Feb 2017capital raising announcement● NeutralMajor
Placement of 33.3m shares at $0.03 to Gleneagles clients raises $1.0m for working capital, about 8.32% of the enlarged capital. It is issued under existing placement capacity, without shareholder approval.
What it means for a shareholder
33.3m new shares at $0.030 to raise about $1.0m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Create a free account to see this worked out for your own holding.
31 Jan 2017quarterly activities report▲ GoodMajor
December 2016 quarter: shareholders approved all Gunnison resolutions at the 30 November AGM. 265.9m shares were issued at $0.01, taking capital to 367.2m, and about $560k of debt was retired. A 167m surface hole at Gold Links awaits assays.
30 Nov 2016investor presentation● Neutral
AGM presentation on Gold Links, repeating the already-announced Colorado plan. It sets a target of more than 500,000oz resource and lifting mill capacity to 400tpd. The resource target is conceptual, not a defined resource.
29 Nov 2016asset acquisition disposition● NeutralMajor
Non-binding agreement to buy the Sooner Lucky Strike mine and 150-200tpd mill in Colorado, about 50km from Gold Links. Terms include 28.25m shares, US$125k cash and later payments including about US$9.5m in April 2022; completion targeted by April 2017, subject to due diligence.
10 Nov 2016other● Neutral
Corporate governance statement describing board roles and independence. Directors listed are Johnson, Hall and Baghdadi. Administrative policy document with no new business information.
19 Oct 2016capital raising announcement● NeutralMajor
Southern Cross (SXX) will take 100m Dateline shares at $0.01 for $1m, plus shares for about $400k debt owed to it, giving it about 43% of Dateline. Linked to Dateline taking over Gunnison Gold; subject to Dateline shareholder approval.
19 Oct 2016asset acquisition disposition● NeutralMajor
Dateline will take over Gunnison Gold from Southern Cross, giving it the Gold Links Mine and 50tpd mill in Colorado. This is a major strategy shift away from Fiji and WA. Terms: US$200k upfront, US$3m in two years and US$7m later, plus $250k fee and 25m options at $0.04. Needs shareholder approval.
10 Oct 2016other● Neutral
9,999,774 shares issued in the Golden Phoenix deal will be released from voluntary escrow on 16 October 2016. These shares could now be sold, which is a potential supply overhang (inference).
27 Sept 2016admin correction● Neutral
Appendix 4G corporate governance checklist for the year to 30 June 2016, lodged with the annual report. Administrative filing with no new business information.
26 Sept 2016annual report● Neutral
Annual report for year to 30 June 2016. Readable text covers corporate details and director information only; no financial results visible. Board is Johnson, Baghdadi and Hall, following Niumataiwalu's death in December 2015.
15 Mar 2016half year report● Neutral
Half-year to 31 December 2015: cash $157,597 (up from $45,907 at June) and net assets $4.12m (from $3.35m). Auditor is now HLB Mann Judd. Udu and Mt Augustus are the focus projects; drilling not mentioned as resumed.