27 Feb 2026resource reserve update● Neutral
Barrick filed a final technical report dated February 27, 2026 on the Kibali gold mine in the Democratic Republic of the Congo, with an effective date of December 31, 2025. It updates the March 2022 report, and the cautionary statement again names AngloGold Ashanti alongside Barrick and Kibali Goldmines SA. The reserve, resource and economic figures are cut off in the text shown, so no change can be stated, and the ownership split is not shown.
Barrick filed a technical report dated February 27, 2026 on the Pueblo Viejo mine in the Dominican Republic, with an effective date of December 31, 2025. It updates the March 2023 report and again refers to the process plant extension and the new Naranjo tailings storage facility, and names Newmont alongside Barrick. The operating company is now named as Pueblo Viejo Dominicana Jersey 2 Limited (formerly Pueblo Viejo Dominicana Corporation). The reserve, resource and economic figures are cut off in the text shown, so no change can be stated, and the ownership split is not shown.
Barrick filed a technical report dated March 14, 2025 on the Carlin Complex in Eureka and Elko Counties, Nevada, with an effective date of December 31, 2024, prepared for Barrick. It updates the March 2020 Carlin report and covers the Nevada Gold Mines operation shared with Newmont. The reserve, resource and cost figures are cut off in the text shown, so no change can be stated.
Barrick filed a technical report dated February 19, 2025 on the Reko Diq Project in Balochistan, Pakistan, with an effective date of December 31, 2024. It is the formal technical report behind the Reko Diq feasibility study that the company said was due by end 2024, and its contents include reserve, capital cost and economic analysis sections. The reserve, cost and return figures are cut off in the text shown, so none can be stated here.
Barrick filed a technical report dated February 19, 2025 on the Lumwana Expansion Project in Zambia, with an effective date of December 31, 2024. It is the formal technical report behind the Lumwana Super Pit expansion study that the company said was due by end 2024, and its table of contents includes capital cost and economic analysis sections. The reserve, cost and return figures are cut off in the text shown, so none can be stated.
Barrick released its 2024 reserve and resource statement. Attributable gold reserves are 89 million ounces at 0.99 g/t, up from 77 million ounces at 1.65 g/t in 2023, led by 13 million ounces added at Reko Diq after its feasibility study was completed. Copper reserves rose to 18 million tonnes at 0.45% from 5.6 million tonnes, with the Lumwana Super Pit feasibility study adding 5.5 million tonnes and Reko Diq adding 7.3 million tonnes. This resolves the end-2024 Reko Diq and Lumwana feasibility study threads. The company says that before Reko Diq it replaced annual depletion for a fourth year running at a 4% higher grade. Measured and indicated gold resources stay at 180 million ounces, with inferred up to 41 million ounces. The release also says Long Canyon resources were removed because the site is planned to move into full closure during 2025, and that Barrick plans prefeasibility-study drilling at Fourmile from the end of Q1 2025.
Barrick filed a technical report dated March 15, 2024 on the Turquoise Ridge Complex in Humboldt County, Nevada, with an effective date of December 31, 2023. It updates the March 2020 report and covers the Nevada Gold Mines operation shared with Newmont. The reserve, resource and economic figures are cut off in the text shown, so no change can be stated.
Barrick released its 2023 reserve and resource statement. Attributable gold reserves are 77 million ounces at 1.65 g/t, up from 76 million ounces at 1.67 g/t in 2022, which the company calls a third straight year of growth beyond depletion (5.0 million ounces added before depletion). Copper reserves are 5.6 million tonnes at 0.39%, with Lumwana drilling adding 330 thousand tonnes. Measured and indicated gold resources are flat at 180 million ounces, inferred is 39 million ounces (down from 42), and the company says Reko Diq and the Lumwana Super Pit feasibility studies are on track for completion by end of 2024. A table in the release records a 2.2 million ounce reserve reduction in 2020 from the divestiture of Massawa effective March 4, 2020, which resolves the open Massawa development thread as a sale.
Barrick filed a technical report, dated March 17, 2023, on the Loulo-Gounkoto gold mine complex in Mali, with an effective date of December 31, 2022. Loulo-Gounkoto came with the 2019 Randgold merger. The forward-looking section flags risks including the rules on repatriating the complex's cash held in Mali and political developments in Mali. The reserve, resource and economic figures are cut off in the text shown, so none can be stated.
Barrick filed a technical report, dated March 17, 2023, on the Pueblo Viejo mine in the Dominican Republic, with an effective date of December 31, 2022. Its forward-looking section names Newmont Corporation alongside Barrick and refers to the process plant extension and the new Naranjo tailings storage facility, which ties to the 2022 reserve increase from Naranjo. The reserve and resource figures are cut off in the text shown, so none can be stated. The text shown does not state the ownership split.
Barrick released its 2022 reserve and resource statement. Attributable gold reserves are 76 million ounces at 1.67 g/t (at $1,300/oz), up from 69 million ounces at 1.71 g/t in 2021, with the company citing growth of 6.7 million ounces net of depletion, led by Pueblo Viejo (a new Naranjo tailings facility added 6.5 million ounces) and Africa & Middle East. Copper reserves are held at 12 billion pounds at 0.38%, and measured and indicated gold resources rose to 180 million ounces and copper resources to 44 billion pounds, helped by Reko Diq being brought back in after its reconstitution in December 2022 and a Lumwana Super Pit preliminary economic assessment. This continues the 2021 reserve growth and adds Reko Diq and the Lumwana expansion as new threads.
Barrick filed a technical report, dated March 18, 2022, on the Kibali gold mine in the Democratic Republic of the Congo, with resources and reserves as of December 31, 2021. Kibali came with the 2019 Randgold merger. The report's cautionary statement names AngloGold Ashanti Limited alongside Barrick and Kibali Goldmines SA, which indicates AngloGold is a party to the mine (the exact stake is not shown in the text). The reserve and resource figures are cut off in the text shown, so no change can be stated.
Barrick released its 2021 reserve and resource declaration. Attributable gold reserves are 69 million ounces at 1.71 g/t, up from 68 million ounces at 1.66 g/t in 2020. The company says it replaced 150% of its gold reserve depletion before acquisition and equity changes at South Arturo and Porgera. Growth was led by the Goldrush underground project (up 3.6 million ounces to 4.8 million ounces at 7.29 g/t), Turquoise Ridge (up 1.4 million ounces before depletion), Bulyanhulu Deep West (up 0.77 million ounces) and North Mara (up 1.1 million ounces). Attributable measured and indicated gold resources are 160 million ounces at 1.50 g/t, with 42 million ounces inferred. Copper reserves are 12 billion pounds at 0.38%. The release attributes resource declines to dispositions and equity changes mainly related to Lagunas Norte and Porgera. It continues the Nevada Gold Mines story and also shows that Lagunas Norte and Porgera have changed in the portfolio since the earlier context.
Barrick filed a technical report, dated March 25, 2020, on the Carlin Complex in Eureka and Elko Counties, Nevada, with an effective date of December 31, 2019. It is prepared for Barrick and Newmont by Nevada Gold Mines LLC, the operator named in the report. This is the first Carlin report in the history seen so far. The text shown contains only the author certificates and forward-looking statements, so no reserve or resource figures can be stated.
Barrick filed a technical report, dated March 25, 2020, on the Turquoise Ridge Complex in Nevada, with resources and reserves as of December 31, 2019. It is prepared for Barrick and Newmont by Nevada Gold Mines LLC, the operator named in the report, which is consistent with the Barrick-Newmont Nevada joint venture agreed in March 2019. It follows the March 2018 Turquoise Ridge report and again mentions the shaft-sinking project. The report now covers Turquoise Ridge Underground, Turquoise Ridge Surface and Vista Underground. The reserve and resource figures are cut off in the text shown, so no change can be stated.
Barrick filed a feasibility study technical report, dated July 23, 2019, on the Massawa gold project in Senegal, one of the projects that came with the Randgold merger. The contents list shows reserve, capital cost and economic analysis sections, including an alternate case at a $1,200/oz gold price. The actual reserve, cost and return figures are cut off in the text shown, so none can be stated.
Barrick filed an updated independent technical report, dated March 22, 2019, on the Cortez joint venture operations in Nevada, with resources and reserves as of December 31, 2018. It updates the March 2016 report. Its forward-looking section mentions a 'Deep South expansion' and the Barrick-Newmont Joint Venture. The reserve and resource figures are cut off in the text shown, so no change can be stated.
Barrick filed an updated independent technical report, dated March 22, 2019, on the Goldstrike mine in Nevada, with resources and reserves as of December 31, 2018. It updates the April 2017 report, and its forward-looking section mentions the Barrick-Newmont Joint Venture. The reserve and resource figures are cut off in the text shown, so no change from the 2017 report can be stated.
Barrick filed an updated independent technical report, dated March 19, 2018, on the Veladero mine in Argentina, with resources and reserves as of December 31, 2017. It follows the 2014 report (reserves of 186.6 million tonnes, 5.12 million ounces of gold). The report's forward-looking section names Shandong Gold alongside Barrick and refers to a proposed transition-period metal recovery initiative and a pit wall steepening initiative, both described as in early evaluation, and to possible further deformation of the South Waste Rock Facility. The text shown does not say what Shandong Gold's role is, and the reserve figures are cut off, so no change from 2014 can be stated.
Barrick filed an independent technical report, dated March 19, 2018, on the Turquoise Ridge joint venture gold mine in Humboldt County, Nevada, with resources and reserves as of December 31, 2017. This is the first Turquoise Ridge report in the history seen so far. The report mentions a 3rd Shaft Project and a shaft-sinking project that could improve performance and mine life; the reserve and resource figures, and Barrick's ownership share, are cut off in the text shown.
Barrick filed an updated independent technical report, dated March 19, 2018, on the Pueblo Viejo mine in the Dominican Republic, with resources and reserves as of December 31, 2017. It was prepared for Barrick and Goldcorp, consistent with the earlier 60%/40% split, and the forward-looking section refers to an expansion of the processing plant. The reserve and resource figures are cut off in the text shown, so no change from the 2014 report can be stated.
Barrick filed an updated independent technical report, dated April 25, 2017, on the Goldstrike mine in Nevada, with resources and reserves as of December 31, 2016. It follows the March 2012 Goldstrike report (open pit plan to 2025, underground reserves to 2020). The reserve and resource figures are cut off in the text shown, so no change can be stated.
Barrick filed an independent technical report, dated April 25, 2017, on the Hemlo mine (open pit and underground) in Ontario, Canada, with resources and reserves as of December 31, 2016. This is the first Hemlo report in the history seen so far. The report flags that Phase 6 of the open pit is still in early evaluation; the reserve and resource figures are cut off in the text shown.
Barrick filed an updated independent technical report, dated March 21, 2016, on the Cortez joint venture operations in Nevada, with resources and reserves as of December 31, 2015. It updates the March 2012 report; the report also mentions a Cortez Underground Expansion Project and other 'Value Realization Initiatives' that it says are still in early evaluation. The resource and reserve totals are cut off in the text shown, so no change from the 2012 report can be stated.
Barrick filed another updated technical report, dated March 21, 2016, on the Lagunas Norte mine in Peru, with resources and reserves as of December 31, 2015. It replaces the August 2015 report and again covers the Refractory Project, now called the Lagunas Norte Refractory Ore Mine Life Extension Project, which the report describes as in early evaluation. The reserve figures are cut off in the text shown, so no change from the prior report can be stated.
Barrick filed a new independent technical report, dated August 31, 2015, on the Lagunas Norte gold mine in Peru, with resources and reserves as of December 31, 2014. It updates the 2012 report and covers a Refractory Project (a possible extension to process harder ore) and 'Value Realization Initiatives' that the report says are still in early evaluation. The reserve and resource figures are cut off in the text shown, so no change from the 2012 figures can be stated.
Barrick filed an updated technical report, dated March 27, 2014, on the Lumwana copper mine in Zambia (the mine gained in the Equinox acquisition), with figures as of December 31, 2013. Reserves are now 538.8 million tonnes at 0.56% copper (about 6.62 billion pounds), up from 426.34 million tonnes at 0.52% in the 2012 report. The plan is to mine 537 million tonnes from 2014 to 2038, versus 2012 to 2032 before, with the 68,000 tonne-per-day plant unchanged. The text shown does not explain the increase.
Barrick filed an updated independent technical report, dated March 27, 2014, on the Pueblo Viejo mine in the Dominican Republic, with resources and reserves as of December 31, 2013. Barrick holds 60% and Goldcorp 40%. The report says commercial production was reached in January 2013, ramp-up to full production is expected in 2014, reserve mine life is 20 years, and the plant averaged 19,382 tonnes a day in December 2013 against a 24,000 design capacity. Measured and indicated resources (excluding reserves) are 15.0 million ounces of gold on a 100% basis. This updates the 2012 report, which gave an 18-year mine life; the reserve table is cut off in the text shown.
Barrick filed an updated independent technical report, dated March 27, 2014, on the Veladero mine in Argentina, replacing the 2012 report with figures as of December 31, 2013. Proven and probable reserves are now 186.6 million tonnes at 0.85 g/t gold (5.12 million ounces of gold), down from 436.5 million tonnes and 10.56 million ounces in the 2012 report. The mine is operated through the wholly owned subsidiary Minera Argentina Gold S.A., and mining is expected to average about 30 million tonnes a year for the next six years, versus the 2025 end date in the earlier report. The filing text shown does not explain the drop in reserves.
Barrick filed an independent technical report, dated March 16, 2012, on the Veladero gold and silver mine in San Juan Province, Argentina. At December 31, 2011, proven and probable reserves are 436.5 million tonnes at 0.75 g/t gold, containing 10.56 million ounces of gold and 197.7 million ounces of silver, with mining scheduled to conclude in 2025. Measured and indicated resources, excluding reserves, hold 462,000 ounces of gold. It is part of the same-day series of technical reports.