Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

31 Oct 2018quarterly activities report● Neutral

September 2018 quarter: no production. Donald spend $106k, Niafarang $105k. Donald feasibility update still 'shortly'; CMEC contract remains ended with other funding options considered. Niafarang start now targeted Q1 2019, slipping again. About 30,000t TiO2 feedstock acquired; plant commissioning has commenced.

Discuss in chat

1 Oct 2018annual report▼ Bad

Statutory FY18 accounts: net assets fell $2.85m to $99.8m, net loss $4.67m, no dividend. NTA is stated as 20.6cps, versus 19.4cps in the preliminary report. Donald water pipeline now expected shorter than the earlier 75km.

Discuss in chat

1 Oct 2018listing compliance notice▼ BadMajor

ASX paused trading in Astron securities pending a further announcement. No reason is given in the text.

Discuss in chat

25 Sept 2018regulatory community update● Neutral

Niafarang approvals are now complete, and equipment is shipping. Start-up awaits government resettlement of local landholders, so the earlier timeline has slipped with no new date. Astron plans a JORC 2012 reserve update.

Discuss in chat

31 Aug 2018annual report▼ Bad

Unaudited FY18 results: revenue up 163.9% to $5.01m, loss before tax $3.89m, loss after tax $4.67m. NTA fell 20.5% to 19.4cps. Operating cash flow positive $765k. Test pit stockpiled; initial zirconia sales.

Discuss in chat

31 July 2018quarterly activities report● Neutral

June 2018 quarter: no production. Donald spend $317k, Niafarang $69k. EL5472 also expired; CMEC contract ended. About 30,000t of low-grade TiO2 feedstock bought for the China plant, commissioning targeted Q3 2018. Niafarang start now second half 2018.

Discuss in chat

16 July 2018annual report● Neutral

Annual report for year to June 2017, released July 2018. Says Donald is financing-dependent after strategic funding milestones were missed. Niafarang production targeted mid-to-late Q4 2018. Carries no resource or reserve references because of delayed reporting.

Discuss in chat

16 July 2018other● Neutral

Appendix 4G corporate governance checklist lodged with the annual report. Administrative; no new company information.

Discuss in chat

3 July 2018material agreement termination▼ BadMajor

The CMEC EPC contract ended after the 30 June 2018 conditions-precedent date passed unmet. Astron says it continues talking to CMEC and considering other options, so Donald's funding route, pursued since October 2015, is now open.

Discuss in chat

27 Apr 2018quarterly activities report● Neutral

March 2018 quarter: no production. Donald spend $196k, Niafarang $562k. 1,000t test pit sample completed. Feasibility study still 'shortly'; CMEC deadline remains 30 June 2018.

Discuss in chat

27 Apr 2018contract award▲ GoodMajor

Astron signed a construction contract for a China plant and warehouse to make up to 150,000 tpa artificial rutile, initially from bought-in lower-grade feedstock. Donald development and execution is now expected in Q3 2018. A new downstream business step, no cost stated.

Discuss in chat

18 Apr 2018regulatory community update▲ Good

Donald completed a second test pit extraction, a 1,000t ore sample for geotechnical and metallurgical tests. Described as a step toward the final work plan submission and approval, and samples for offtake agreements. Final approval not yet obtained.

Discuss in chat

13 Mar 2018listing compliance notice▲ GoodMajor

ASX lifted the suspension from 14 March 2018 after Astron lodged its December 2017 half-year report, resolving the late-filing suspension.

Discuss in chat

1 Mar 2018listing compliance notice▼ BadMajor

ASX suspended Astron's shares from 1 March 2018 for failing to lodge its half-year report for the period to 31 December 2017 on time.

Discuss in chat

9 Feb 2018auditor change● Neutral

BDO Limited (Hong Kong), assisted by BDO East Coast, engaged as auditor, and Boardroom Corporate Services (HK) as company secretary. Future reports will follow Hong Kong Financial Reporting Standards.

Discuss in chat

31 Jan 2018quarterly activities report● Neutral

December 2017 quarter: no production. Donald spend $592k, Niafarang $910k. Feasibility study still 'shortly'; CMEC deadline now 30 June 2018. RL2006 merged into RL2003; EL5255 expired and was not renewed.

Discuss in chat

18 Dec 2017auditor change▼ Bad

Auditor Grant Thornton Australia resigned. Astron intends to appoint BDO East Coast Partnership, subject to formalities. No reason for the resignation is given in the text.

Discuss in chat

7 Dec 2017material agreement● NeutralMajor

CMEC EPC conditions-precedent deadline extended a third time, to 30 June 2018. Contract price amended to US$119.6m (plus about US$5.5m insurance and fees) as financing moves from seller's to buyer's credit; DMS's 15% contribution unchanged. Conditions still unmet.

Discuss in chat

1 Nov 2017quarterly activities report● Neutral

September 2017 quarter: no production. Donald spend $108k, Niafarang $499k. Feasibility study still 'shortly'; CMEC deadline remains 1 December 2017. Niafarang activity still targeted for Q1 2018; new Senegalese subsidiary incorporated.

Discuss in chat

2 Oct 2017annual report▼ Bad

Statutory FY17 accounts: net assets fell $3.07m to $102.7m; net loss $2.59m. Gambia legal fees were $135k. NTA 24.4cps. Donald export permit and test pit approvals listed; execution strategy uses a modular plant built via a Chinese fabrication yard.

Discuss in chat

1 Sept 2017annual report▼ Bad

Unaudited FY17 results: revenue up 305.9% to $1.90m, loss before tax $4.0m, NTA down 18.3% to 24.4cps. Operating cash outflow $3.2m. A further $1.73m of China land sale proceeds received after year end. Senegal licence obtained.

Discuss in chat

31 July 2017quarterly activities report● Neutral

June 2017 quarter: no production. Donald spend $317k, Niafarang $177k. Niafarang licence issued 8 June, activity targeted for Q1 2018. Feasibility study still 'shortly'. CMEC deadline 1 December 2017.

Discuss in chat

16 June 2017regulatory community update● Neutral

Management visit to Senegal after the mining licence grant. Production start now targeted for Q4 2017. Environmental impact statement to be finalised; export routes still being defined. Signed a 3-year Casa Sport football sponsorship, about A$200k in total.

Discuss in chat

8 June 2017regulatory community update▲ GoodMajor

Senegal's Minister of Mines granted a 5-year small mining licence over 184.98 ha for Niafarang, resolving the long-pending licence thread. Astron targets production in the first quarter of 2018.

Discuss in chat

28 Apr 2017material agreement▼ BadMajor

CMEC EPC conditions-precedent deadline extended a second time, from 1 May 2017 to 1 December 2017. Conditions still not completed despite 'significant progress'. Donald funding remains unresolved about 18 months after the contract was signed.

Discuss in chat

28 Apr 2017quarterly activities report● Neutral

March 2017 quarter: no production. Donald spend $611k, Niafarang $29k. Feasibility study still 'shortly'; work plan now first half 2017. Repeats the CMEC extension to 1 December 2017.

Discuss in chat

1 Mar 2017half year report● Neutral

Half year to December 2016: revenue up 78.5% to $1.02m, mainly from sales of investments; trading revenue down 43.5% to $127k. Loss before tax $2.12m. NAV per share $0.83. Received $983k from the China land sale. No dividend.

Discuss in chat

9 Feb 2017annual report● Neutral

2016 annual report restates known items: 5.71Bt Donald resource, CMEC deadline extended to 1 May 2017, and Niafarang environmental approval obtained in August 2016. Reserve update is expected by early 2017. Objectives: meet CMEC conditions and obtain the Niafarang licence.

Discuss in chat

9 Feb 2017other● Neutral

Appendix 4G corporate governance checklist lodged with the annual report. Administrative; no new company information.

Discuss in chat

31 Jan 2017quarterly activities report▼ Bad

December 2016 quarter: no production. Donald spend $526k, Niafarang $68k. Feasibility study still 'shortly'; work plan slipped to Q1 2017. Niafarang licence now expected early 2017, after the earlier end-2016 guidance.

Discuss in chat