31 Oct 2018quarterly activities report● Neutral
September 2018 quarter: no production. Donald spend $106k, Niafarang $105k. Donald feasibility update still 'shortly'; CMEC contract remains ended with other funding options considered. Niafarang start now targeted Q1 2019, slipping again. About 30,000t TiO2 feedstock acquired; plant commissioning has commenced.
Statutory FY18 accounts: net assets fell $2.85m to $99.8m, net loss $4.67m, no dividend. NTA is stated as 20.6cps, versus 19.4cps in the preliminary report. Donald water pipeline now expected shorter than the earlier 75km.
Niafarang approvals are now complete, and equipment is shipping. Start-up awaits government resettlement of local landholders, so the earlier timeline has slipped with no new date. Astron plans a JORC 2012 reserve update.
Unaudited FY18 results: revenue up 163.9% to $5.01m, loss before tax $3.89m, loss after tax $4.67m. NTA fell 20.5% to 19.4cps. Operating cash flow positive $765k. Test pit stockpiled; initial zirconia sales.
June 2018 quarter: no production. Donald spend $317k, Niafarang $69k. EL5472 also expired; CMEC contract ended. About 30,000t of low-grade TiO2 feedstock bought for the China plant, commissioning targeted Q3 2018. Niafarang start now second half 2018.
Annual report for year to June 2017, released July 2018. Says Donald is financing-dependent after strategic funding milestones were missed. Niafarang production targeted mid-to-late Q4 2018. Carries no resource or reserve references because of delayed reporting.
3 July 2018material agreement termination▼ BadMajor
The CMEC EPC contract ended after the 30 June 2018 conditions-precedent date passed unmet. Astron says it continues talking to CMEC and considering other options, so Donald's funding route, pursued since October 2015, is now open.
March 2018 quarter: no production. Donald spend $196k, Niafarang $562k. 1,000t test pit sample completed. Feasibility study still 'shortly'; CMEC deadline remains 30 June 2018.
Astron signed a construction contract for a China plant and warehouse to make up to 150,000 tpa artificial rutile, initially from bought-in lower-grade feedstock. Donald development and execution is now expected in Q3 2018. A new downstream business step, no cost stated.
Donald completed a second test pit extraction, a 1,000t ore sample for geotechnical and metallurgical tests. Described as a step toward the final work plan submission and approval, and samples for offtake agreements. Final approval not yet obtained.
BDO Limited (Hong Kong), assisted by BDO East Coast, engaged as auditor, and Boardroom Corporate Services (HK) as company secretary. Future reports will follow Hong Kong Financial Reporting Standards.
December 2017 quarter: no production. Donald spend $592k, Niafarang $910k. Feasibility study still 'shortly'; CMEC deadline now 30 June 2018. RL2006 merged into RL2003; EL5255 expired and was not renewed.
Auditor Grant Thornton Australia resigned. Astron intends to appoint BDO East Coast Partnership, subject to formalities. No reason for the resignation is given in the text.
CMEC EPC conditions-precedent deadline extended a third time, to 30 June 2018. Contract price amended to US$119.6m (plus about US$5.5m insurance and fees) as financing moves from seller's to buyer's credit; DMS's 15% contribution unchanged. Conditions still unmet.
September 2017 quarter: no production. Donald spend $108k, Niafarang $499k. Feasibility study still 'shortly'; CMEC deadline remains 1 December 2017. Niafarang activity still targeted for Q1 2018; new Senegalese subsidiary incorporated.
Statutory FY17 accounts: net assets fell $3.07m to $102.7m; net loss $2.59m. Gambia legal fees were $135k. NTA 24.4cps. Donald export permit and test pit approvals listed; execution strategy uses a modular plant built via a Chinese fabrication yard.
Unaudited FY17 results: revenue up 305.9% to $1.90m, loss before tax $4.0m, NTA down 18.3% to 24.4cps. Operating cash outflow $3.2m. A further $1.73m of China land sale proceeds received after year end. Senegal licence obtained.
June 2017 quarter: no production. Donald spend $317k, Niafarang $177k. Niafarang licence issued 8 June, activity targeted for Q1 2018. Feasibility study still 'shortly'. CMEC deadline 1 December 2017.
Management visit to Senegal after the mining licence grant. Production start now targeted for Q4 2017. Environmental impact statement to be finalised; export routes still being defined. Signed a 3-year Casa Sport football sponsorship, about A$200k in total.
Senegal's Minister of Mines granted a 5-year small mining licence over 184.98 ha for Niafarang, resolving the long-pending licence thread. Astron targets production in the first quarter of 2018.
CMEC EPC conditions-precedent deadline extended a second time, from 1 May 2017 to 1 December 2017. Conditions still not completed despite 'significant progress'. Donald funding remains unresolved about 18 months after the contract was signed.
March 2017 quarter: no production. Donald spend $611k, Niafarang $29k. Feasibility study still 'shortly'; work plan now first half 2017. Repeats the CMEC extension to 1 December 2017.
Half year to December 2016: revenue up 78.5% to $1.02m, mainly from sales of investments; trading revenue down 43.5% to $127k. Loss before tax $2.12m. NAV per share $0.83. Received $983k from the China land sale. No dividend.
2016 annual report restates known items: 5.71Bt Donald resource, CMEC deadline extended to 1 May 2017, and Niafarang environmental approval obtained in August 2016. Reserve update is expected by early 2017. Objectives: meet CMEC conditions and obtain the Niafarang licence.
December 2016 quarter: no production. Donald spend $526k, Niafarang $68k. Feasibility study still 'shortly'; work plan slipped to Q1 2017. Niafarang licence now expected early 2017, after the earlier end-2016 guidance.