The story so far
The events that changed the company's story, in plain English, each written against everything known about the company at the time. The dot shows whether it was good, bad or neutral for shareholders.
2026
- 30 Sept
The target lending package for Phase 1 is now $200m, down from $220m, and FID slips again to Q4 2026 (previously Q3). First production is still planned for 2028. Energy Fuels has contributed $97.4m of its $183m earn-in.
debt financing
- 1 Sept
The Commonwealth Government approved export of Donald's rare earth concentrate to the United States, where Energy Fuels has the right to buy 100% for processing at White Mesa. Permits need renewal every two years. FID is still targeted for Q3 2026.
regulatory community update
- 22 June
The targeted Phase 1 lending package is now $220m, down from up to $300m under discussion earlier. Talks with EFA, other agencies and lenders continue. FID slips again to Q3 2026, after Q2 2026 earlier; EFA's A$80m support remains non-binding and conditional.
debt financing
- 9 June
Revised Phase 2 study for Donald's RL2002 licence shows incremental pre-tax NPV8 of $1.5b, with capex of $557m and mine life of 52 years. Phases 1 and 2 combined are $2.3b at 25.6% IRR. RL2002 Ore Reserve is 435Mt at 4.7% HM.
resource reserve update
- 31 Mar
Bankable Feasibility Study for Donald Phase 1: pre-tax NPV8 $759m (was $837m), IRR 19.3% (was 22.1%), capex $450m (was $439m), ~40-year life. Lenders are negotiating a package of up to $300m (earlier target ~$260m). FID slips again, now to Q2 2026.
resource reserve update
- 2 Mar
MIN5532 (Phase 1 site) Resource updated with detailed rare earth data: 530Mt at 4.0% HM and 1.4% TREO, replacing the 2022 estimate. Forecast dysprosium oxide output rises 57% to 144tpa and terbium 22% to 22tpa versus the July 2025 study. Grade-control drilling shows ~5% higher HM.
resource reserve update
2025
- 25 Nov
Astron sold 686,974 Energy Fuels shares at about US$14.24, raising roughly US$9.8m (A$15.2m). These were the shares issued at JV start in Sept 2024 (then US$3.5m). A further US$14m is still due on FID, now targeted late 2025/early 2026.
asset acquisition disposition
- 21 Oct
Export Finance Australia gave a non-binding, conditional Letter of Support for up to A$80m of senior debt for Donald, against a total funding need of about A$520m and a 50:50 debt-to-equity target. Subject to due diligence; other lenders still being lined up.
debt financing
- 20 Oct
The Australian Government granted Major Project Status to the Donald project through the Major Projects Facilitation Agency. The company says this should streamline federal agency engagement; it does not itself state any funding or timing change for the project.
regulatory community update
- 29 Aug
The redomicile scheme was implemented on 29 August 2025: Astron Limited shares were issued to eligible holders 2:1 and holding statements sent. Total shares 418,357,508; normal trading expected from 1 September. This completes the Hong Kong-to-Australia move.
business combination
- 20 Aug
The redomicile scheme became legally effective on 20 August 2025; CDIs stop trading that day and Astron Limited shares trade from 21 August. Holders get 2 new shares per 1 held, giving 418.36m shares, with implementation due 29 August.
business combination
- 19 Aug
The Hong Kong court sanctioned the redomicile scheme on 19 August 2025. Scheme becomes effective 20 August, with record date 22 August and implementation 29 August, when holders receive two new Astron Limited shares for each one held.
business combination
- 30 July
Securityholders approved the Hong Kong-to-Australia redomicile scheme at the 30 July court meeting, with 99.9996% of votes cast in favour. Next is Hong Kong court sanction on 19 August; CDIs would stop trading 20 August, with new Astron Limited shares replacing them 2:1.
business combination
- 23 July
Updated Phase 1 economics: pre-tax NPV8 $837m, IRR 22.1%, capex $439m (versus A$450-490m guided earlier and $392m in the 2023 DFS). FID planned late 2025, first production expected Q4 2027. Lender discussions to conclude in the second half.
resource reserve update
- 17 July
The Astron-Energy Fuels joint venture company signed a $3.5m contract with CHS Group for a 14.3 km raw water pipeline, on the project's critical path. Construction starts September and finishes early December 2025, before FID, which is now targeted for end of 2025.
contract award
- 25 June
Victorian Government approved the Donald Work Plan, the final major regulatory approval for Phase 1. This resolves the delay flagged in the April quarter. FID is expected this calendar year, with project financing satisfactory to the joint venturers the key prerequisite.
regulatory community update
- 16 June
Astron detailed its scheme to redomicile from Hong Kong to Australia, replacing securities with new Astron Limited shares on a 2-for-1 basis. Court meeting is set for 30 July 2025, with completion expected by 29 August 2025. Interests are described as materially the same.
business combination
- 1 May
Astron is seeking recognition of its ICSID award against The Gambia (about A$35m) as an English High Court judgment, with service of the claim ordered. Completion is anticipated by Q4 2025; costs are met by its litigation funder. This builds on the long-running enforcement effort.
regulatory community update
- 31 Jan
December 2024 quarter: Work Plan approval is now expected in the March quarter 2025, with FID during 2025. An in-principle deal with Harmony Group for a management buy-out of Astron's Niafarang (Senegal) interest was reached. HMC offtake arrangements are approaching finalisation. Phase 1 capex remains A$450-490m.
quarterly activities report
2024
- 5 Dec
The entitlement offer closed oversubscribed, raising about $11.5m; with the $3.0m placement, the total is about A$14.5m. All five directors and Ruiqing Tan took up their full entitlements. This resolves the open question about the offer's outcome. Securities on issue: 204.67m CDIs.
capital raising announcement
- 17 Oct
Astron raised $3m via an institutional placement at $0.66 per CDI and launched a 1-for-12 non-renounceable entitlement offer at $0.66 to raise about $10m, about $13m in total. Directors and Tan Ruiqing have indicated they will take up about $7.3m. Offer is not underwritten; funds go to pre-FID work, a Yingkou HMC study, Jackson exploration and redomicile investigations.
capital raising announcement
- 26 Sept
Donald JV with Energy Fuels completes 26 Sept 2024. Astron receives US$3.5m of Energy Fuels shares; the $8.6m loan converts to ~3.2% of the JV company (Astron ~96.8%). Phase 1 capex now guided at A$450-490m versus $392m in the DFS, and FID is now likely early 2025, later than the Q4 2024 previously targeted.
farm in farm out completion
- 31 July
Collins Street converts all its notes into 11.5m shares: 9,259,259 for the $5m principal, 1,851,852 for $1m of interest notes and 388,889 as an early conversion fee. Shares carry 12 months' escrow. This removes the $5m convertible note maturing March 2026 and adds dilution.
security holder rights change
- 4 June
Binding Donald JV signed with Energy Fuels, which will fund $183m for 49% (Astron 51%, manager) and issue Astron US$17.5m of shares. It takes 100% of rare earth concentrate for the life of mine (indicatively 58 years). FID now as early as Q4 2024. Resolves the MoU thread; completion needs conditions precedent.
farm in farm out agreement
- 18 Mar
Collins Street's $5m convertible note is extended 24 months to 17 March 2026, with 10% interest paid in new notes and conversion at $0.54. $1m of capitalised-interest notes convert into 1,851,852 CDIs. MIN5532 and RL2002 are released from security to enable the joint venture.
debt financing
- 26 Feb
Astron signed an Early Contractor Involvement agreement with Sedgman (CIMIC Group) for Donald Phase 1, chosen after a competitive tender. It is expected to complete in H1 2024 and leads toward a full delivery contract for the processing plant. This progresses the EPC tender thread.
contract award
- 12 Jan
Kang Rong is stepping back from her executive role running the China operations, but stays as a non-executive director and becomes chair of the Yingkou subsidiary. A search for a new China chief has begun; Tiger Brown oversees China meanwhile.
director officer appointment
2023
- 28 Dec
Non-binding MoU with Energy Fuels to form a Donald joint venture over MIN5532 and RL2002. Energy Fuels would invest A$180m for 49% (Astron 51%, operator) and issue Astron US$17.5m of shares, and take 100% of rare earth concentrate. Exclusivity runs to 1 March 2024.
farm in farm out agreement
- 28 Nov
Senegal's mines ministry has issued an order purporting to withdraw the Niafarang small mine licence renewed in April 2023. Astron's subsidiary says the order is invalid and is starting mandatory mediation, expected to take 2-3 months. This reopens the licence thread.
regulatory community update
- 7 Nov
Second-largest shareholder Tan Ruiqing committed to a $10m placement at $0.56 per CDI (17,857,144 CDIs) in three tranches to March 2024, about a 7.7% premium. The last $4m needs shareholder approval. He would then hold 30,820,107 CDIs, about 18.5%.
capital raising announcement
- 3 Oct
Work Plan for Donald Phase 1 submitted to the Victorian regulator, with review expected to take 6-9 months. FID is pushed to mid-2024 and first production to H1 2026 (previously Q1 2024 and H2 2025). Astron is also considering moving its parent company from Hong Kong to Australia.
regulatory community update
- 28 Sept
Firm commitments for a $2.68m placement at $0.56 per CDI (4,785,714 new CDIs), about a 19.1% premium to the $0.47 close. Funds go to Donald progression and working capital. Another small raise following the $7m at $0.54 in May.
capital raising announcement
- 27 June
New RL2002 Ore Reserve of 516Mt at 4.6% HM lifts the Donald deposit total to 825Mt at 4.5%. A Phase 2 study shows combined NPV8 of $2.2bn and 30.3% IRR, with $566m Phase 2 capex, construction from 2029 and funding from internal cashflow.
resource reserve update
- 19 May
Firm commitment for a $7m placement at $0.54 per CDI (12,962,963 new CDIs) to Tan Ruiqing, a former vice chairman of Lomon Billions Group. The price is about a 15% premium to the $0.47 close. Funds go to engineering, offtake, approvals and Work Plan.
capital raising announcement
- 26 Apr
Donald Phase 1 definitive feasibility study: after-tax NPV8 of $852m, IRR 25.8%, over a 41.5-year mine life. Capex is $364m and total funding need $392m. Final investment decision planned Q1 2024, first production H2 2025. Resolves the feasibility study thread; the funding need remains open.
resource reserve update
- 31 Mar
New MIN5532 Ore Reserve (the Phase 1 site) is 309Mt at 4.4% heavy minerals, up 59% in tonnes on the 2021 reserve. Contained heavy minerals rose 32% to 13.6Mt, and rare earth minerals 71% to 334,500t, including newly estimated xenotime. Feasibility study due early Q2 2023.
resource reserve update
2022
- 1 Dec
Updated MIN5532 Resource, the Phase 1 site, is 525Mt at 4.0% heavy minerals. Contained heavy minerals rose 25% to 21Mt and rare earth minerals 60% to 511,400t, including a new 135,500t xenotime resource. Resolves the Q4 2022 resource update; whole-project Resource now 2.6Bt at 4.6%.
resource reserve update
- 18 Nov
The Security Purchase Plan raised $891,000 from 70 holders (about 13% of eligible), including $150,000 of shortfall placement, well under the $3m maximum. With the October placement and loan conversion, total raised is $5.9m, funding Donald feasibility work.
capital raising announcement
- 17 Oct
Astron raised $5m at $0.54 per CDI: a $4m placement plus a $1m director loan conversion, with a $3m Security Purchase Plan to follow. Directors commit $2.415m. Funds go to the resource update, mine studies, plant design and approvals. Follows the Collins Street note; the price matches its A$0.54 conversion price.
capital raising announcement
- 18 Aug
Donald Phase 1 review outcome: ore throughput cut to 7.5Mtpa from 12.5Mtpa, with the on-site zircon/titania separation removed. Preliminary output is 250-300ktpa heavy mineral concentrate and 7-10ktpa rare earth concentrate, processed off-site, possibly at Yingkou. Feasibility study still due end Q1 2023.
investor presentation
- 1 Aug
June 2022 quarter: Donald project review is nearing completion, but delayed assay results from the 2022 drilling push the feasibility study to Q1 2023, from Q3 2022. A revised Resource for MIN5532 is now expected in Q4 2022.
quarterly activities report
- 1 Feb
Astron agreed to issue convertible notes to Collins Street Asset Management for A$5m, plus A$1m to pay interest. Two-year term, 10% coupon capitalised, convertible at A$0.54 per share, secured over Donald. Needs shareholder approval; funds Donald feasibility work. Relieves the very short cash runway.
capital raising announcement
2021
- 8 Nov
George Lloyd, a director since 20 July 2021, will become Chairman after the AGM, replacing Gerard King, who stays as non-executive director. Lloyd says Donald will go through feasibility and funding over the next 12 to 18 months.
director officer appointment
- 1 Nov
ASX suspended Astron's securities from 1 November 2021 for failing to lodge a periodic report by the due date.
listing compliance notice
- 21 Oct
The board decided not to proceed with the China demerger approved on 19 July, citing the Hong Kong injunction, expected delay of at least 6 months, cost and distraction from Donald. It will seek AGM approval to withdraw Resolution 1. Ends the demerger thread.
business combination
- 10 Sept
The Hong Kong court granted the interim injunction stopping Astron from implementing the demerger approved on 19 July. The in-specie distribution, due by 13 September, is on hold. Astron says the injunction is the last obstacle to the demerger, and will oppose a permanent order.
regulatory community update
- 2 July
Astron proposes demerging its China downstream processing and sales business into unlisted Titanium Hong Kong, distributed one share per Astron security. Astron would keep Donald and Niafarang. Shareholders vote at an EGM on 19 July 2021, which also covers option plans.
business combination
- 30 Mar
Pilot tests on Donald's 24t concentrate gave rare earth concentrate (51.2% REE) at up to 94.6% recovery, zircon recovery up to 90.8% and titania recovery up to 94.4%. Builds on the earlier recoveries and supports the move to a feasibility study in 2021.
drilling result
- 18 Feb
Donald Ore Reserve rises 141Mt (31%) to 602Mt at 4.8% heavy minerals, about 5.4Mt of contained zircon. This replaces the 2012/2013 reserve of 461Mt that Astron had said was unchanged, and is a key step toward the feasibility study.
resource reserve update
- 17 Feb
Tiger Brown, son of late founder Alex Brown, becomes Managing Director at $100,000 a year, replacing Kang Rong, who stays as executive director and Chief Marketing Officer. His stated focus is a Definitive Feasibility Study for Donald. This resolves the board structure review.
director officer appointment
2020
- 31 July
June 2020 quarter: Donald spend $287k (FY $900k), Niafarang $54k. The China plant produced 2,923t of rutile, up 354%, and sold 3,372t, up 1077% on the prior quarter. Donald feasibility update still 'shortly'; funding unresolved.
quarterly activities report
- 9 July
ICSID rejected The Gambia's annulment application in full and lifted the stay on enforcing the award (about A$31m, from 2015). Astron will explore enforcement options. This resolves the annulment thread; actual collection is not yet shown.
other
- 15 May
Pilot of 1,000t of Donald ore in a four-stage plant in Queensland, run by Mineral Technologies, was completed and Astron is pleased with it. Total TiO2, ZrO2 and CeO2 recovery to sand was 85.2%, 94.6% and 95.9%. About 24t of concentrate was produced. Supports the planned process design.
drilling result
- 3 Feb
Astron says commissioning of its Yingkou TiO2 plant (up to 150,000tpa) is complete, ahead of milestones. The plant runs at about 65% capacity, processing 15,000t of feed a month into 3,000-5,000t of product. This ends the extended commissioning thread; a throughput update is promised.
production update
2019
- 4 Dec
Managing Director Alex Brown, long-time driving force of Astron, died on 30 November 2019. Kang Rong, previously COO and Deputy MD, becomes CEO and Managing Director. Tiger Brown, son of Alex Brown and Kang Rong, joins the board; board structure to be reviewed.
director officer appointment
- 16 May
Astron began commissioning its China TiO2 processing plant, built for up to 150,000tpa, delivering the plant contracted in April 2018. Customers have pre-sale arrangements and orders are being filled during commissioning. No throughput or revenue figures given.
production update
- 1 Mar
Half-year to December 2018: revenue up 168.2% to $4.37m, net loss $945k, NTA 19cps. The auditor's review includes a going-concern emphasis of matter. Cash and term deposits fell $1.76m, partly offset by about $5.1m bank loans and $3.09m land-sale receipts.
half year report
2018
- 1 Oct
ASX paused trading in Astron securities pending a further announcement. No reason is given in the text.
listing compliance notice
- 3 July
The CMEC EPC contract ended after the 30 June 2018 conditions-precedent date passed unmet. Astron says it continues talking to CMEC and considering other options, so Donald's funding route, pursued since October 2015, is now open.
material agreement termination
- 27 Apr
Astron signed a construction contract for a China plant and warehouse to make up to 150,000 tpa artificial rutile, initially from bought-in lower-grade feedstock. Donald development and execution is now expected in Q3 2018. A new downstream business step, no cost stated.
contract award
- 13 Mar
ASX lifted the suspension from 14 March 2018 after Astron lodged its December 2017 half-year report, resolving the late-filing suspension.
listing compliance notice
- 1 Mar
ASX suspended Astron's shares from 1 March 2018 for failing to lodge its half-year report for the period to 31 December 2017 on time.
listing compliance notice
2017
- 7 Dec
CMEC EPC conditions-precedent deadline extended a third time, to 30 June 2018. Contract price amended to US$119.6m (plus about US$5.5m insurance and fees) as financing moves from seller's to buyer's credit; DMS's 15% contribution unchanged. Conditions still unmet.
material agreement
- 8 June
Senegal's Minister of Mines granted a 5-year small mining licence over 184.98 ha for Niafarang, resolving the long-pending licence thread. Astron targets production in the first quarter of 2018.
regulatory community update
- 28 Apr
CMEC EPC conditions-precedent deadline extended a second time, from 1 May 2017 to 1 December 2017. Conditions still not completed despite 'significant progress'. Donald funding remains unresolved about 18 months after the contract was signed.
material agreement
2016
- 4 Oct
The CMEC EPC deadline to satisfy conditions precedent, due about Aug-Oct 2016, is extended to 1 May 2017. Conditions are not yet complete, though 'significant progress' is claimed. The Donald funding path remains unresolved.
material agreement
- 7 Apr
Donald resource updated after 2015 infill drilling: total 5.71Bt at 3.2% HM. Measured resource at Donald doubled to 715Mt at 4.3% HM. Measured plus Indicated in-situ heavy mineral rose from 52Mt to 115Mt. Resolves the pending assay results; a reserve upgrade is expected later.
resource reserve update
2015
- 2 Dec
The Gambia has applied to ICSID to annul the July 2015 award, citing the tribunal's constitution, admissibility and jurisdiction. A panel of 3 arbitrators will decide whether to annul in whole or part. Astron will oppose; the award is not yet safe to collect.
other
- 13 Oct
Donald Mineral Sands signs the EPC contract with CMEC, following the April 2014 framework: US$135m price, with CMEC arranging seller's credit funding and Astron's subsidiary paying 15% (about US$18m). Conditions precedent, including Sinosure insurance and approvals, must be met within 10-12 months.
material agreement
- 23 July
ICSID awards Astron about A$31m against The Gambia: US$18.66m damages plus interest, costs and £2.25m legal fees. Resolves the Gambia arbitration open since 2008. Appeal period and enforcement against the government still to come, so collection is not assured.
other
2014
- 7 Oct
ICSID arbitration panel found comprehensively in Astron's favour over the Gambian licence cancelled in 2008, finding no basis for the cancellation. Damages not yet quantified; submissions due late October 2014. Resolves the long-open liability question; payment is not yet secured.
other
- 31 July
Donald resource updated to JORC 2012: total 4.78 billion tonnes at 3.7% heavy minerals, up from 4,040Mt at 4.8%. Jackson gets a maiden Indicated resource of 1.66Bt at 3.2%. Kang Rong is described as CEO.
resource reserve update
- 28 May
Capital return payment of $0.75 per share proceeds on 28 May 2014 after regulatory matters were completed. Resolves the earlier delay.
security holder rights change
- 14 Apr
Donald signs a binding framework agreement with China Machinery Engineering Corporation (CMEC) for phase 1 equipment and funding: about US$100m, 85% via CMEC seller's credit. Subject to approvals and a formal contract targeted for end July 2014. First concrete funding step for Donald.
material agreement
- 10 Mar
Board proposes returning $0.75 per share to all shareholders, subject to a shareholder vote. Says Chinese companies have shown interest in funding Donald, but investor search continues. A change from keeping cash for Donald.
dividend declaration
2013
- 31 July
Donald definitive feasibility study completed: capex $518m for 950ktpa, $277m for the first 475ktpa stage; NPV10 $2,104m, IRR 36.5%; first production targeted for early 2016. Concentrate would now be processed in China rather than Australia. Final investment decision and financing still pending.
resource reserve update
- 1 May
Goldman Sachs appointed sole financial adviser for Donald funding options, which may include selling a strategic interest in the project. Clarifies that Goldman has not agreed to provide funding. Advances the open funding thread.
material agreement
- 13 Mar
CEO Hayden Stockdale left of his own accord, effective 12 March 2013, only about a year after being appointed. Managing Director Alex Brown takes over his duties immediately. This follows the CFO's resignation two weeks earlier.
director officer appointment
2012
- 5 Sept
Niafarang in Senegal (100% owned) gets a first Probable Ore Reserve of 4.65Mt at 10.9% heavy minerals, from a Minxcon estimate based on the 2007 Indicated resource. Assemblage is 75.4% ilmenite, 13.6% zircon, 2.3% rutile. Supports the mining licence application.
resource reserve update
- 18 June
An independent review (METS) found Donald's zircon washing process feasible, finding no fatal flaws. Astron upgraded part of the reserve to Proved: 150Mt Proved and 311Mt Probable within EL4433, 461Mt total. Next is a mini-production plant. Resolves the washing verification thread.
resource reserve update
- 21 May
Hong Kong redomicile scheme implemented on 21 May 2012. Astron Corporation Limited now has 122,479,784 shares, 122,477,078 of them held through CDIs. CDIs trade normally from 23 May. Completes the thread opened January 2012.
business combination
- 4 May
The Federal Court approved the Hong Kong redomicile scheme, the final approval step. It becomes effective 8 May, with implementation expected 21 May (record date 15 May). Shareholders get two shares or CDIs per share; no action required. Resolves the delay reported 1 May.
business combination
- 20 Apr
Shareholders approved the Hong Kong redomicile scheme, with 99.9% of shares voted in favour and 91.9% of votes cast. Final court approval is set for 1 May 2012, with implementation planned for 15 May.
business combination
- 25 Jan
Astron plans to move its parent company to Hong Kong via a scheme of arrangement, with shareholders receiving two Astron HK shares or CDIs per existing share. The board cites China market proximity and a possible future Hong Kong listing to raise Donald funding. Needs shareholder and court approval.
business combination
2011
- 12 Dec
Hayden Stockdale, a Goldman Sachs natural resources financing executive, becomes CEO from 1 January 2012, relocating to Melbourne. He previously advised Astron on its 2008 China sale. Alex Brown is described as President.
director officer appointment
- 1 Dec
Donald resource upgraded 8% to 194 million tonnes of heavy minerals (4,040Mt at 4.8% HM, 1% cut-off), from 179Mt in April 2010. About 37Mt of zircon is contained. Most of the resource is in the lowest-confidence Inferred category.
resource reserve update
- 28 Oct
Astron's Donald subsidiary bought a 25-year annual water allowance of 6,975 ML at auction for $17.94m, with an option to extend another 25 years. This settles the long-running Donald water supply question, at a significant cost.
material agreement
- 5 Aug
Austpac announced that a WA court ruled its farm-in with Australian Zircon was not assignable, so the sale of EL4521 (WIM 150) to Astron has ended. This resolves the litigation against Astron's $5m purchase; Astron's own position is not stated here.
other
- 19 May
The agreements between Astron and Posco have expired, freeing Astron to keep talking to potential investors and partners, including Posco. This ends the Feb 2010 MOU and Sept 2010 framework arrangements; no funding deal was reached.
material agreement termination
2010
- 23 Aug
Donald mining licence MIN5532 was granted, with a 20-year renewable term. This resolves the application lodged in May 2010. The licence covers part of the 4.5bn tonne resource, including the 305Mt Probable reserve. Plant designs and a mining work plan continue.
regulatory community update
- 28 July
First Donald ore reserve: 305Mt Probable at 6.3% heavy mineral, based on 7.5Mtpa production and a life of over 40 years. Backed by 370Mt Indicated resource. The reserve is a conceptual-level study with ±30% accuracy.
resource reserve update
- 5 May
Astron relays Austpac's announcement that Australian Zircon is seeking to restrain the EL 4521 sale, and says it will defend its contractual rights to complete the purchase.
other
- 27 Apr
Donald resource re-modelled to 4.5 billion tonnes at 4% heavy mineral, versus 1.7 billion tonnes at 6% previously. Only 500Mt of it is Indicated; the rest is Inferred. A mining licence application is to be lodged soon.
resource reserve update
- 30 Mar
Astron agreed to acquire exploration licence 4521, including the WIM 150 project, from Austpac, subject to Ministerial approval. It also took a technology licence for Austpac's processes, intended for making synthetic rutile from Donald feedstock.
asset acquisition disposition
- 11 Feb
Astron signed a non-binding MOU with Korean steelmaker Posco to evaluate becoming a funding partner for Donald and its downstream processes. It could lead to a formal agreement, but nothing is committed. Astron also plans drilling to upgrade resources toward proven reserves.
material agreement
2009
- 5 Oct
Imerys notified potential warranty claims under the 2008 zirconia sale, some with estimated amounts and some without. Astron admits no liability and is considering them; any proceedings must start before 29 March 2010. Reopens a thread thought settled.
other
- 19 Aug
FY2009 preliminary results: net loss $2.5m, revenue $10.66m, cash $169m, no final dividend. Astron is revising feasibility studies for Donald and its China processes because of the financial crisis, and says Donald trial mining follows. Shares were also bought back.
annual report
- 11 May
Astron gave notice terminating its heads of agreement with South American Iron & Steel, with no further obligations. This ends the February 2009 conditional deal that could have given it control; its $774,500 placement subscription is not addressed.
material agreement termination
- 18 Mar
Astron received Commonwealth approval to mine and process Donald mineral sands, effective until March 2034, with first-stage mining in the north. It plans up to 500,000t of concentrate a year for China. This resolves the federal approval step; a mining licence is still needed.
regulatory community update
- 16 Mar
Astron terminated its Zambezi share subscription agreement from 11 March 2009 because shareholder approval and due diligence conditions were not met by 9 March. Ends the January 2009 Zambezi investment plan, including the A$3.42m placement and US$6m note.
material agreement termination
- 13 Feb
South American Iron & Steel (SAY) announced a $1.03m placement at 20c, including $774,500 from Astron, and a conditional agreement that could give Astron board control and 51%. It involves due diligence, a rights issue and sub-underwriting. Astron's cover note cites titanium interest.
capital raising announcement
- 28 Jan
Zambezi Resources (not Astron's own announcement) said Astron applied for 29m shares at A$0.02 (A$580,000, about 12.78%), the first step of a three-stage deal. Astron also agreed to a further A$3.42m placement and a US$6m convertible note, all conditional. A new investment outside Astron's mineral sands base.
capital raising announcement
2008
- 14 Nov
Victoria approved the Donald project's environmental requirements, provided the minister's recommendations are followed. It still needs Victorian resources and federal environment assessment, then a mining licence. It expects 75 direct jobs. Resolves the EES process begun in 2007.
regulatory community update
- 1 Sept
Preliminary FY2008 results: net profit $114.1m, mostly $116.7m from discontinued operations (the Imerys sale), against $11.4m. A 10c final dividend is proposed for 12 December 2008. Impairments include $6.8m of titanium costs and $6.0m of Gambian investment. Profit guidance said about $128m.
annual report
- 14 July
Astron guided FY08 net profit of about $128m on the Imerys sale, and about $8m for FY09. Cash is expected near $180m. It bought a 133.2ha Yingkou site for a titanium park, with about $30m more needed. Donald's go-ahead depends on the China plants.
investor presentation
- 15 Feb
Carnegie told Astron the Gambian government cancelled the licence to mine heavy mineral sands. Negotiations continue to resolve issues and resume mining. This escalates the January suspension of the Gambian operation Astron co-owns 50%.
regulatory community update
- 6 Feb
The sale of the four Chinese zirconia subsidiaries to Imerys settled on 5 February 2008 (the quarterly and later reports date it 4 February). Astron received A$196.4m gross, subject to later adjustment. This completes the sale announced in August 2007.
farm in farm out completion
- 31 Jan
December 2007 quarter: Gambia produced 22,767t of concentrate before the government stopped operations on 16 January. Directors fully provided against the Gambian assets. Donald spent $504,414, with no production, and the EES was lodged awaiting exhibition approval.
quarterly activities report
- 17 Jan
Carnegie said the Gambian government ordered all mining stopped immediately pending information on minerals mined and lab results. Carnegie says it complies with its licence. This hits the Gambia operation Astron co-owns 50% and takes offtake from.
regulatory community update
2007
- 30 Nov
Astron agreed amended Imerys terms: price cut from RMB1.25bn to RMB1.20bn, expected cash now about A$194m versus A$220m in August. The earn-out threshold falls to RMB130m. Completion is expected early 2008 after an EGM vote. This resolves the earnings-condition problem.
asset acquisition disposition
- 30 Oct
Astron blamed the accounts delay on Imerys sale audits and a faulty accounting system rollout. Audited profit is $11.43m, down from the $14.05m preliminary figure. Earnings of the businesses being sold may miss the RMB130m sale condition, so terms are being renegotiated with Imerys.
financial restatement
- 1 Oct
Astron said it could not release its audited 2007 accounts by the end of September as listing rules require. It acknowledged the ASX may suspend trading in its shares until they are released.
listing compliance notice
- 29 Aug
Astron agreed to sell its China zirconia materials business to Imerys for about A$220m cash (RMB1.25bn plus adjustments), plus an earn-out. It follows April's approach. Shareholder vote and KPMG report are due, with completion expected Oct/Nov; Astron will refocus on mineral sands and titanium.
asset acquisition disposition
- 12 June
Carnegie reported a Probable Ore Reserve for Niafarang of 3.4Mt of sand at 16.0% heavy minerals, within the 4.8Mt resource. Carnegie says it effectively doubles the size of the planned SeneGambia mining operation, which Astron co-owns 50%.
resource reserve update
- 7 May
Partner Carnegie reported a first Niafarang resource in Senegal: 4.8Mt of sand at 12.4% heavy minerals (Indicated, JORC 2004), about 13.7% zircon. This delivers the resource estimate expected from the Senegal JV, which Astron co-funds 50%.
resource reserve update
- 20 Apr
Astron received a third-party approach to buy its China zirconia materials business at a value implied to be significantly above market. Talks are at a more definitive stage, with no guarantee of a deal. Goldman Sachs JBWere has been retained; shareholder approval would be needed.
business combination
2006
- 15 Dec
Astron named the northern section (about 2,845 ha) as Donald's preferred mine start-up area, with enough ore for 7.5mtpa for at least 25 years. A mining licence application is planned. This resolves the start-up decision that was due in May 2006.
regulatory community update
- 29 Nov
Astron cut its profit guidance for the year to June 2007 to about $18m, from the earlier expectation of a result similar to 2006's $20.6m. It cited variable market conditions.
other
- 14 Sept
Preliminary results for year to 30 June 2006: revenue up 7.5% to $151.2m, net profit down 20.9% to $20.6m. A 10 cent final dividend is proposed for payment 12 December 2006. Margins fell as zircon costs could not be passed on.
annual report
- 19 July
Astron said ASIC issued an infringement notice over the timing of disclosure of January 2006 drilling results. The company was disappointed but complied and paid a $66,000 fine. This resolves the ASIC inquiry opened in January.
regulatory community update
- 11 Apr
Carnegie announced it signed an offtake agreement giving Astron, its 50% partner, the Gambian project's entire zircon and rutile output at world market prices. This formalises the in-principle deal flagged in January.
material agreement
- 31 Jan
Joint venture partner Carnegie said it received its Gambian mining licence, with about 20,000 tonnes a year of zircon/rutile concentrate forecast. Astron has agreed in principle to take all output. This is Carnegie's release, not Astron's.
joint venture update
- 31 Jan
Astron confirmed the 50/50 Carnegie joint venture, formed in 2002, has its Gambian mining licence. Dredging is to restart soon, with two more suction dredges and a bucket dredge on site. Output of up to 20,000 tonnes a year goes to Astron's Chinese operations.
joint venture update
- 12 Jan
Astron lifted the Donald Mineral Sands resource (Victoria) to 693 million tonnes at 5.1% heavy minerals, from 187 million tonnes at 6.3%. The rise follows a lower cut-off grade and wider areas. Mining is planned to start early 2007.
resource reserve update