2 Dec 2016regulatory community update▲ Good
Donald Mineral Sands obtained a permit to export up to 1.32 million tons of heavy mineral concentrate (controlled ores) until 31 October 2018, to be shipped to Astron's Chinese subsidiary Yingkou. A regulatory step for Donald; no construction funding is secured by it.
September 2016 quarter: no production. Donald spend $908k, Niafarang $90k. Updated feasibility study 'shortly'. Niafarang licence expected by end of calendar 2016. Repeats the CMEC extension to 1 May 2017.
The CMEC EPC deadline to satisfy conditions precedent, due about Aug-Oct 2016, is extended to 1 May 2017. Conditions are not yet complete, though 'significant progress' is claimed. The Donald funding path remains unresolved.
Statutory FY16 accounts: net assets fell $6.7m to $105.7m; net loss $3.46m excluding $0.95m Gambia legal fees. NTA fell to 29.9cps. Updated Donald feasibility now expected in the December 2016 quarter, later than the earlier 'within 3 months' guidance.
Unaudited FY16 results: loss before tax from continuing operations $5.0m, revenue down 60.3% to $1.11m. Net tangible assets fell 22.9% to 29.9 cents a share. Reports Senegal public enquiry meetings held and in-principle advice that the mining licence milestone will be achieved.
June 2016 quarter: no production. Donald spend $1.06m, Niafarang $50k. Updated Donald feasibility study expected within 3 months. Work plan submission still due Q4 2016. EL5354 expired in June 2016 and was not renewed.
Donald Mineral Sands sold 5 gigalitres of surplus carryover water to the Victorian Environmental Water Holder at $25 per megalitre, which the company says is well below its cost. Small community-minded trade; total proceeds were not stated (inference: roughly $125k at the quoted price).
March 2016 quarter: no production. Donald spend $700k, Niafarang $140k. Licence RL2006 granted in March 2016. Work plan submission expected in Q4 2016. CMEC conditions precedent still being worked on.
Donald resource updated after 2015 infill drilling: total 5.71Bt at 3.2% HM. Measured resource at Donald doubled to 715Mt at 4.3% HM. Measured plus Indicated in-situ heavy mineral rose from 52Mt to 115Mt. Resolves the pending assay results; a reserve upgrade is expected later.
Half year to December 2015: revenue down 49.8% to about $0.57m, loss before tax $2.26m. Net asset value per share $0.89. Received $4.2m of receivables from the China land sale. No dividend.
December 2015 quarter: no production. Donald spend $1.27m, Niafarang $215k. Assaying still underway. Funding: parties working to satisfy the CMEC conditions precedent; no further detail.
The Gambia has applied to ICSID to annul the July 2015 award, citing the tribunal's constitution, admissibility and jurisdiction. A panel of 3 arbitrators will decide whether to annul in whole or part. Astron will oppose; the award is not yet safe to collect.
2015 annual report restates known items: NTA 38.8c, FY15 profit $7.99m, the CMEC EPC contract subject to conditions, and the Gambia award. Says a Niafarang mining licence will be submitted once environmental approval is obtained, and a community memorandum of terms has been reached.
September 2015 quarter: no production. Donald spend $921k, Niafarang $204k. Repeats the 13 October CMEC EPC contract (US$135m, 15% or about US$18m from Donald, 10 months for conditions). Drill sample assaying still underway.
Donald Mineral Sands signs the EPC contract with CMEC, following the April 2014 framework: US$135m price, with CMEC arranging seller's credit funding and Astron's subsidiary paying 15% (about US$18m). Conditions precedent, including Sinosure insurance and approvals, must be met within 10-12 months.
Statutory FY15 accounts: net assets rose $15.6m to $112.4m, helped by the $11.1m China land sale and $7.3m foreign exchange gains. Net loss excluding the land gain was $3.09m. No dividend. Donald work plan still in draft with the Department of Primary Industries.
Unaudited FY15 results: profit after tax $7.99m, driven by $11.1m other income from selling Chinese land, against a $6.17m pre-tax loss from continuing operations. Net tangible assets 38.8 cents a share. Land sale proceeds are expected from September 2015.
June 2015 quarter: no production. Assaying of drill samples from RL2002 and RL2003 is underway. Still no binding funding beyond the CMEC framework. Donald spend $848k, Niafarang $157k. Some licences expired in May 2015.
ICSID awards Astron about A$31m against The Gambia: US$18.66m damages plus interest, costs and £2.25m legal fees. Resolves the Gambia arbitration open since 2008. Appeal period and enforcement against the government still to come, so collection is not assured.
March 2015 quarter: no production. Drilling of 157 holes at RL2002 and 82 at RL2003 completed at Donald, with results to follow. No binding funding beyond the CMEC framework. Donald spend $1.01m, Niafarang $165k.
S&P Dow Jones index announcement lists Astron among removals from the All Ordinaries index after 20 March 2015. Third-party notice, no new company information.
Half year to December 2014: revenue down 61% to $1.14m, loss before tax $2.13m. Net assets per share $0.82. Interest income fell after the capital return; the report notes new activities in the USA. No dividend.
December 2014 quarter: no production. Donald spend $939k, Niafarang $190k. No binding funding beyond the CMEC framework. Donald licences now listed as including RL2002 and RL2003.
2014 annual report restates known items: the 75c capital return, the Gambia arbitration win with damages to be determined, and ongoing CMEC negotiations. Fundraising for Donald is the stated focus for the coming year. No new figures.
September 2014 quarter: no production. Donald spend $1.03m, Niafarang $81k. Still no binding funding beyond the April 2014 CMEC framework; the end-July 2014 target for a formal EPC contract passed without one being reported.
Kang Rong, already an executive director, is appointed Chief Operating Officer and Deputy Managing Director. Director Ron McCullough resigns and ends his consulting role after 8 years.
ICSID arbitration panel found comprehensively in Astron's favour over the Gambian licence cancelled in 2008, finding no basis for the cancellation. Damages not yet quantified; submissions due late October 2014. Resolves the long-open liability question; payment is not yet secured.
Full audited accounts for FY14 repeat the preliminary result: net assets fell $99.9m to $96.8m, with $91.9m returned to shareholders in May 2014 and a $7.58m net loss. Donald work plan still awaits approval.