History
Alderon took in Chinese steel partner Hebei to back its Kami iron ore project, won key approvals and a feasibility study, but by late 2015 was conserving cash and leaving the NYSE MKT.
2012: A Chinese partner for Kami
Alderon set out to build its Kami iron ore project in Labrador and Quebec. In April 2012 it signed a deal with Hebei Iron & Steel Group: C$194 million for 19.9% of Alderon's shares at C$3.42 and a 25% stake in a new partnership to own Kami. Hebei would also buy 60% of annual output, up to 4.8 million tonnes, at the Platts price less 5%, and would use best efforts to help arrange project debt. Existing shareholders faced dilution, and Liberty Metals & Mining planned to use its right to buy about 3.8 million shares.
In July the final resource estimate showed 1.1 billion tonnes of Measured and Indicated resource at 29.8% iron, with the Inferred portion falling as more rock moved into higher-confidence categories. In August the share price in the deal dropped to C$2.41, so the placement (still about 25,828,305 shares) raised C$62.2 million rather than C$88.3 million. Hebei's payment for the partnership interest rose to C$120 million, cutting the total to C$182.2 million. Chinese approvals were in hand by August 21, and in September Alderon filed its 5,000-page Environmental Impact Statement.
2013: Feasibility and financing
The Feasibility Study, released January 9, 2013, described an 8 million tonne a year operation producing concentrate at 65.2% iron. It showed a pre-tax value of US$3.244 billion, initial capital of US$1,272.9 million, a 30-year mine life and payback in 3.8 years. Compared with the 2011 preliminary study, capital was higher and the return lower. For the first time it stated reserves: 668.5 million tonnes at 29.5% iron. In March Alderon reported that the $119.9 million Hebei financing had closed.
By October, environmental review was advancing and equipment bids were in, with production targeted for the end of 2015. But project debt financing, rail and power agreements were still unfinished. In December the power agreement was ready but awaited a provincial decision on a new transmission line, which the CEO called critical to the debt financing.
2014: Approvals and power
The approvals fell into place. Newfoundland and Labrador's Cabinet released the project from provincial assessment on January 10, and the federal Minister found on February 18 that it was not likely to cause significant adverse environmental effects. Director Danny Williams resigned from the Board in February but stayed as an adviser. After the province confirmed the transmission line, Kami LP signed its power purchase agreement on February 25. It had to post US$65.0 million in letter-of-credit security deposits, and the first was funded by a $22.0 million loan from Liberty Metals & Mining at 8%, secured on the project, due December 31, 2018 and convertible into shares at $2.376. Construction was planned for later in 2014, though the record does not show it starting.
2015: Cash conservation
The record is quiet through 2015 until October, when Alderon said it would voluntarily leave the NYSE MKT and end its US Securities and Exchange Commission reporting, citing a cash conservation program, lower listing and legal costs, and exchange minimum share price rules. Shares remain on the Toronto exchange, where most trading occurs. As of October 5, 2015, Kami was still in development, held 75% by Alderon and 25% by Hebei, with financing risk still flagged and no construction start reported.
Written from the 14 story beats below (2012 to 5 Oct 2015), which come from the company's own announcements and filings.