Each one in plain English, with the numbers worked through for a shareholder.
2 May 2025other● Neutral
Woodside refiled an amended version of the transcript of its 29 April 2025 Louisiana LNG investment decision presentation. The visible text repeats the already-reported figures (US$17.5B capex including US$15.9B for the LNG project and US$1.1B for the pipeline, Stonepeak's US$5.7B, Woodside share US$11.8B, IRR above 13%, 7-year payback). The visible text does not say what was amended.
Woodside filed two announcements dated 30 April 2025, the day after the Louisiana LNG final investment decision. The first says Woodside signed an agreement with bp, through its Louisiana LNG Gas Management LLC subsidiary, to buy up to 640 billion cubic feet of gas long term, delivered to Line 200 from 2029. It is described as the first tranche of a diversified feedgas portfolio for the project. The second is the transcript of the 29 April FID presentation, repeating the already-reported figures (three trains, 16.5 Mtpa, first LNG 2029, US$17.5B capex, Woodside share US$11.8B, IRR above 13%, 7-year payback); the visible text is truncated.
Woodside took the final investment decision on the three-train, 16.5 Mtpa Louisiana LNG development, targeting first LNG in 2029. It forecasts an internal rate of return above 13%, a seven-year payback and about $2 billion a year of net operating cash in the 2030s at full capacity. Total capex including pipeline and management reserve is US$17.5 billion (100%), of which Woodside's share is $11.8 billion after Stonepeak's $5.7 billion, with Stonepeak's deal expected to close in Q2 2025. This resolves the open FID thread; Woodside says it is advancing further equity sell-downs.
Woodside signed LNG sale and purchase agreements with Uniper: 1.0 Mtpa from Louisiana LNG LLC (free-on-board, for up to 13 years from commercial operations) and up to 1.0 Mtpa from its global portfolio delivered into Europe, from Louisiana's start of operations until 2039. This resolves the previous day's talks and follows the Stonepeak deal, but both agreements are subject to Woodside's final investment decision on the three-train, 16.5 Mtpa Louisiana LNG development.
In response to media speculation, Woodside confirmed it is in discussions with Uniper about potential LNG supply, saying talks are ongoing and incomplete with no final agreement on terms. This precedes the Uniper supply agreements signed the next day.
Woodside signed a binding deal to sell 40% of Louisiana LNG Infrastructure LLC (the company holding the Bechtel construction contract and liquefaction facilities) to infrastructure investor Stonepeak. Stonepeak will contribute $5.7 billion toward capital spending, covering 75% of project capex in both 2025 and 2026, with about $2 billion payable on completion for spending since 1 January 2025. This is the partner sell-down for the project acquired via Tellurian; the deal is conditional on a final investment decision and approvals, with closing targeted for Q2 2025. Woodside says it is also seeking further sell-downs toward about 50% of the integrated project, and the forward cost estimate stays at $900-960 per tonne. The same filing includes the sustainability briefing transcript.
Woodside announced a 3 April 2025 sustainability briefing by CEO Meg O'Neill and attached the slides. It says the company is on track for its net equity Scope 1 and 2 emissions reduction targets and making material progress toward its Scope 3 investment and abatement targets. No new transactions or financial figures appear in the visible text.
Woodside issued its notice for the Annual General Meeting on 8 May 2025 (hybrid, Perth and online), with a voting form and letter to shareholders. Ann Pickard, Ben Wyatt and Tony O'Neill (who joined the board in 2024) stand for election or re-election. The letter cites 2024 results of net profit after tax of $3.6 billion (underlying $2.9 billion), record production of 194 MMboe, EBITDA of $9.3 billion and Scarborough 80% complete.
28 Mar 2025asset acquisition disposition● NeutralMajor
Woodside agreed to sell its Greater Angostura assets in Trinidad and Tobago to Perenco for $206 million, covering the Angostura and Ruby fields, production facilities and the onshore terminal. Closing is expected in the third quarter of 2025 (effective date 1 January 2025), subject to joint venture, government and regulatory approvals, and Perenco takes on the restoration obligations. The sale follows the Australian asset swap announced in December 2024, and the deepwater Calypso field is not included.
Routine filings on executive share holdings. CEO Meg O'Neill had 16,391 performance rights lapse after performance conditions were tested, leaving 204,502 rights plus 182,936 shares and 337,044 restricted shares; her opening rights balance was corrected from a previous error. A separate notice reports 98,393 unquoted rights issued under an employee incentive scheme on 5 March 2025 (further detail truncated, including the Appendix 3H). No new ordinary shares are shown.
Routine director share notices dated 6 March 2025. Non-executive directors Larry Archibald (1,852 shares bought, to 15,376) and Ashok Belani (960 shares bought, to 1,693) had shares bought on-market at $25.01 each on 27 February 2025 by the trustee of the Non-Executive Directors Share Plan. The visible text also references a notice for CEO Meg O'Neill (not shown in the truncated portion). No effect on Woodside's operations or share count.
Woodside reported year-end 2024 reserves of 1,975.7 MMboe proved and 3,092.2 MMboe proved plus probable, down from 2,450.1 and 3,757.1 MMboe a year earlier. The Scarborough sell-downs (25.1% in total) removed 323.0 MMboe of proved and 504.7 MMboe of proved plus probable reserves, which more than outweighs the 54.9 MMboe proved and 46.2 MMboe proved plus probable gains excluding divestments and production. Sangomar produced 13.3 MMboe in 2024 with about US$950 million of sales revenue; final Phase 1 cost was about US$5.0 billion, at the low end of the US$4.9-5.2 billion range, and plateau output is forecast into Q2 2025. It also gives 2024 line-item guidance ahead of full-year results due 25 February 2025.
Woodside agreed an asset swap with Chevron: it gives up its 13% of Wheatstone and 65% operated interest in Julimar-Brunello, and gets Chevron's 16.67% of the North West Shelf Project and NWS Oil Project (taking it to 50% and 66.67%) plus a further 20% of the Angel CCS project (to 40%). Chevron also pays up to US$400 million in cash (US$300 million at completion, up to US$100 million contingent), and has paid a refundable US$100 million advance on signing. Effective date is 1 January 2024, but completion is expected in 2026, after Julimar Phase 3 handover, and needs competition, foreign investment and other approvals. This is the Australian asset swap previously listed as an open thread.
Woodside published a revised Securities Dealing Policy, effective 4 December 2024, which sets rules on trading in its shares by directors, employees and contractors. The visible text does not say what changed from the previous version. It has no direct financial effect on shareholders.
Woodside signed a revised fixed-price (lump sum turnkey) construction contract with Bechtel for the three-train, 16.5 Mtpa foundation development of Louisiana LNG (the former Driftwood), with work continuing under a limited notice to proceed. Spending from December to the end of Q1 2025 is forecast at up to US$1.3 billion, included in the overall cost estimate. The estimated forward cost is US$900-960 per tonne, unchanged from acquisition, and FID readiness is still targeted from Q1 2025. A final investment decision has not yet been taken.
Woodside held an investor site visit at Pluto LNG, including a tour of Pluto Train 2, and filed the presentation slides. The cover note says Scarborough is almost three quarters complete and on track for first LNG cargo in 2026, consistent with the 73% figure at 30 September. The visible text contains no new transactions or figures.
Woodside completed the sale of a 15.1% non-operating interest in the Scarborough Joint Venture to JERA, the deal agreed on 23 February 2024; it received about US$1.4 billion (purchase price plus reimbursed expenditure). Woodside now holds 74.9% and remains operator. Scarborough 1P undeveloped reserves fall by 194.3 MMboe to 964.0 MMboe and 2P by 303.6 MMboe to 1,506.1 MMboe (Woodside share). The project was 73% complete at 30 September 2024, with first LNG still targeted for 2026.
Woodside completed its purchase of all of Tellurian's common stock for about US$900 million cash (US$1.00 per share; implied enterprise value about US$1,200 million), finishing the deal agreed on 22 July 2024 and within the Q4 2024 target. It renamed the Driftwood LNG project Woodside Louisiana LNG (27.6 Mtpa permitted, pre-FID, under construction in Calcasieu Parish). Woodside still targets FID readiness from Q1 2025, and says several parties have approached it about joining as strategic partners.
Woodside completed the purchase of 100% of OCI Clean Ammonia Holding B.V., owner of the 1.1 Mtpa Texas ammonia project, for about US$2,350 million in cash (80% paid, 20% due at project completion). This completes the deal agreed on 5 August 2024. The project is still under construction, with first ammonia targeted from 2025 and lower carbon ammonia from 2026, which depends on carbon-abated hydrogen supply and ExxonMobil's CCS facility starting up. OCI manages construction through provisional acceptance, and Phase 1 is expected to add to free cash flow from 2026.
Woodside published the transcript of its 16 September US investor event. Management said 2024 production is expected to be over 500,000 boe/d, in line with guidance, and that the half-year dividend represented an annualised yield of 7.3%. It framed the Tellurian/Driftwood acquisition as adding Atlantic basin exposure, and said Sangomar has quickly reached nameplate capacity (a claim from the visible text). Daniel Kalms is named as Chief Operating Officer International and Mark Abbotsford as Chief Commercial Officer.
Woodside announced a US investor event on 16 September 2024, a 'Global LNG Deep Dive' with CEO Meg O'Neill, CFO Graham Tiver and Chief Commercial Officer Mark Abbotsford, with a presentation attached. The visible text is an overview of the strategy and LNG portfolio; no new transactions or figures are shown in the portion provided.
Routine notice that 32,307 existing Woodside shares were transferred on 4 September 2024 to CFO Graham Tiver when his SWEP equity rights vested and converted. No new shares were created and the ordinary share count stays at 1,898,749,771. Unquoted SWEP equity rights fall to 1,493,559 (from 1,570,432 in the earlier context, other changes possible).
Woodside priced US$2 billion of senior unsecured US bonds, issued by subsidiary Woodside Finance and guaranteed by Woodside Energy Group: US$1.25 billion of 10-year bonds at 5.1% and US$0.75 billion of 30-year bonds at 5.7%. Settlement is expected 12 September 2024, and proceeds are for general corporate purposes. This adds new debt, and the filing does not link it to the pending Tellurian or OCI acquisitions (such a link would be an inference). Damien Gare signs as Corporate Secretary.
Directors' share dealings notified on 4 September 2024. On 2 September the Non-Executive Directors Share Plan trustee bought shares on a pre-determined date at $27.55: 733 for Ashok Belani (his first holding, from nil) and 947 for Arnaud Breuillac (798 to 1,745). These are routine plan purchases, not discretionary trades. The visible text does not show whether other directors were also included.
Directors' share dealings notified on 2 September 2024. Chair Richard Goyder bought 10,000 shares on market on 30 August at $27 per share, taking his holdings to 27,829 (Warrangi Trust) and 8,334 (superannuation fund). Director Ian Macfarlane bought 1,250 shares directly and his spouse bought 1,250, at $26.99 per share. These are small purchases by directors, not a company transaction.
Woodside and the Australian Conservation Foundation agreed to dismiss the ACF's Federal Court challenge to a primary environmental approval for Scarborough, which had been brought in June 2022. Woodside says the project now has all primary environmental approvals, and it was 67% complete at the end of June 2024 (up from 55% at end 2023) with first LNG still targeted for 2026. This resolves one legal risk to the project that followed the September 2023 seismic plan ruling.
Woodside published the transcript of the OCI ammonia acquisition call. Management said construction is 70% complete, OCI will finish and performance-test Phase 1 under cost, schedule and performance guarantees, and the US$2.35 billion price includes the full Phase 1 construction cost. Phase 1 is expected to be free cash flow accretive from 2026 and earnings per share accretive from 2027. The call also introduces Shaun Gregory as former EVP New Energy and Special Adviser.
Woodside agreed to buy 100% of OCI Clean Ammonia Holding B.V. and its Beaumont, Texas ammonia project for about US$2,350 million in cash, including capital spending to finish Phase 1. First ammonia is targeted for 2025 and lower carbon ammonia for 2026, with Phase 1 abating 1.6 Mtpa CO2-e and both phases 3.2 Mtpa, over 60% of the Scope 3 abatement target set in the climate plan. Phase 2 (a second 1.1 Mtpa train) is still pre-FID. Woodside says it expects returns above its 10% IRR target.
Woodside agreed to buy all of Tellurian for about US$900 million in cash (US$1.00 per share; implied enterprise value about US$1,200 million), gaining the fully permitted Driftwood LNG development in Louisiana (27.6 Mtpa permitted capacity). This is a new US LNG position beyond its roughly 10 Mtpa of Australian equity LNG. Woodside targets FID readiness for Phase 1 from Q1 2025 and completion in Q4 2024, subject to Tellurian shareholder, regulatory and other approvals, and it will lend Tellurian up to US$230 million before completion. Tellurian's board has approved the deal.
Woodside published the transcript of its Sangomar first-oil call. Management said the first cargoes are sold (expected to go to Europe), drilling results are in line with expectations, and Senegal's production sharing contract lets 75% of revenue be used to recover costs, with the government's share of the remaining revenue at 15-20%. It also said it has signed a loan agreement with JBIC to fund the Scarborough Energy Project and a long-term LNG offtake contract with KOGAS (February 2024), and that first steel cut for the Trion platform is expected later in 2024. Shiva McMahon is named as EVP International Operations.