Story beats
208 since 2007
Last event
19 Aug 2026

Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

29 July 2013quarterly activities report▲ Good

June quarter ROM output was 2.247Mt, up 53%; FY2013 ROM was 9.072Mt, up 71%, meeting the 9.0Mt guidance. Maules Creek construction is underway, with first coal sales expected in late 2014. A finance shared-services restructure is part of Stage 2.

Discuss in chat

22 July 2013production update▲ Good

Narrabri's first longwall changeout is finished safely, on time and on budget, and cutting started in panel 2. Weekly output should return to normal levels over coming weeks. Addresses a point of shareholder focus on the ramp-up.

Discuss in chat

19 July 2013regulatory community update▼ BadMajor

A group has started Federal Court proceedings against the Environment Minister and Whitehaven, challenging the 11 February 2013 Maules Creek approval on legal grounds. Whitehaven says construction can proceed meanwhile and will seek an expedited hearing. A new risk to the approval just won.

Discuss in chat

4 July 2013regulatory community update▲ GoodMajor

Maules Creek receives all approvals needed to start construction. Capex is about $767m, with $607m still to spend ($455m Whitehaven's 75% share), funded from existing facilities and cashflow. Rail loop work starts August; first coal sales expected second half of 2014.

Discuss in chat

19 June 2013security holder rights change● NeutralMajor

Farallon Capital buys about 9.91% of Whitehaven from Tinkler entities and agrees to buy another 1.63%, becoming largest shareholder. Rest of Tinkler's stake went to other members of its lending syndicate. Ends Tinkler Group's role as largest shareholder.

Discuss in chat

12 June 2013investor presentation● Neutral

UBS conference presentation by MD Paul Flynn largely repeats known facts: Maules Creek at 75%, Vickery now 100%, and a path to about 23Mtpa saleable production by FY2017. No new figures or events are announced.

Discuss in chat

13 May 2013other▲ Good

Whitehaven settles the claim by Hamish Collins, ex-Aston CEO, over alleged equity entitlements under his Aston contract. Terms are confidential, but Whitehaven says it paid an immaterial sum. Resolves the lawsuit filed in April 2012.

Discuss in chat

7 May 2013production update▲ Good

Record monthly coal railings of 0.95Mt in April, beating the 0.82Mt record set in January, reflecting the Narrabri ramp-up. Whitehaven projects FY2013 ROM production and sales of 9.0Mt each, including 0.9Mt of purchased coal, and expects lower take-or-pay charges.

Discuss in chat

30 Apr 2013admin correction● Neutral

Re-release of the March quarterly report, amended only to add the equity-basis production tables on page 4. Other content is unchanged.

Discuss in chat

30 Apr 2013quarterly activities report● Neutral

March quarter ROM output rose 99% to 2.551Mt, driven by the Narrabri longwall ramp-up, with record weekly Narrabri output. Most Maules Creek management plans are approved. FY2013 ROM is expected at about 9.0Mt, in line with broker consensus. Weak prices and a strong dollar persist.

Discuss in chat

22 Mar 2013regulatory community update▼ Bad

Whitehaven cuts costs at Rocglen and Tarrawonga, removing one excavator and four trucks at each site. About 30 permanent and 10 contractor jobs go. It cites weak coal prices, the exchange rate and cash margin pressure, and says the mines stay viable at current prices.

Discuss in chat

12 Mar 2013regulatory community update▲ GoodMajor

The federal government approves the Tarrawonga expansion, subject to conditions, following NSW approval in January. Output can rise from 2 to 3Mtpa and mine life extend from 2017 to 2030. Whitehaven owns 70% and Idemitsu 30%. Closes that open thread.

Discuss in chat

8 Mar 2013asset acquisition disposition▲ GoodMajor

Whitehaven buys Itochu's 29% interest in Vickery South, plus its right to rise to 49%, taking the project to 100%. Payment is 11.47 million Whitehaven shares, and Itochu's offtake and sales agency rights end. Vickery's environmental impact statement went on display 5 March.

Discuss in chat

26 Feb 2013investor presentation● Neutral

Presentation repeats the half-year results: underlying EBITDA $8.2m, net loss $47.0m, and undrawn debt facilities of $650m. Maules Creek construction is targeted for mid-2013. No new information beyond the results release.

Discuss in chat

26 Feb 2013half year report▼ BadMajor

Half-year to December 2012: underlying EBITDA $8.2m, as guided, but net loss $47.0m versus a $19.9m profit a year earlier, including about $20m from Sunnyside closure accounting. No interim dividend. Cash $83.2m, debt $487.5m; Maules Creek construction targeted mid-2013.

Discuss in chat

26 Feb 2013resource reserve update▲ GoodMajor

Total coal resources rise 2% to 3,787.9Mt from 3,706.7Mt in August 2012, with marketable reserves unchanged at 776.58Mt. Ferndale rises 21% to 445.7Mt and Pearl Creek to 52.4Mt, while Vickery resources dip 6.5Mt.

Discuss in chat

21 Feb 2013director officer appointment● NeutralMajor

Paul Flynn, a Whitehaven non-executive director and former Tinkler Group MD, becomes MD/CEO from 25 March 2013, replacing Tony Haggarty, who stays as a non-executive director. Flynn's fixed pay is $1.3m a year. Resolves the succession thread.

Discuss in chat

11 Feb 2013regulatory community update▲ GoodMajor

Minister Burke grants conditional federal approval for Maules Creek, only four days after the extension. Resolves the long-awaited federal approval, following NSW approval in October. Whitehaven will seek to start production as soon as possible despite the difficult coal market.

Discuss in chat

7 Feb 2013regulatory community update▼ Bad

The federal environment department and Minister Burke extend the Maules Creek assessment by three months to 30 April 2013. Whitehaven is 'extremely disappointed' and says it knows of no substantive issues. Delays the December-assumed federal approval for the 75%-owned project.

Discuss in chat

31 Jan 2013quarterly activities report▼ BadMajor

December quarter ROM output rose 96% to 2.367Mt, with Narrabri producing 1.063Mt. But weak coal prices and a strong Australian dollar leave first-half EBITDA expected below $10m, with the second half similar if conditions persist. Writedowns and the derailment also weigh.

Discuss in chat

25 Jan 2013regulatory community update▲ GoodMajor

The NSW Planning Assessment Commission approves the Tarrawonga expansion, subject to stringent conditions, lifting output from 2Mtpa to 3Mtpa and extending mine life to 2030. Federal approval is still awaited. Follows Maules Creek's NSW approval in October.

Discuss in chat

25 Jan 2013director officer appointment● Neutral

Jamie Frankcombe, from Fortescue, becomes Executive General Manager Operations from 4 February, replacing Allan Davies, who retires after about four years in the role and stays on part-time as a consultant.

Discuss in chat

7 Jan 2013admin correction● Neutral

Whitehaven says a hoax media release claiming ANZ had withdrawn the $1.2 billion bank facility is false, and ANZ has confirmed it is a hoax. The facility is unaffected.

Discuss in chat

28 Dec 2012contract award▲ GoodMajor

Aurizon announces a 12-year contract from 1 July 2014 to haul up to 16Mtpa of Whitehaven coal from four sites including Maules Creek, with Aurizon investing up to $280m. It adds a second rail operator in the Gunnedah Basin.

Discuss in chat

28 Dec 2012material agreement▲ Good

Whitehaven confirms a long-term rail haulage agreement with Aurizon for up to 16Mtpa of Gunnedah Basin export coal, supplementing existing arrangements and brought on progressively as growth requires. Whitehaven's own release gives no term or start date.

Discuss in chat

21 Dec 2012debt financing▲ GoodMajor

Financial completion of the A$1.2 billion four-year senior secured bank facility, now underwritten by ANZ, CBA, Macquarie and NAB. It replaces existing facilities and funds corporate needs and Maules Creek. Closes the refinancing thread.

Discuss in chat

19 Dec 2012price query● Neutral

Responding to a press report, Whitehaven says it has discussed possible synergies with Shenhua in the Gunnedah Basin, but has received no proposal from Shenhua to sell assets to it or to acquire Whitehaven.

Discuss in chat

17 Dec 2012director officer appointment● Neutral

Jonathan Vandervoort, former CEO of the Hunter Valley Coal Chain Co-ordinator, is appointed Executive General Manager Infrastructure from mid January. He also takes over new projects previously under Business Development, the unit just scaled back.

Discuss in chat

14 Dec 2012regulatory community update● Neutral

The rail line is now expected to reopen on 20 December, five days earlier than advised. The trucking application is still being assessed, and a small trial raised issues mainly around increased grain and freight traffic.

Discuss in chat

6 Dec 2012regulatory community update▼ Bad

Whitehaven applies for temporary approval to truck up to 80,000 tonnes a week of Narrabri coal to Gunnedah for 2-3 months. Rail is now expected to reopen by 25 December. Without a transport option, Narrabri stockpiles would fill in December and mining would stop.

Discuss in chat