Stockle - the stock oracle

Whitehaven Coal Ltd

ASX:WHC
A$7.65Close 7 Oct 2026 · delayed

Past year: ▲ 6%(6.93 – 9.25 AUD)

Market cap
A$78.49bn
Shares on issue
10.26bn
Story beats
208 since 2007
Last event
19 Aug 2026

Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

7 May 2014production update▲ Good

Narrabri longwall is back at normal production, resolving the April outage. Narrabri FY2014 ROM guidance is lifted to 5.0–5.2Mt (from 4.8–5.0Mt), and group saleable guidance to 10.0–10.2Mt (from 9.8–10.0Mt), still below the original 10.7Mt.

Discuss in chat

29 Apr 2014quarterly activities report● Neutral

March quarter saleable output was 2.234Mt (down 3%); nine-month saleable output was 7.4Mt (up 25%). Maules Creek is 36% complete, on schedule and budget, with all major contracts let at or below budget. Operating lease finance was secured for the initial mining fleet.

Discuss in chat

24 Apr 2014production update▼ BadMajor

FY2014 saleable coal guidance is cut from 10.7Mt to 9.8–10.0Mt after Narrabri's longwall lost floor horizon control on panel three, plus the earlier-disclosed Rocglen geotechnical issues. Narrabri ROM is cut to 4.8–5.0Mt from 5.5Mt; return to mining in 2–3 weeks, costs not material.

Discuss in chat

16 Apr 2014regulatory community update▲ Good

The federal environment department finds the Maules Creek biodiversity offsets package compliant with approval conditions and closes its inquiry into false-information allegations with no further action. Some additional offset land may be needed; the package covers about 13,000ha for 1,600ha cleared.

Discuss in chat

3 Mar 2014production update▲ Good

Narrabri longwall production restarted on panel three after the change-out, on schedule and on budget. First-half ROM was a record 3.29Mt, with December-quarter output above the 6.0Mtpa nameplate. The mine now moves to one change-out a year.

Discuss in chat

28 Feb 2014contract award▲ GoodMajor

Downer EDI is awarded the Maules Creek coal handling plant contract (1600tph), one of the largest parts of the $767m project. About $220m is spent and $333m of major contracts let; first coal is expected March 2015. Contract value is not stated.

Discuss in chat

26 Feb 2014half year report▲ GoodMajor

Half-year to December 2013: revenue $402.2m (up 43%), net loss narrowed 76% to $11.6m, operating EBITDA $50.8m before significant items. Net debt rose to $556.9m (from $471.6m) and gearing to 15%. No interim dividend.

Discuss in chat

26 Feb 2014investor presentation▲ Good

Half-year presentation repeats known results: EBITDA $50.8m, net debt $556.9m, unit costs down 10% to $71.69/t. It says Maules Creek is on schedule for first coal in March 2015.

Discuss in chat

26 Feb 2014half year report▲ Good

Results release repeats the half-year: revenue up 43% to $402.2m, EBITDA $50.8m, average FOB cost $71.69/t. Cash from operations was $78.3m versus a $100.1m outflow a year earlier. $525m of the debt facility remains undrawn.

Discuss in chat

12 Feb 2014other● Neutral

Prudential group's holding in Whitehaven edges down from 6.03% to 5.96% (61.2m shares). A routine substantial holder notice with no company-specific event.

Discuss in chat

23 Jan 2014quarterly activities report▲ Good

December quarter set records: saleable output 2.860Mt (up 44%) and sales 3.156Mt (up 52%). Narrabri ROM was 1.924Mt, above nameplate. Werris Creek expansion finished, the Federal Court upheld Maules Creek, and rail construction began.

Discuss in chat

16 Jan 2014director officer appointment● Neutral

Austen Perrin, the outgoing CFO, resigns as joint company secretary. Tim Burt remains company secretary. This is an administrative step in the CFO handover to Kevin Ball.

Discuss in chat

13 Jan 2014material agreement▲ GoodMajor

Pacific National Coal and Whitehaven sign a new rail haulage agreement from January 2014 to June 2026, replacing the old one. Volume stays at 9.5Mtpa, rising to 11.5Mtpa with 30-tonne axle loads from 2015; per-tonne haulage costs are expected to fall.

Discuss in chat

20 Dec 2013regulatory community update▲ GoodMajor

Federal Court dismisses the NICE challenge to the Maules Creek federal approval, resolving the reserved judgement. Construction is expected to start in early January 2014, with first coal still targeted for Q1 CY2015.

Discuss in chat

2 Dec 2013debt financing● NeutralMajor

Banks approve a change to the A$1.2bn debt facility: the first interest cover test moves from December 2014 to the earlier of December 2015 or the half-year after Maules Creek reaches 3.5Mtpa. No repricing; WHC's 75% share of remaining construction is stated as funded.

Discuss in chat

4 Nov 2013investor presentation● Neutral

AGM address calls FY2013 a tough year with a first loss in several years, and repeats the shift from a 4Mt to a 23Mt producer. Maules Creek cost is put at $67/t FOB, with rail construction awaiting artefact salvage. FY14 budget targets 11Mt.

Discuss in chat

4 Nov 2013agm notice● Neutral

All six AGM resolutions passed, each with at least 98.8% support. These included the remuneration report, rights for the Managing Director, and the elections of Raymond Zage, Tony Haggarty, John Conde and Richard Gazzard.

Discuss in chat

1 Nov 2013production update▲ Good

October railings to Newcastle hit a record of just over 1 million tonnes, and monthly sales a record 1.24Mt. FY2014 production is anticipated at 10.7Mt (100% basis), versus the 11Mt budget target cited at the AGM on 4 November.

Discuss in chat

25 Oct 2013quarterly activities report▲ Good

Record September quarter: managed saleable output 2.349Mt, up 44%, driven by Narrabri's 1.363Mt ROM after the second longwall panel started on 20 July. Narrabri thermal coal now beats the Newcastle specification; Werris Creek expansion to 2.5Mtpa is due by December 2013.

Discuss in chat

24 Oct 2013director officer appointment● NeutralMajor

Kevin Ball is appointed CFO from 16 December 2013, replacing Austen Perrin, who is leaving and will hand over in an orderly way by early 2014. Ball has prior CFO experience in oil and gas and coal.

Discuss in chat

10 Oct 2013contract award▲ GoodMajor

Whitehaven signs Leighton Contractors to build the Maules Creek rail loop, the project's longest lead-time item. Contract value is not stated. Production is still targeted for the first quarter of 2015.

Discuss in chat

2 Oct 2013annual report● Neutral

Cover letter for the 2013 Annual Report being sent to shareholders. Contents repeat the FY2013 results already released: net loss $82.2m, underlying EBITDA $18.6m, cash $110.5m.

Discuss in chat

26 Sept 2013regulatory community update▲ Good

The Federal Court dismisses an injunction sought by the Northern Inland Council for the Environment to stop Maules Creek construction. Judgement on the main challenge, heard 16-19 September, is reserved. Whitehaven now says production starts in the first quarter of 2015.

Discuss in chat

27 Aug 2013annual report▼ BadMajor

FY2013 net loss was $82.2m (underlying loss $60.7m) on underlying EBITDA of $18.6m, after lower prices and the Sunnyside closure. Cash $110.5m, net debt $471.6m. Maules Creek construction awaits indigenous consultation and the Federal Court challenge outcome.

Discuss in chat

27 Aug 2013director officer appointment● NeutralMajor

Raymond Zage, CEO of Noonday Asset Management Asia, joins the board. Noonday and Farallon manage funds that are together Whitehaven's largest shareholder group. Follows Farallon's June purchase of the Tinkler stake.

Discuss in chat

27 Aug 2013resource reserve update▲ GoodMajor

Total resources fall 1% to 3,743.9Mt from 3,787.9Mt, but marketable reserves rise 19.6Mt to 796.2Mt. Merging the Vickery areas adds 53.6Mt of marketable reserves; Narrabri marketable reserves rise 12.6Mt to 212.5Mt.

Discuss in chat

27 Aug 2013annual report▼ Bad

Full-year accounts for FY2013: net loss $82.2m against a $62.5m profit, revenue $622.2m. No final dividend; AGM set for 4 November 2013. Net tangible assets per share fell to $3.12 from $3.38.

Discuss in chat

27 Aug 2013investor presentation● Neutral

Presentation repeats the FY2013 results: net loss $82.2m, underlying EBITDA $18.6m, cash $110.5m, interest-bearing debt $582.0m, gearing 12.5%. Includes the capital spend and the Coalworks acquisition cost of $154.9m. No new announcements in the text provided.

Discuss in chat

20 Aug 2013production update▲ Good

Narrabri thermal coal, now blended with the new CHPP by-pass circuit, tested at over 6,000kcal/kg, meeting the Newcastle benchmark. Narrabri PCI output is forecast at about 650,000t in FY2014. Addresses the earlier below-benchmark quality problem and should lift margins.

Discuss in chat

19 Aug 2013other● Neutral

Second and final in-specie distribution of Orpheus Energy shares paid to former Coalworks shareholders, at 0.0672 Orpheus shares per Coalworks share. Completes the arrangement announced in September 2012.

Discuss in chat