11 Sept 2013other▲ Good

The company names the Oxford Nickel Prospect on the Minigwal belt, on tenement E39/982 (100% owned, over 15 strike-km), based on a review of earlier drilling and geophysics. An airborne EM survey is planned. This is a new target, not a drill result.

Discuss in chat

3 Sept 2013investor presentation● Neutral

September 2013 investor presentation repeats known Cambridge and East Laverton results. It shows 71,981,000 shares and a market cap of about $9m at 12c. No new announcements of substance.

Discuss in chat

28 Aug 2013drilling progress report● Neutral

Most lab assays from the first 2013 Cambridge drilling are in, and a supplementary soil survey has started to pick targets for phase two. The company says preliminary geochemistry supports nickel sulphide potential; no new grades are given, and a detailed review is promised.

Discuss in chat

16 Aug 2013annual report● Neutral

Annual report for the year to 30 June 2013 is released. The chairman's letter restates 2012 Stella Range nickel sulphide results, BHP's May 2013 Stage One election at Project Dragon, and 100%-owned Stella Range coverage of over 30 km. No new results in the extract.

Discuss in chat

7 Aug 2013other● Neutral

Notice that a Kalgoorlie Miner article of 5 August 2013, 'St George Confident in Nickel Find', is on the company website. No new information.

Discuss in chat

5 Aug 2013asset acquisition disposition▲ GoodMajor

Exploration licence E39/1722 was granted, extending 100%-owned coverage of the Stella Range nickel belt by 12 km north of Cambridge. East Laverton now holds over 60 strike-km of the belt. This resolves the pending application; an initial RC drill programme is planned.

Discuss in chat

31 July 2013quarterly activities report● Neutral

June 2013 quarter report restates the Cambridge results, BHP's exercise of its Project Dragon option, and Red Dragon: two RC holes totalling 488m show the rare earth system continues at depth, with assays pending. The company holds 26 granted East Laverton licences plus one application.

Discuss in chat

29 July 2013drilling result▲ GoodMajor

Lab assays from the 2013 Cambridge drilling gave 19m @ 0.56% Ni in CAMRC-010 and 42m @ 0.26% Ni with over 40% MgO at the bottom of CAMRC-011. The company calls it a breakthrough that favours the central body. These are secondary enrichment results, not a sulphide discovery.

Discuss in chat

24 July 2013other● Neutral

Notice that a July 2013 Australia's Paydirt article, 'Project Dragon Ready to Breathe Fire', is on the company website. No new information.

Discuss in chat

29 May 2013farm in farm out completion▲ GoodMajor

BHP Billiton Nickel West exercised its option to start earning into Project Dragon, nominating seven exploration licences. It can earn 51% of the nickel rights by meeting Stage One spend. This resolves the option decision that had been extended to 28 May.

Discuss in chat

29 May 2013drilling progress report● Neutral

First phase of 2013 Cambridge drilling finished: 10 RC holes, 2,295m, with extensive ultramafic and anomalous nickel on field XRF. Results point to the central body for deeper testing. Two holes deferred for groundwater; lab assays due in about four weeks. Two possible gold areas noted.

Discuss in chat

8 May 2013capital raising announcement● Neutral

The 5,000,000 shares at $0.16 from the 30 April placement were allotted on 8 May 2013. Shares on issue are 71,981,000. Administrative completion with the Appendix 3B and cleansing notice.

What it means for a shareholder

5.0m new shares at $0.160 to raise about $800,000. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.

Create a free account to see this worked out for your own holding.

Discuss in chat

30 Apr 2013capital raising announcement● NeutralMajor

St George placed 5,000,000 shares at $0.16 to sophisticated investors, raising $800,000, capped despite oversubscription. Funds extend the 2013 Cambridge drilling. Shares on issue rise to 71,981,000; the price is below the 21c October 2012 placement.

What it means for a shareholder

5.0m new shares at $0.160 to raise about $800,000. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.

Create a free account to see this worked out for your own holding.

Discuss in chat

30 Apr 2013quarterly activities report● Neutral

March 2013 quarter report restates the Cambridge assays (160m @ 0.25% Ni) and Desert Dragon 2m @ 1.08% Ni, notes the 2013 drilling start, and the BHP option extension to 28 May. A gravity survey at Balmoral upgraded the West and South gold prospects and downgraded Balmoral North.

Discuss in chat

29 Apr 2013joint venture update● Neutral

St George granted BHP Billiton Nickel West a one-month extension of the Project Dragon option to 28 May 2013. This pushes out BHP's decision on earning a Stage One interest in the nickel rights.

Discuss in chat

23 Apr 2013drilling spud▲ GoodMajor

The 2013 drilling campaign started on 23 April, with 14 RC holes planned, each to 250m, beginning at Cambridge South on strike from earlier nickel sulphide intersections, then moving north. This follows the rig mobilisation flagged on 19 April; no results yet.

Discuss in chat

19 Apr 2013drilling scheduled▲ Good

Preparation is underway for the 2013 deep RC drilling at 100%-owned Cambridge, with 250m design holes and a rig arriving early the following week. Targets include new Cambridge South and North prospects on E39/1667 and E39/1666. Final targets are still to be announced.

Discuss in chat

11 Apr 2013drilling result▲ GoodMajor

Re-analysis found visible nickel sulphides in Desert Dragon hole DDNRC-002, with lab assay of 2m @ 1.08% Ni, the highest-grade nickel at East Laverton so far. Cambridge MgO is higher than first inferred. 2013 drilling is planned for late April or early May.

Discuss in chat

12 Mar 2013half year report● Neutral

Half-year to 31 December 2012: loss of $327,954 after $777,801 exploration spend written off, $358,086 administration costs and a $794,984 R&D tax refund. Operations text repeats known Cambridge and Project Dragon results.

Discuss in chat

31 Jan 2013quarterly activities report● Neutral

December 2012 quarter: Cambridge drilling was suspended by storms after two partial holes, with restart hoped for late Q1 2013. Company applied for tenement E39/1722, extending the Stella Range belt about 12 km. No field work at Project Dragon. Cash figures are not in the readable text.

Discuss in chat

30 Jan 2013drilling result▲ GoodMajor

Lab assays confirm Cambridge holes hit long nickel-bearing ultramafic, e.g. 160m @ 0.25% Ni (CAMRC-001) and 150m @ 0.22% Ni (CAMRC-002). The company says this supports nickel sulphide potential at depth. Holes were cut short; no sulphide discovery is reported.

Discuss in chat

22 Jan 2013drilling scheduled▲ Good

Infill soil sampling confirmed strongly anomalous rare earths over a 2km x 1.5km priority area at Red Dragon. Four 250m RC holes are planned for Q2 2013, with a $122,000 WA Government grant towards drilling costs.

Discuss in chat

15 Jan 2013other▲ Good

St George received a $796,129.62 cash R&D tax incentive payment for 2011/12, the rebate expected earlier. It comprises $794,984.40 rebate plus $1,145.22 interest. This resolves the open rebate thread.

Discuss in chat

17 Dec 2012drilling result● Neutral

Preliminary XRF on the two Cambridge holes shows long ultramafic intervals, best 14m @ 0.503% Ni and 8m @ 0.61% Ni. The company calls this likely shallow secondary enrichment, and says the holes only tested an upper, lower-MgO unit. Lab assays are due late January 2013.

Discuss in chat

26 Nov 2012drilling progress report● Neutral

Gold holes at Athena and Desert Dragon finished, showing strong alteration. Preliminary XRF gave 7m @ 0.53% Ni at Desert Dragon. Cambridge hole 1 finished (168m) and hole 2 stopped at 150m; drilling suspended by heavy rain. Assays still pending.

Discuss in chat

20 Nov 2012drilling scheduled▲ Good

Final EM and magnetic modelling at Cambridge shows the ultramafic body keeps its original orientation, implying a larger prospective basal contact. Three priority holes are set, two on the newly recognised western margin, with drilling due about 22 November 2012.

Discuss in chat

19 Nov 2012other● Neutral

A company-commissioned initiating research report by Independent Investment Research is available on the website. It is based on public information and is not company guidance. No new information.

Discuss in chat

12 Nov 2012drilling spud▲ Good

The 2012 RC drilling programme began at East Laverton, starting with gold targets at Desert Dragon and Athena, then Cambridge nickel. Preliminary EM results show several nickel drill targets at Cambridge; final targets are due within the week.

Discuss in chat

8 Nov 2012investor presentation● Neutral

New investor presentation restating known facts: Cambridge nickel, BHP farm-in terms, Project Dragon results and gold prospects. 2012 RC drilling is due to start 12 November at Cambridge, Desert Dragon and Athena. No new results.

Discuss in chat

31 Oct 2012quarterly activities report● Neutral

September 2012 quarter: restates the Cambridge nickel target, the new E39/1666 and E39/1667 tenements, and the Project Dragon RC results (first primary nickel sulphides at East Laverton, 20m @ 0.39% Ni in DRAC35). Cambridge EM survey fieldwork is complete, with modelling awaited. No cash figures are in the readable text.

Discuss in chat