Each one in plain English, with the numbers worked through for a shareholder.
3 June 2015drilling spud▲ GoodMajor
The 2015 drilling campaign has started at East Laverton: over 2,500m planned at 7+ targets over 6-7 weeks. Cambridge is drilled first (500m hole), then Aphrodite 4; Dragon 9 is last. Drilling begins the campaign flagged since April.
1 June 2015capital raising announcement● NeutralMajor
Placement of 15,000,000 shares at $0.07 raises $1,050,000, led by Alto Capital, with one free option per three shares. Funds go to East Laverton drilling. A further 5,405,962 shares may be placed. First raising since the Sep/Oct 2014 placement at 9c.
What it means for a shareholder
15.0m new shares at $0.070 to raise about $1.1m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
DDH1 Drilling's rig is due on site 2 June 2015 for over 2,500m of diamond drilling at least seven targets over 6-7 weeks. Planned depths are mostly 220-300m, deepest 500m. Scheduling update only; no results.
Drill campaign expanded to at least seven targets, about 2,100m of diamond drilling over 6-7 weeks from the last week of May 2015. New targets include a basal contact test below DDNRC002 (2m @ 1.08% Ni) and three conductors near DRAC35. Targets, not results.
RIU Sydney presentation repeats known points: 100% of East Laverton, the 2015 technical review, 111,831,806 shares and market cap about $8m at 7c. No new results.
Dragon 9 (443ms, 4900 Siemens) is picked as the first drill target, with Dragon 8 (190ms, 3500 Siemens) and Aphrodite 4 also to be tested. Drilling is due in the last week of May 2015. Targets only, not results; Dragon 9 was Target 5 in March.
New strong EM conductor, Aphrodite 4 (176ms, 2947 Siemens), selected for immediate drilling at a structural embayment. DDH1 Drilling has been engaged, with drilling due to start by end of April 2015. Target only, not a result.
Restates BHP Nickel West's 2012 Project Dragon drill results (35 holes, 8,560m) under the 2012 JORC Code. Administrative reporting update; no new drilling or change in results.
Presentation repeats known facts: 111,831,806 shares, 11,183,181 listed options, market cap about $8m at 7c, and the technical review's conclusions. No new results.
Two strong EM conductors (Targets 4 and 5) at Desert Dragon Central are recommended by Dr Hronsky for drilling. Target 5 has a 443ms time constant and 4900 Siemens conductance. Drilling is due to start early April 2015. Targets only, not a result.
Three drill targets identified at Desert Dragon North, following hole DDNRC002's 2m @ 1.08% Ni massive sulphide stringers from 55m. Strong EM conductors will be tested when drilling resumes in March/April 2015. Targets, not new drilling results.
Half-year to 31 December 2014: loss of $1,596,174 after $1,974,029 exploration spend written off, $436,313 administration and a $797,715 R&D tax refund. Repeats Windsor results and the Phase 2 drilling of 21 holes for 4,890m.
Technical review led by Dr Jon Hronsky backs East Laverton as a potential new nickel camp, naming an 18km stretch of the Stella Range belt (Desert Dragon to Windsor) as most prospective; possibly as little as 5% of the basal contact has been drilled. Drilling restarts in March.
Phase 2 assays confirm nickel sulphides at Windsor: WINRC007 90m @ 0.20% Ni from 227m (incl. 1m @ 0.75%), WINRC005 147m @ 0.25% Ni. Four of six holes hit sulphides in a channel over 4km long; drilling restarts March 2015. Resolves the pending Windsor assays.
MLEM survey found new Category 1 EM conductors: four at Desert Dragon North and two at Aphrodite. Windsor assays are due next week, a technical review with Dr Jon Hronsky is underway, and drilling is planned to resume in late February 2015.
The new bonus options began trading on ASX today under code SGQOA. This completes the bonus issue announced in December; no new information on exploration.
Confirms the bonus option prospectus, dated 17 December 2014, has been sent to shareholders. One option per ten shares, 20c exercise price, expiring 30 June 2017. Administrative confirmation only.
WINRC007 extension to 380m and WINRC008 (300m) are drilled, with samples sent to the lab without site XRF. WINRC009 is at 125m, heading to 300m. Downhole EM surveys are planned for early January. No assay results yet.
Drilling has restarted at Windsor, with WINRC007 being extended to 380m and WINRC008 and WINRC009 planned. New EM conductors were identified at Cambridge North and Aphrodite, with modelling to define targets for 2015 drilling.
Prospectus lodged for the bonus option issue: one 20c option per ten shares, expiring 30 June 2017, issued 16 January 2015 for nil consideration. No funds are raised. Administrative document following the 2 December announcement.
Letter to optionholders explaining they only join the bonus issue if they exercise options and have shares registered by 5 January 2015. Notes about 13,162,706 options on issue after the bonus. Administrative notice.
Drilling resumes at Windsor that week. WINRC007 will be deepened from 300m to 380m to test the basal contact, where massive sulphides are more likely, and more holes will follow on the same section. The 60m @ 0.31% Ni result is interim XRF.
Company will give shareholders a free bonus option for every ten shares held at 5 January 2015, 11,183,181 options in total. Each is exercisable at 20c and expires 30 June 2017. No money is raised; trading expected late January.
48,508,000 listed 20c options and 750,000 unlisted 25c options expired unexercised on 28 November 2014, as the shares were trading below the exercise price. No funds were raised from them.
Windsor hole WINRC007 intersected 60m @ 0.31% Ni from 238m and 18m @ 0.33% Ni from 179m on interim XRF, including 1m @ 0.76% Ni, the highest at Windsor. Sulphides are disseminated; the channel exceeds 300m. Desert Dragon South wet samples await lab assays.
Drilling of the Dragon 3 EM conductor, expected to be a more central part of the VMS system than DDD011 (16m @ 0.45% Zn), starts next week. Gravity and MLEM surveys also found two new conductors north-west still to be tested. Interim XRF only.
Downhole EM on WINRC005 found an off-hole conductor near the Windsor disseminated nickel sulphides. The company says a possible source is matrix or massive sulphide. Hole WINRC006 is scheduled for the following week. A target only, not yet drilled.