Each one in plain English, with the numbers worked through for a shareholder.
19 July 2018other▲ Good
Test work produced 99.9995% purity graphite from Malingunde flake using a lower-temperature thermal process, with impurities under 5 ppm. Company calls it a step toward battery and other high-value markets. Spherical graphite results promised in coming weeks. Lab-scale only.
Updated Malingunde resource: 45.7Mt at 7.2% TGC (saprolite plus saprock), 81% Measured and Indicated, including a high-grade 14.5Mt at 9.7%. Up from the 2017 saprolite 28.8Mt; the high-grade tonnage rise comes mainly from adding saprock. It becomes the PFS focus.
Testwork validates a scrubber-based flowsheet at Malingunde, with ~89% weighted recovery and 96-98% TGC concentrates. A small pebble crusher could let harder saprock be added as plant feed beyond the 2017 scoping study. PFS now targeted for July; resource due early June.
March 2018 quarterly report: PFS progressing (process design done, variability testing started) and still due mid-2018. Recaps Msinja and the new 3,993km2 ground. Resource update now expected toward end of May. Mostly repeats earlier releases.
Final 71 of 209 aircore holes at Malingunde confirm wide, high-grade graphite, e.g. 21m at 21.7% TGC and 26m at 17.2% TGC. One zone flattens and stays open to the west, a possible tonnage addition. Updated resource still due late Q2 2018.
Drilling found a new zone of high-grade saprolite graphite at Msinja, 1.5km south-east of Malingunde, over ~1km of strike and open to the south-east, e.g. 15m at 15.1% TGC. Also a new 1,896km2 licence EPL0492 was granted, lifting holdings to 3,993km2.
Half-year accounts to 31 December 2017. Directors' report restates the PFS start, drilling, the transport MoU and the A$6.5M placement. Financial figures are not visible in the excerpt.
Second batch of 68 infill holes shows wide, high-grade graphite, e.g. 18m at 19.3% TGC and 16m at 14.7% TGC, with up to ~200m surface width. 106 holes still pending; updated resource expected Q2 2018. Continues January's strong results.
PFS update: DRA Global chosen as project engineer, pit optimisations done, and scrubber and variability testwork under way. PFS stays on track for mid-2018. Sales trip found the highest value is in large and jumbo flake for industrial uses; battery qualification continues.
February 2018 company presentation repeating Malingunde's known resource (28.8Mt at 7.1% TGC), scoping study economics (US$29M capex, US$301/t opex) and transport MoU. Says resource update expected Q2 2018. No new information in the excerpt.
December 2017 quarterly report recapping the PFS start, the CEAR transport MoU, first drill results, the completed A$6.5M placement and the new ground. Targets PFS completion mid-2018. Mostly repeats earlier releases; no new results in the excerpt.
First 36 of 210 infill aircore holes at Malingunde returned high grades, e.g. 23m at 21.2% TGC and 36m at 11.1% TGC. Results feed an updated resource due early Q2 2018. Also raises the Managing Director's salary to $215,000 from 1 Jan 2018.
19 Dec 2017capital raising announcement▲ GoodMajor
Second tranche of the placement completed: 20.1M shares at $0.11 for $2.2M gross, after shareholder approval on 8 December. This completes the A$6.5M raise to fund the Malingunde PFS and DFS. Includes a routine 708A notice for 1,747,345 shares.
What it means for a shareholder
20.1m new shares at $0.110 to raise about $2.2m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
PFS progress update: 210 aircore holes (6,212m) completed, first assays expected early in the new year. Orelogy appointed for mining, ALS for scrubbing metallurgy, SLR for infrastructure, AECOM for social work; project engineer to be chosen by year end.
4 Dec 2017asset acquisition disposition▲ GoodMajor
Granted 229km2 of extra ground on EPL0372 along strike south-east of Malingunde, extending the Malingunde Trend by ~25km. After relinquishing non-prospective areas, the total ground package is now 2,740km2, down from ~3,788km2. Company says it holds ~80% of prospective area.
The 5,000m infill aircore program at Malingunde for the PFS mine plan is finished. One rig has moved to three other saprolite targets, including Thete and Chiziro, about 40km away. Assays are expected in Q1 2018. A second rig has started groundwater drilling.
November 2017 Perth conference presentation repeating Malingunde's resource, scoping study economics (US$29M capex, US$301/t opex) and the Vale/Mitsui transport MoU. No new results in the excerpt.
Pre-feasibility study for Malingunde has started, targeted for completion by mid-2018. Company says it is fully funded for PFS and DFS after the A$6.5M raise. A ~6,000m infill and regional drilling program starts shortly. Follows the June scoping study.
First tranche of the placement completed: 39.0M shares at A$0.11 raising A$4.3M. The second tranche of 20.1M shares (A$2.2M, including 2M for the Chairman) awaits shareholder approval. Completes the first part of the raising announced on 25 October.
What it means for a shareholder
39.0m new shares at A$0.110 to raise about A$4.3m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
September 2017 quarterly report summarising the transport MoU, Malawi government support, flotation and spheroidisation results, and the A$6.5M placement. Says pre-feasibility study start and infill drilling are coming. Mostly repeats earlier releases; no cash figure visible in the excerpt.
25 Oct 2017capital raising announcement● NeutralMajor
Raising A$6.5M through a placement of 59.1M shares at A$0.11, a 15% discount, to fund Malingunde pre-feasibility and definitive feasibility studies. Tranche 1 is A$4.3M; tranche 2 (A$2.2M) needs shareholder approval. Also 12M advisor options at $0.18. Total dilution 15.2% for tranche 1 capacity.
What it means for a shareholder
59.1m new shares at A$0.110 to raise about A$6.5m. Shares on issue before the raise aren't in the record, so the dilution can't be worked out.
Non-binding MoU with Central East African Railways (Vale and Mitsui-linked) for rail and Nacala port services for up to 100,000tpa over up to 20 years. Backs the scoping study's ~US$65/t logistics cost. A binding agreement is targeted before 30 June 2018.
2017 annual report for the year to 30 June 2017. Restates the Malingunde saprolite resource (28.8Mt at 7.1% TGC) and the scoping study (44,000t a year, US$29M capex, US$301/t opex). Excerpt shows no new results; financial statements not visible in the text.
Appendix 4G governance checklist for the year to 30 June 2017, lodged with the annual report. Points to the corporate governance statement on the company website. No financial or project information.
Malawi Government, including the Minister of Mining, has offered support and resources to progress Malingunde to development after Sovereign presented the June scoping study. Release also notes the Nacala Logistics Corridor opened in August 2017. Supportive, but no permit or approval is announced.
New flotation test F23 with longer attritioning gave concentrates of about 98% carbon across all size fractions (98.2% overall by double loss-on-ignition). Finer flake than test F13, suited to battery markets. Lab-scale result supporting the dual-market strategy.
First spheroidisation tests on Malingunde concentrate produced spherical graphite meeting most Li-ion anode benchmarks, e.g. purity above 99.95%, though yield of 21-51% and some size-distribution results were outside or near the benchmark. Company plans more battery testing; traditional markets remain the primary focus.
June 2017 quarterly report restating the scoping study: 44,000t a year over 17 years, US$29M capex, US$301/t opex. Notes study was managed by Amec Foster Wheeler and the production target was about 8.0Mt at 10.0% TGC. Mostly repeats the 20 June release.
Malingunde scoping study (±35% accuracy): about 44,000t a year of concentrate over a 17-year mine life, US$29M capex including 35% contingency, and US$301/t operating cost FOB Nacala. Payback under 2 years. Additional funding will likely be needed. Delivers the study flagged since 2016.