15 Apr 2008contract award▲ GoodMajor
Contact Energy (Origin 51.36%) signed contracts with GE and United Group (NZ) for two 100MW gas peaking units at Stratford, costing about $250m. In service is expected before winter 2010, alongside the Ahuroa gas storage facility.
Origin lodges its 2007 Sustainability Report for shareholders who elected to receive it. It covers the year to 30 June 2007 and is not a financial or operating update.
NZOG reports attempts to free the stuck pipe in Kupe KS-7 were abandoned by 9 April. The reservoir section will be sidetracked and redrilled. Mid-2009 completion is still stated. Duplicates Origin's release.
Origin says efforts to recover the stuck pipe in Kupe KS-7 are abandoned and the reservoir section will be sidetracked and redrilled. This resolves the 2 April fishing attempt, but adds work to the campaign.
Beach weekly report: in Santos-operated Cooper wells, Cook-10 (Origin 25%) was plugged and abandoned at 2,042m. Mudera-12 (13.19%) is now cased as a gas producer after strong gas shows, and Coonatie-13 is suspended as a future gas producer.
Geodynamics says Jolokia 1 is progressing well, with 18 5/8 inch casing cemented and the 16 inch section now at 1,862m. Target depth is 4,250m. Origin holds 30% of the joint venture.
Origin reports pipe stuck at 3,454m in Kupe KS-7's reservoir section after the Farewell top was reached with gas shows; a fishing assembly is being run. The third and last Kupe development well is therefore delayed.
NZOG reports Kupe KS-7 hit the Farewell reservoir top on 29 March with gas shows, but pipe stuck at 3,454m in the 8-1/2 inch section; fishing is under way. Mid-2009 completion unchanged. Duplicates Origin's release.
Beach weekly report: in Santos-operated Cooper wells, Fly Lake-24 (Origin 13.19%) is cased as a gas producer with 27m of gas pay, and McKinlay-8 was unsuccessful. Coonatie-13 (Origin 10.54%) reached 3,091m. Mudera-12 is still under rig repairs.
Origin forwards Contact Energy's (51.36% owned) investor presentation on strategy: Te Mihi 225MW geothermal from late 2008, 550MW wind from 2011, up to 300MW of gas peakers, and Swift gas storage in 2010. Largely repeats known plans.
Geodynamics says the open flow test is complete, apparently within budget, but Origin has yet to review costs. Origin's extra $9.6m contribution is decided by about May. A further test is set for 21 April and a six-week closed loop test from mid May.
QGC weekly report: Matilda-John #1 (Origin CSG 40.625%) finished at 804.6m with 32.8m of coal, was released 29 March and is suspended for possible conversion to a monitoring well. Other wells listed are QGC-only.
The Kupe JV (Origin 50% operator) will drill the Momoho exploration well from May, 6km south of the Kupe field, to about 3,150m, before the Ensco 107 rig is released. A discovery could possibly connect to the Kupe platform.
Origin set the dividend reinvestment price at $8.92 per share for the 12c interim dividend payable 4 April 2008. No discount applies, so reinvesting shareholders receive shares at the 10-day average price after the record date.
NZOG reports Kupe KS-8's 5 inch liner is set and cemented and the well suspended. The rig moves to KS-7 to drill its reservoir section. Mid-2009 completion unchanged. Duplicates Origin's release.
Origin reports Kupe KS-8 has its 5 inch liner set and cemented and is suspended; the rig moves to KS-7. Two of three development wells now have their reservoir sections drilled.
QGC weekly report: Jen #2 (Origin 31.25%) reached 625m with 37.8m coal and awaits a workover rig. Matilda-John #1 (Origin 40.625%) reached 804.6m with 32.8m coal and is logging. Woleebee Creek wells are QGC-only.
Beach weekly report: Santos-operated Cook-11 (Origin 25%) cased as a future oil producer with a 24m gross oil column, and Squalo-1 (13.19%) with 4.5m oil pay. Mudera-12 still awaits top drive parts.
Origin forwards Contact Energy's (Origin 51.36%) half-year report to 31 December 2007. It repeats the previously released EBITDAF of NZ$281.9m and an 11.0c interim dividend; nothing materially new on the text shown.
Origin reports Kupe KS-8 hit the Farewell reservoir top with elevated gas shows, finished coring and reached its 3,834m planned depth. Logs and a 5 inch liner follow. Second Kupe development well nearing completion.
Origin raised $1.54bn, including $420m of oversubscriptions, from syndicating the 3-year credit facility announced on 11 February. Margin is 65 basis points over base rate; it is senior unsecured, A$1.32bn plus a US$200m tranche, to fund growth capex.
NZOG reports Kupe KS-8 intersected the Farewell reservoir top with elevated gas shows and reached 3,834m. Logging then a 5 inch liner come next. Mid-2009 completion unchanged. Duplicates Origin's release.
Beach weekly report: Santos-operated Cooper wells Cook-11 and Squalo-1 (Origin 25% and 13.19% respectively per the table) are in progress, with Fly Lake-24 and Mudera-12 also listed. Mudera-12 is still awaiting top drive repair parts.
Geodynamics spudded Jolokia 1, targeting 4,250m in granites about 10°C hotter than the Habanero wells. Origin holds 30% of the Innamincka JV, from the December 2007 geothermal deal. Fortnightly updates are promised.
Origin reports Kupe South 6 reached its planned 3,385m, with logs completed and the 5 inch liner cemented, and the well suspended. First of three development wells is finished; KS-8's 8-1/2 inch section is starting.
NZOG reports Kupe KS-6 reached its planned 3,385m, was logged, had its 5 inch liner set and cemented, and was suspended. Rig now drilling out KS-8's shoe-track. Mid-2009 completion unchanged. Duplicates Origin's release.
Beach weekly report: Santos-operated Mudlalee-5 (Origin 13.19%) was plugged and abandoned after a water-heavy test. Coonatie-9 (10.54%) was cased as a future gas producer. Cook-12 was a success, and Murrippi-1 is not an Origin well.
QGC weekly report: Bellevue #15 (Origin 29.375%) reached 527m with 33.9m coal and awaits a workover rig. Matilda-John #1 (Origin 40.625%) is coring at 504.7m. Teviot #1 and Woleebee Creek #4 are QGC-only wells.
Presentation by Grant King and Frank Calabria to investors in Asia and the UK, restating Origin's integrated generator-retailer strategy and 10-15% average EPS growth objective. Only the opening is readable; no new figures are evident.
NZOG reports Kupe South 6 (Origin 50% operator) drilled its 8-1/2 inch section to 3,313m with a hydrocarbon column in the Farewell Formation, as anticipated. Planned depth is 3,385m. Mid-2009 completion unchanged. Duplicates Origin's release.