30 Mar 2012drilling progress report● Neutral
Triceratops-2 reached 5,971 feet with persistent mud losses of 5-40 barrels an hour in the carbonate; drill-stem test equipment was delayed, so InterOil chose to keep drilling toward about 7,546 feet and log the well first, deferring the flow test. The same release extended the Mitsui condensate-plant deadline to 30 June 2012 and Energy World's to 31 December 2012.